2026 LEPC Meeting November 17th, 2026 at 4:00 p.m. to be held in the EOC. Virtual link available in the agenda notice.
Bayfield County · Bayfield County · meeting of Nov 17, 2026 · Agendas
Open the original document More from Bayfield County
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
Bayfield County LEPC
Meeting Agenda
November 17th, 2026
4:00 p.m.
Meeting Facilitator: Meagan Quaderer
Microsoft Teams meeting
Join: https://teams.microsoft.com/meet/274197789379808?p=BE0YYLNxTVDKvNvHob
Meeting ID: 274 197 789 379 808
Passcode: nX2W8Fj6
Dial in by phone
+1 715-318-2087,,248277410# United States, Eau Claire
Find a local number
Phone conference ID: 248 277 410#
For organizers: Meeting options | Reset dial-in PIN
I. Call to order
II. Roll call
III. Approval of previous meeting minutes
IV. Public Comment, 3 minutes per person, up to 15 minutes total
V. New & Open issues
a) Committee Elections
b) Review and update the LEPC Membership list.
c) TC Energy planning facility offsite plan review.
d) Iron River Fish Hatchery offsite plan review.
e) Annual Review of Bylaws.
f) Review of Designation of a Compliance Inspector.
g) Hazard Mitigation Plan process for 2027
h) Other items for discussion as identified by the membership.
VI. Adjournment
Bayfield County LEPC
Meeting Minutes
November 12th, 2025
I. Call to order
Victorson called to order the regular meeting of the Bayfield County Local Emergency
Planning Committee held virtually at 03:36 p.m. on Wednesday, November 12th, 2025.
II. Roll call
• Jan Victorson – Citizen Committee Member
• Marian Schraufnagel – Village of Mason Clerk
• Meagan Quaderer – Bayfield County Emergency Management Director
• Ryan Matthews – Emergency Management Clerk
• Charly Ray – Bayfield County Board Member
• Matt Spangler – Ashland Fire Captain and HazMat Coordinator
• Stuart Matthias – Ashland Fire Chief
• Tara Klevgard – Tamarack Health
• Jack Hoiby – Grand View Fire
• Trent Meske – TC Energy
III. Approval of minutes from last meeting
Charly Ray made a motion to approve the meeting minutes as read, second by Jack Hoiby.
Motion carried.
IV. New business
a) Officer election for the LEPC committee.
Jan Victorson was nominated for Chairperson by Meagan Quaderer, second by
Charly Ray. Motion carried.
Charly Ray was nominated for Vice Chair by Meagan Quaderer, seconded by Jack
Hoiby. Motion carried.
b) Review and update for the LEPC Membership list:
Recommendations:
• Mary Motiff, City of Washburn Mayor, to fill section IV, to replace City of Washburn
Administrator.
• Greg Ledin, City of Washburn Public Works Director, to replace Tom Kovochevich in
category II.
• Tom Stankard, Ashland Daily Press, to fill the requirement for section III.
• Mark Manning, Tamarack Health to replace Lance Ritola of Tamarack Health in section
II.
• Tom Croteau, Bayfield County Human Services Director, to replace Carrie Linder, for
section IV.
Charly Ray made a motion to approve changes to the LEPC Membership List, seconded
by Jack Hoiby. Motion carried.
c) Review of the TC Energy Offsite Plan: Trent Meske provided an overview of the TC
Energy compressor station's chemical inventory and emergency response plan,
with Meagan and Stuart clarifying plan access and activation procedures, and the
committee discussed the possibility of a future onsite meeting. Trent explained
that the primary chemical of concern at the TC Energy site is sulfuric acid in sealed
backup batteries, which qualifies the facility as a Tier 2 reporting site, and
confirmed no expected changes for 2025.
d) Review of Iron River Fish Hatchery Offsite Plan: Brandon Keesler advised Meagan
prior to the meeting that the hatchery was misclassified as a reporting facility.
They are working to amend their report to return to being a reporting facility.
e) Bylaws: LEPC conducted a thorough review of the LAPC bylaws, discussing updates
such as changing 'coordinator' to 'director', removing outdated references to the
Citizen Core Council, and addressing formatting and role definitions, with Ryan
assisting in documenting changes. The Bylaws state that Bayfield County LEPC will
utilize the State of Wisconsin Compliance Director.
V. Adjournment
Victorson adjourn the meeting at 4:48 p.m., second by Ray. Motion Carried.
Minutes submitted by: Meagan Quaderer
LEPC BYLAWS Page 1 November 17th, 2026
STATEMENT of PURPOSE and BYLAWS
of the
BAYFIELD COUNTY
LOCAL EMERGENCY PLANNING COMMITTEE
ARTICLE I
NAME
The name of this Committee shall be the Bayfield County Local Emergency Planning Committee,
abbreviated as LEPC.
ARTICLE II
PURPOSE
Section 1.
The Bayfield County Local Emergency Planning Committee - LEPC - shall serve the local planning
district of Bayfield County. This planning district was established by Wisconsin Emergency
Management as required by the Superfund Amendments and Reauthorization A ct - SARA Title III :
Emergency Planning and Community Right to Know Act - EPCRA. The Bayfield County LEPC shall
also serve as the Bayfield County Citizen Corps Council.
Section 2.
The purpose of the LEPC shall be to:
A. Provide a forum wherein representatives of local government, community leaders, emergency
response agencies, long term response agencies, reporting and planning facilities, the media,
and other concerned parties may cooperatively examine and discuss the political, financial,
environmental, and personal safety issues of emergency planning activities.
B. Conduct fact finding, planning, exercising, evaluating, and coordinating activities for the
development of a comprehensive area -wide response system to hazardous materials
emergencies.
C. Fulfill requirements set out in the Emergency Community and Right to Know Act (EPCRA),
Wisconsin State Statutes 323.60 and administrative rules promulgated by Wisconsin
Emergency Management.
D. Provide for ongoing development of the countywide Pre-Disaster Mitigation Plan.
E. Support countywide activities related to the Northwest Household Hazardous Materials
Clean Sweep Program.
F. Identify local response needs and resources.
G. Serve as an information resource for residents of Bayfield County regarding all-hazards
emergency preparedness, mitigation, response, and recovery.
H. Provide information to citizens to improve personal, family and community preparedness
I. Establish liaison, maintain communication, and exchange information with other LEPC s and
Citizen Corps Councils in the Northwest WEM region
LEPC BYLAWS Page 2 November 17th, 2026
J. Advise the Bayfield County Board and local governmental agencies of the LEPC's activities.
ARTICLE III
MEMBERSHIP
Section 1.
The membership of the Local Emergency Planning Committee - LEPC - shall be as required in the
SARA Title III: Emergency Planning and Community Right -to-Know Act (EPCRA), Subtitle A, Section
301, as follows:
Each committee shall include, at a minimum, representatives from each of the following groups or
organizations:
(1) Elected state and local officials;
(2) Law enforcement, Emergency Management , firefighting, first aid, health, local
environmental, hospital, and transportation personnel;
(3) Broadcast and print media;
(4) Community groups;
(5) Owners and operators of facilities subject to the requirements of this subtitle.
Section 2.
Membership of the LEPC is recommended to Wisconsin Emergency Management (WEM) by the
Bayfield County Board of Supervisors. Appointments are made by WEM ba sed on those
recommendations. Interested persons may petition WEM to modify the membership of the LEPC.
Section 3.
Wisconsin Emergency Management has determined that the County Emergency Management
Coordinator will be a member of the LEPC.
Section 4.
Each member of the LEPC appointed may select an alternate to attend meetings in his or her
absence. The alternate may participate in discussions but will not have voting privileges.
ARTICLE IV
POSITIONS
Subject to EPCRA, Section 301 and Section 303, the following positions shall be appointed by the
Local Emergency Planning Committee - LEPC.
Section 1.
CHAIRPERSON: The Chairperson of the LEPC shall be a member of the Committee, elected by the
membership of the LEPC for a term of two years. The principal duties of the Chairperson shall
include: preside over all meetings of the LEPC; appoint subcommittee chairs as required; approve
grant documentation as required; and provide general supervision of the Committee.
Section 2.
COORDINATOR FOR INFORMATION: The Coordinator for Information shall be a member of the
LEPC, designated by the Committee. The Coordinator for Information will implement procedures for
LEPC BYLAWS Page 3 November 17th, 2026
receiving and processing requests from the public for information, including information as provided
for under EPCRA, Section 312 and 324. The LEPC may designate Deputy Coordinators for
Information to serve in the absence of the primary designee.
COMMUNITY EMERGENCY MANAGEMENT DIRECTOR: The Community Emergency Management
Director shall be a member of the LEPC, designated by the Committee. The Community Emergency
Coordinator will undertake those duties assigned by the LEPC including making determinations
necessary to implement the emergency plan. The LEPC may designate Deputy Community
Emergency Management Directors to serve in the absence of the primary designee. The Community
Emergency Coordinator may serve as the Coordinator for Information.
In order to assure the continuity of operations and ongoing documentation of LEPC
activities, the following positions have been established. These positions are not
required by EPCRA.
Section 3.
CHAIRPERSON: The Chairperson of the LEPC shall be a member of the Committee, elected by the
membership of the LEPC for a term of two years. The principal duties of the Chairperson shall be to
facilitate meetings and approve and sign LEPC & EPCRA forms.
Section 4.
VICE CHAIRPERSON: The Vice Chairperson of the LEPC shall be a member of the Committee,
elected by the membership of the LEPC for a term of two years. The principal duties of the Vice
Chairperson shall be to discharge the duties of the Chairperson in the event of his or her absence.
Section 5.
SECRETARY: The Secretary of the LEPC shall be a member of the Committee, appointed by the
Chairperson. The principal duties of the Secretary include keeping minutes of LEPC business
conducted; assure proper minutes of all LEPC meetings are kept; and forward minutes to the
Coordinator for Information for distribution as required.
Section 6.
COMPLIANCE DIRECTOR: The Bayfield County LEPC will utilize the State of Wisconsin Compliance
Director.
Section 7.
The election or appointment of a position replacement when an individual is unable or unwilling to
serve will take place at the earliest regular meeting of the LEPC following notification of said
individual's inability to serve.
ARTICLE V
MEETINGS
Section 1.
REGULAR MEETINGS: Regular meetings of the LEPC shall be held at a minimum of once a year.
Notice of these meetings shall be sent to The Daily Press. The Bayfield County website may also be
considered a posting source for information.
LEPC BYLAWS Page 4 November 17th, 2026
Section 2.
LOCATION: The LEPC has established a normal meeting location of the EOC (Emergency
Operations Center) in the Bayfield County Courthouse Annex, Washburn. Meetings of the LEPC will
be held in the county with the exception of joint meetings held between the Bayfield County LEPC and
other LEPCs which are required for coordination of activities or for the conduct of jointly related
business. Public notice of meetings outside the normal meeting location will be given at least 24 hours
in advance of the meeting. Remote meeting attendance and participation will be recognized.
Section 3.
SPECIAL MEETINGS: In addition to remote meetings, special meetings of the LEPC may be held at
locations throughout the county to discuss the emergency plan, to facilitate public input, or to access
facility specific information. Public notice of special meetings outside the normal meeting locat ion will
be given at least 24 hours in advance of the meeting.
Section 4.
EMERGENCY MEETINGS: The Chairperson or designee may call an emergency meeting of the
LEPC as soon as possible when emergency conditions are occurring or are imminent. All reasonable
attempts shall be made to notify all Committee members and the public of the meeting. The conduct
of business at such meetings will be limited to those items required by the emergency conditions
present.
Section 5.
AGENDA: Items to be included on the agenda will be submitted to the Coordinator for Information at
least five working days prior to a regular meeting of the LEPC. The agenda will be compiled and
mailed to committee members, local media representatives, and others who request copies at least
72 hours prior to the Committee meeting. Emergency agenda items may be added during the
meeting at the discretion of the Chairperson.
Section 6.
PUBLIC INPUT: The LEPC will provide an item on every agenda that facilitates receiving publi c
comment and input. The LEPC may limit public comments to a certain time frame as well as change
those time frames with a majority roll call of the Committee.
Section 7.
QUORUM: A quorum will consist of one-third of the approved membership of the LEPC, except in the
case of an emergency meeting when the members present will constitute a quorum.
Section 8.
VOTING: A majority vote of members present where a quorum exists will be needed for action on
motions.
Section 9.
MINUTES OF MEETINGS: Minutes o f all meetings of the LEPC and subcommittees will be
distributed to Committee members, County Board Chair, County Clerk, County Administrator, the
Northwest regional office of Wisconsin Emergency Management, and others who request them
through the Coordinator for Information.
LEPC BYLAWS Page 5 November 17th, 2026
ARTICLE VI
COMMITTEES
Section 1.
The Local Emergency Planning Committee - LEPC - shall designate such subcommittees as it may
find necessary to carry out the purpose of the LEPC. The members of these committees shall be
appointed by the Chairperson. Members of these committees may include people other than LEPC
members, i.e., those with technical knowledge, facility representatives, response information, specific
expertise and/or skills, etc.
Section 2.
Subcommittees of the LEPC may include, but are not limited to, the following : Planning , Training,
Exercising, Response Guidelines, Special Facilities, Evacuation, Public Information, Outreach,
Environmental Assessment, etc.
Section 3.
Each subcommittee will have an appointed chai r who is a member of the LEPC. This Subcommittee
Chair will serve as the liaison between the Subcommittee and the LEPC, relaying information and
recommendations as appropriate.
ARTICLE VII
PARLIAMENTARY AUTHORITY
The rules contained in the current edition of Robert's Rules of Order Newly Revised shall govern the
LEPC in all cases to which they are applicable and in which they are not inconsistent with these
statements and any special rules of order the LEPC may adopt.
ARTICLE VIII
ADOPTION of and AMENDMENTS to BYLAWS
Adoption of these bylaws or approval of amendments to these bylaws can be accomplished at any
regular or special meetings of the LEPC as an agenda item with a majority roll call vote.
Approved
Revised
Jan Victorson, Chair
Bayfield County Local Emergency Planning Committee
BAYFIELD COUNTY
Local 117 E Sixth St – PO Box 423
Emergency Washburn WI 54891
Planning 715-373-6113
Committee 2026
NAME GROUP ORGANIZATION MAILING ADDRESS TELEPHONE APPT LEPC POSITION
Lynn Hall
lynn.m.hall@xcelenergy.com
V Xcel Energy
2400 Farm Road
Ashland WI 54806
715.577.0613 (cell)
9/25
Jan Victorson
jan.victorson21@gmail.com
IV Community Member PO Box 441
Iron River WI 54847
715-813-7127 1/23 Chair
Jack Hoiby
jhoiby@cheqnet.net
II Grand View Fire
Mason Ambulance
22475 Sunset Acres La
Grand View WI 54837
715.739.3301 (h) 05/19
Paul Houck
phouck@bayfieldcounty.org
II County Information
Technology
05/17
Ben Garrett
benjamin.garrett@wisconsin.gov
II Wildfire Mitigation Specialist
WDNR
05/17
Jim Filby
administrator@cityofwashburnwi.gov
IV City of Washburn
Administrator
119 N Washington Ave - Box 638
Washburn WI 54891
715-373-6160x4
09/26
Tom Kovachevich
citypublicworks@cityofbayfield.com
II City of Bayfield Public
Works
Bayfield Fire
125 S 1st Street - PO Box 1170
Bayfield WI 54814
715-779-5731
01/13
Tom Stankard
tstankard@ashlanddailypress.net
III Ashland Daily Press 248-930-8687
10/25
Lance Ritola
lritola@tamarackhealth.org
II Tamarack Health Ashland
Medical Center
715-685-5327 (o)
715-581-7395 (c) 1/25
Tom Croteau
tom.croteau@bayfieldcounty.wi.gov
IV Human Services/ ADRC 117 E 6th St – PO Box 100
Washburn WI 54891
715-373-6144 (w)
09/26
Charly Ray
cray@bayfieldcounty.org
I Bayview Town Board 04/20 Vice Chair
Marian Schraufnagel
marschrauf@gmail.com
I Village of Mason
Clerk
05/19
Tony Williams
tony.williams@bayfieldcounty.wi.gov
I & II Bayfield County Sheriff PO Box 115
Washburn WI 54891
715.373.6300 (o) 1/23
Natasha Trush
natasha.trush@redcliff-nsn.gov
II Red Cliff Tribe
Environnemental Health
37295 Community Rd
Bayfield, WI 54814
715-779-3650 x4313
715-209-3863 1/23
Meagan Quaderer
Meagan.quaderer@bayfieldcounty.wi.gov
II Bayfield County
Emergency Management
PO Box 423
Washburn WI 54891
715.373.6113 (o)
715.558.2484 (c) 03/22
Information &
Emergency Coordinator
Ryan Matthews
Ryan.Matthews@bayfieldcounty.wi.gov
II Bayfield County
Emergency Management
PO Box 423
Washburn WI 54891
10/25
Anne Marie Coy
annemarie.coy@bayfieldcounty.wi.gov
II BA Public Health 117 E 5th St
Washburn WI 54891
715.373.3321 (o)
715.209.0318 (c) 10/25
Bayfield County Hazard Mitigation Plan Update
Overview
Bayfield County is starting the update of its All-Hazard Mitigation Plan in January 2027. The work will
take about 12 months, from the kickoff meeting to adoption.
The current plan was last updated in November 2020. Bayfield County Emergency Management is
leading the update, with the Northwest Regional Planning Commission (NWRPC) as the planning
consultant.
Why we need a hazard mitigation plan
Without a current, FEMA-approved plan, the County and its communities can't apply for federal
mitigation grants. The plan must be reviewed and resubmitted every five years to stay approved.
• Federal funding eligibility. The Disaster Mitigation Act of 2000 requires local and tribal
governments to have an approved plan before they can receive FEMA mitigation funding. This
includes the Hazard Mitigation Grant Program and the Flood Mitigation Assistance Program.
• Breaking the damage cycle. Mitigation is the only phase of emergency management aimed at
stopping the cycle of damage, rebuilding and repeated damage.
• Lower costs and fewer injuries. Taking action before a disaster reduces loss of life, property
damage and the cost of recovery.
• A guide for decision makers. The plan identifies the greatest risks, so local officials know where
to spend limited budgets, staff and resources.
• Keeping current with change. Since 2020, new hazard events, development, population shifts
and completed projects have changed the County's risk. The plan needs to reflect those
changes.
Topics we will cover
The update follows the six plan elements FEMA requires under 44 CFR §201.6.
1. Planning process. We will document how the plan is updated, who takes part, and how the
public and each participating community are involved.
2. Hazard identification and risk assessment. We will confirm the County's hazards and add any
new ones. Then we will record hazard events since the last plan and update how likely each
hazard is and what losses it could cause.
o Natural hazards in the current plan include flooding, winter storms, wildfire, extreme
temperatures, thunderstorms, inland and coastal erosion, infectious disease, fog,
tornadoes, dam failure and landslides.
o Human-caused and technological hazards include energy emergencies, communications
disruption, cyber threats, utility disruption, hazardous materials incidents and mass
casualty incidents.
o In 2020, the top-ranked hazards were flash flooding, heavy snow, blizzards, wildfire and
extreme cold.
3. Community profile. We will update population, housing and development trends, and the
inventory of buildings, infrastructure and critical facilities in hazard areas.
4. Capability assessment. We will review the County's current resources, plans and programs for
reducing risk and record what has changed.
5. Mitigation strategy. We will review the plan's goals and objectives and identify which past
actions were completed, dropped or deferred. Then we will add new actions and set new
priorities, using cost/benefit analysis.
6. Plan maintenance. We will check whether the current process for monitoring and updating the
plan worked, and decide how the plan will connect with other County and local plans.
7. Maps. We will update the GIS maps and data, which the County will keep for future updates.
8. Review and adoption. The plan will be reviewed by Wisconsin Emergency Management and
FEMA, then adopted by each participating jurisdiction.
Timeline
The plan will be drafted over eight months. The last four months are set aside for state and federal
review and for adoption.
Month (2027) Work Meetings
January Kickoff meeting; public and community participation plans 1
January–February Confirm hazards; collect and analyze data 2
February Update community profiles 1
March–April Update risk assessment and loss estimates 2
May Update capability assessment 1
June–July Update mitigation strategy and actions 2
August Draft plan; public information session 1
September Finalize plan and submit for WEM/FEMA review 1
October–December State and FEMA review; formal adoption 1
Months are approximate and based on NWRPC's 12-month schedule.
Bayfield County Hazard Mitigation Plan Update
— Roadmap
Step-by-step guide to meet FEMA requirements · Prepared September 25, 2026
Start here
The plan has lapsed, so this roadmap runs on a compressed nine-month track: kickoff in November 2026,
FEMA’s approvable-pending-adoption letter by about June 2027, adoptions done by September 2027.
Three things to know before anything else:
1. The plan has lapsed. Until a new plan is approved, the county, cities, village and participating towns
cannot apply for or receive FEMA mitigation project grants (HMGP, BRIC, FMA). Disaster response
aid (Public and Individual Assistance) is not affected.
2. The rules changed in 2025. FEMA’s Local Mitigation Planning Policy Guide (April 11, 2025) is the
standard your plan will be graded against. Climate change and underserved-community items are
no longer required. Everything else is.
3. Funding is already scoped. NWRPC quoted $32,856 (on-site) or $29,247 (remote) to write the
update; the BRIC application to pay for it was still unfunded in March 2026. With the plan lapsed,
paying from the county budget now beats waiting on a grant. Hiring NWRPC is the fastest route for
a first-timer: they wrote the 2018 regional flood study and know the county.
Do this week: email WEM (DMAWEMHazardMitigation@widma.gov) that the plan has lapsed and the
update is starting; ask about EMPG, their review turnaround, and any state requirements.
What the update actually is: you re-run the same five steps the 2020 plan followed, prove it with
paperwork, and get every jurisdiction to adopt it. FEMA does not grade how polished the plan looks. It
grades whether each required element is present and documented, using a checklist called the Plan Review
Tool (PRT).
Big new facts the update must cover: the April 2026 storms and flooding (Bayfield received Individual
Assistance under DR-4923), FEMA’s new preliminary flood maps for the county (89.6 miles of new coastal
study), the Enbridge Line 5 reroute, and the county’s 2023–2043 Comprehensive Plan, which now has its
own hazard mitigation element.
What FEMA requires
The plan must satisfy six required elements (A–F) from 44 CFR 201.6; FEMA’s 2025 Policy Guide breaks each
into sub-elements you check off on the Plan Review Tool (Appendix A of the Guide). Confirm the exact sub-
element codes against the PRT you download.
Element What you must show 2020 plan status
A. Planning
process
How the plan was prepared and who participated from each
jurisdiction (A1). That neighboring communities, agencies that
regulate development, businesses, schools and nonprofits had a
chance to take part (A2). How the public was involved during
drafting and how their input was used (A3). Which existing plans
and studies were reviewed and how they were used (A4).
Partial. Lists committee but not
what each town did; no public
comments recorded; outreach to
neighbors not documented
beyond a draft mailing.
B. Risk
assessment
For every hazard: description, location, extent, past events,
probability (B1). Vulnerability summary and impacts on each
participating jurisdiction (B2). NFIP repetitive-loss properties.
Mostly there, but data ends
2018 and several sections have
copy-paste errors (see fix list).
C. Mitigation
strategy
Capability assessment for each jurisdiction (C1). NFIP participation
and compliance for each NFIP community (C2). Goals (C3). A range
of actions per hazard, with at least one action for each
participating jurisdiction (C4). Prioritization, lead, funding and
timeline (C5).
Weak on C1 (no capability table),
C2 (NFIP status appears wrong
for Washburn), and C4 (most
towns have no actions of their
own).
D. Plan
maintenance
How the plan will be monitored, evaluated and updated over five
years, how the public stays involved, and how the plan feeds into
other plans.
Present (Section 7). You must
now show whether the promised
annual LEPC reviews happened.
E. Plan update Changes in development since 2020 in hazard-prone areas, and
status of every 2020 action (completed, deleted, deferred) with
reasons. Priorities that changed.
Must be written new. The
section first-time updaters most
often miss.
F. Adoption Adoption resolution from every jurisdiction seeking approval. Each jurisdiction passes a
resolution after FEMA’s
“approvable pending adoption”
letter.
G. High Hazard
Potential Dams
(optional)
Only needed for HHPD rehabilitation grants. Worth adding: WDNR rates the
Iron River dam High hazard.
H. State
requirements
(optional)
Anything WEM adds. Ask WEM at kickoff.
What the 2025 Guide dropped: plans no longer have to address climate change or specifically engage
underserved and socially vulnerable populations. You may keep that material; it just isn’t graded.
Hazards: FEMA only requires natural hazards. The 2020 plan’s manmade hazards (energy, cyber, hazmat,
mass casualty) can stay but won’t be reviewed and can’t draw FEMA mitigation funds. Consider adding
drought and invasive species / forest health if the committee sees them as real risks.
Who must be involved
Use the LEPC as the planning committee again, but get a named point of contact from every jurisdiction
that wants FEMA grant eligibility, because each one must participate, have its own action, and adopt.
Participating jurisdictions (up to 29). Bayfield County, City of Bayfield, City of Washburn, Village of Mason,
Red Cliff Band of Lake Superior Chippewa, and the 25 towns. The 2020 plan said the county “covers the
towns.” FEMA does not work that way: a town that wants HMGP or BRIC money must itself participate and
pass an adoption resolution. Decide early which towns are in, and document it.
Minimum each participating jurisdiction must do:
• Name a point of contact and send someone to at least one meeting, or complete the written
worksheets.
• Return a capability worksheet (staff, ordinances, budget, NFIP status).
• Report the status of its 2020 actions and any new development in hazard areas.
• Propose at least one mitigation action it will own.
• Adopt the plan by resolution.
Red Cliff. Red Cliff can keep participating in the county plan. If the Band wants to apply to FEMA directly as
a tribal recipient, it needs a plan meeting the tribal rules (44 CFR 201.7); ask FEMA Region 5’s tribal liaison
which path Red Cliff intends.
Stakeholders to invite (and document inviting):
Group Examples
Neighboring jurisdictions Ashland, Douglas, Sawyer and Washburn counties; Bad River Band
Agencies that regulate
development
County Zoning, Land Records, Land & Water Conservation; WDNR (floodplain, dam safety);
WisDOT
Federal and state land
managers
Chequamegon-Nicolet National Forest; Apostle Islands National Lakeshore; WEM Region;
NWS Duluth
Infrastructure and lifelines Xcel Energy, Bayfield Electric Cooperative, Norvado, CenturyLink, Enbridge, sanitary
districts, County Highway
Health and human services County Health Dept., ADRC, Memorial Medical Center, Red Cliff Community Health Center,
EMS and fire departments
Schools, business, nonprofits School districts, chambers of commerce, tourism, American Red Cross, Bayfield Regional
Conservancy
Public. Everyone in the county, including seasonal residents (43.8% of housing units in 2015 were seasonal),
so plan outreach for summer as well as winter.
Schedule
Because the plan has lapsed, this is the compressed track: four committee meetings (3 and 4 combined),
two public input windows, and drafting running alongside the meetings.
When Phase Key outputs
Late Sep –
Oct 2026
Setup Notify WEM; approve funding and NWRPC contract; download PRT and
FEMA Handbook worksheets; set up shared records folder
Oct 2026 Invitations + Public input #1
opens
Letters to all 29 jurisdictions and stakeholders the same week the
survey launches; points of contact named; project web page live
Early Nov
2026
Meeting 1: Kickoff Roles, schedule, hazard list confirmed; worksheets handed out, due in 6
weeks
Oct – Dec
2026
Public survey open Online and paper survey; press release; Towns Association
announcement
Dec 2026 Meeting 2: Risk assessment Updated event history (2018–2026); new flood maps; hazard priority
matrix scored by each jurisdiction
Dec 2026 –
Feb 2027
Drafting (in parallel) Consultant drafts planning-area and hazard-profile sections while
meetings continue
Jan 2027 Meeting 3+4: Capabilities, 2020
actions, new actions
One 3-hour session: capability table, status of every 2020 action, revised
goals, new actions (at least one per jurisdiction) ranked
Late Feb
2027
Meeting 5: Draft review &
maintenance
Full draft + completed PRT; committee releases draft for comment
Mar 2027 Public input #2 30-day public comment period; open house or public hearing
Apr 2027 Submit to WEM WEM pre-review; fix comments
May – Jun
2027
FEMA Region 5 review Approvable Pending Adoption (APA) letter
Jun – Sep
2027
Adoption County Board adopts first; then each jurisdiction; resolutions to WEM;
FEMA approval letters restore grant eligibility
Where the time was cut: invitations and the survey go out together, Meetings 3 and 4 are combined, and
drafting overlaps the meetings. Where it was not: the 30-day public comment window and the adoption
votes. Reviewers check those hardest, and skipping them costs more time in revisions than it saves.
Five-year clock: for a multi-jurisdictional plan, the five years start when FEMA approves the first adopting
jurisdiction, and every jurisdiction shares that expiration date. Get the County Board to adopt first and fast,
then chase the towns. A jurisdiction adopting more than a year after the APA letter has extra paperwork, so
aim for all adoptions within 12 months.
Meeting-by-meeting guide
FEMA sets no minimum number of meetings; it requires proof of who participated and how. Every meeting
below should be a noticed, open LEPC meeting (Wisconsin open meetings law requires at least 24 hours’
public notice), with a Zoom option so remote towns can join.
For every meeting, save: the posted notice, agenda, sign-in sheet with each person’s jurisdiction or
organization, slides, minutes, and the Zoom attendance report. Put them in the plan’s appendix.
Meeting 1 — Kickoff (early Nov 2026)
• Purpose: explain why the plan matters (grant eligibility) and what each jurisdiction must do.
• Agenda: what mitigation is; the FEMA elements; schedule; roles; review 2020 goals and hazard list;
add or drop hazards (drought? invasive species?).
• Hand out: point-of-contact form; capability worksheet; 2020 action status worksheet; “changes in
development since 2020” worksheet. Due before Meeting 3.
• Output: confirmed participant list, hazard list, schedule.
Meeting 2 — Risk assessment (Dec 2026)
• Purpose: update what could happen and how bad.
• Agenda: events since 2018 (April 2026 storms, any others the towns report); NOAA storm events
data; new preliminary flood maps and changes in flood-zone structure counts; HAZUS results from
NWRPC’s 2018 study; FEMA National Risk Index for the county; dam list and hazard ratings; Lake
Superior coastal erosion.
• Exercise: each jurisdiction re-scores the hazard priority matrix (same 9 criteria as 2020, so results
compare).
• Output: ranked hazards for the county and for each city, village, and Red Cliff.
Meeting 3 — Capabilities and 2020 actions (Jan 2027, first half of combined session)
• Purpose: show what each jurisdiction can do today, and what happened to every 2020 action.
• Agenda: capability worksheets summarized in one table; NFIP participation confirmed for each
jurisdiction; walk the 2020 action table line by line: completed, ongoing (with what was done),
deferred (why), or deleted (why).
• Output: capability table; action status table; revised goal statements.
Meeting 4 — Mitigation actions (Jan 2027, second half of combined session)
• Purpose: pick what the county and each jurisdiction will do next.
• Agenda: brainstorm by hazard, starting with the top-ranked ones; carry forward still-valid 2020
actions; add new ones (see ideas in the fix list); rank with the 2020 criteria (lives and property
saved, cost-effectiveness, funding availability).
• Check before leaving: every participating jurisdiction has at least one action with a lead, cost
estimate, funding source, and timeframe.
• Output: draft mitigation action table.
Meeting 5 — Draft review and maintenance (late Feb 2027)
• Purpose: approve the draft for public comment.
• Agenda: walk the completed PRT; agree on how the plan will be monitored (for example, one LEPC
agenda item each year with a written status report); agree on how actions get into comprehensive
plans, budgets, and ordinances.
• Output: motion to release draft for 30-day public comment.
Public involvement
The public needs two chances to weigh in, once while the plan is being written and once on the draft before
it goes to FEMA, and the plan must say how their input was used.
Window 1: during drafting (Oct – Dec 2026)
• Short online survey (10 questions max): which hazards worry you, what happened to you since
2018, what should the county fix. Paper copies at town halls, libraries, and the courthouse.
• Press release to the Ashland Daily Press and local radio; post on the county website and Facebook;
announce at a Towns Association meeting.
• Ask Red Cliff to share through tribal channels and Tribal Council.
Window 2: draft comment period (Mar 2027)
• Post the full draft online for 30 days with a comment form and an email address.
• Hold one open house or public hearing (can be at an LEPC meeting); publish notice.
• Send the draft to Ashland, Douglas, Sawyer and Washburn county emergency managers and the
Bad River Band with a comment deadline.
Keep a comment log. One row per comment: date, source, what they said, and what the committee did
about it. “No comments were received” is fine only if you can show the invitations went out.
Keep proof of outreach: copies of press releases, screenshots of web and social posts with dates, survey
results, mailing lists, and newspaper affidavits of publication.
Fix list for the 2020 plan
Most of the 2020 plan can be reused; these are the specific problems a WEM or FEMA reviewer would likely
flag.
Section Problem Fix
1.2, 1.5,
Annex A
Committee roster, dates and contact (Jan
Victorson) are from 2018
New roster, current EM Director, new email domain
(bayfieldcounty.wi.gov)
1.4, Annex A Says Comprehensive Plan adopted 2018 in one
place, 2012 in another
Cite the 2023–2043 Comprehensive Plan (adopted Nov
14, 2023) and its hazard mitigation element; update
town plans list
2.0 Population, housing and income from 2015 ACS Update with 2020 Census and latest ACS 5-year
estimates
4.1 Flooding Event table ends June 2018; 299 vs. 300
floodplain structures cited in different places;
built on 2011 flood maps
Add 2018–2026 events incl. April 2026 (DR-4923);
recount structures using the new preliminary FIRMs
4.1 and 6.1
NFIP
Plan says Washburn participates in NFIP;
FEMA’s Dec 2025 slides list Washburn and
Mason as non-participating
Confirm status in FEMA’s Community Status Book; write
C2 for each NFIP community
4.6 Inland
erosion
Economic impact, population and critical
facilities paragraphs are pasted from the
thunderstorm section
Rewrite for erosion (roads, culverts, farmland)
4.7 Coastal
erosion
Vulnerability labeled HIGH, text says ranked
low, strategy table says LOW
Pick one rating and make all three agree
4.9 Fog, 5.1
Energy
Refer to “Price County” Replace with Bayfield County data
4.10
Tornadoes
Text says 1983 Barnes tornado was F2, table
says F1; text says 1988 Mason tornado, table
says 1998
Reconcile against NOAA Storm Events
4.8, 5.1, 5.4 Vulnerability given as “Low to High” or “Low”
then “medium”
One rating per hazard
4.8 Infectious
disease
Written mid-COVID Summarize actual COVID-19 impacts and lessons
4.11 Dams Text says 1 of 3 significant dams had an
Emergency Action Plan; the action table shows
more completed
Update from WDNR dam database; consider optional
Element G for Iron River (High hazard)
5.5 Hazmat No mention of Line 5 reroute Add reroute route and response planning
6.1 Actions Many items say “Ongoing” or have 2018 dates
with no explanation
Status and reason for every 2020 action (Element E)
6.1 Actions Most of the 25 towns have no action of their
own
At least one action per participating jurisdiction
7.0 Promised annual LEPC reviews and newsletter
updates
Show evidence they happened, or explain and describe a
more realistic process
New No capability assessment table One table: each jurisdiction’s plans, ordinances, staff,
budget tools, NFIP status
New No “changes in development” discussion Short narrative per jurisdiction on growth in hazard-
prone areas since 2020
Action ideas already in the county’s pipeline worth formalizing: culvert inventory and upsizing (the 2018
flood study and WEM’s Pre-Disaster Flood Resilience Grant both support this), Siskiwit River and
Cornucopia harbor work, Fish Creek slumping, generator capacity for critical facilities, and radio
interoperability.
Review, approval and adoption
The plan goes to WEM first, then FEMA Region 5, and only after FEMA says it is “approvable” do the boards
vote.
1. Self-check. Fill in the PRT with the page number where each sub-element is met. If you can’t point
to a page, it isn’t done.
2. Submit to WEM (Hazard Mitigation Section, DMAWEMHazardMitigation@widma.gov) with the
draft plan, completed PRT, and appendices (meeting records, outreach proof, comment log).
3. Revise per WEM comments; WEM forwards to FEMA Region 5.
4. FEMA review. FEMA either returns required revisions or issues an Approvable Pending Adoption
(APA) letter. Budget roughly two months for WEM plus FEMA combined, more if revisions are
needed.
5. Adopt. County Board adopts first by resolution. Then each city, the village, Red Cliff’s Tribal Council,
and each participating town. Send each signed resolution to WEM.
6. Approval. FEMA issues an approval letter per jurisdiction as resolutions arrive. The plan’s expiration
date is set by the first approval.
Adoption resolution template: reuse the 2020 resolutions in Annex C, updating the plan title, date, and
jurisdiction name. Have them drafted before the APA letter arrives so towns can put them on their next
monthly agenda.
Checklist and funding
Start one shared folder on day one and drop every record in it as it happens; rebuilding the paper trail at
the end is what sinks first-time updates.
Documentation checklist
• ☐ Notify WEM the plan has lapsed; ask about EMPG impact and review turnaround
• ☐ Funding secured and consultant contract signed (if using NWRPC)
• ☐ Download the 2025 Policy Guide, PRT, and 2025 Local Mitigation Planning Handbook worksheets
• ☐ Invitation letters sent to all 29 jurisdictions (copies saved)
• ☐ Invitations sent to neighbors and stakeholders (copies saved)
• ☐ Point-of-contact form returned by each participating jurisdiction
• ☐ Meetings 1–5: notice, agenda, sign-in, slides, minutes saved
• ☐ Public survey run; results summarized
• ☐ Capability worksheet returned by each jurisdiction
• ☐ 2020 action status worksheet returned by each jurisdiction
• ☐ NFIP status verified for every jurisdiction
• ☐ Risk assessment updated (events, maps, dams, data)
• ☐ At least one new or continuing action per jurisdiction
• ☐ Draft posted for 30-day comment; open house held
• ☐ Comment log with responses
• ☐ PRT filled with page numbers
• ☐ Submitted to WEM
• ☐ APA letter received
• ☐ Adoption resolutions collected from every jurisdiction
• ☐ FEMA approval letters filed; next update date on the calendar (start 18 months before
expiration)
Funding options
Source Notes
County budget Covers NWRPC’s $29,247–$32,856 quote outright; fastest, no grant timing risk
FEMA BRIC (FY24/25
NOFO)
Planning is eligible; 25% local match; WEM is the applicant
HMGP planning funds Not available from the April 2026 declaration: the statewide hazard mitigation request was
denied
In-kind match Staff time, committee members’ meeting time, and meeting space count toward a match; track
hours
The county’s 2018 update cost $40,000 total ($30,000 HMGP, $5,000 WEM, $5,000 county in-kind), so the
NWRPC quote is in line.
Resources and contacts
Call WEM’s Hazard Mitigation Section first; they review your plan before FEMA and will tell you their
current turnaround and any state additions.
Who Role Contact
Chad Atkinson, WEM Hazard Mitigation Section
Supervisor
chad.atkinson@widma.gov · (608) 893-0816
Heather Thole, WEM State Hazard Mitigation Officer heather.thole@widma.gov · (608) 282-5301
WEM Hazard Mitigation (shared) Plan submissions and questions DMAWEMHazardMitigation@widma.gov
Sarah Rafajko, WDNR State NFIP Coordinator sarah.rafajko@wisconsin.gov · (608) 893-
8710
Meghan Burrows, FEMA Region 5 Community Planner via WEM
Chad Lanctot, FEMA Region 5 Tribal Liaison (for Red Cliff’s path) via WEM
Northwest Regional Planning
Commission
Plan writing, GIS, HAZUS nwrpc.com
Contacts are from FEMA’s December 2025 Bayfield County flood map meeting slides; confirm before relying
on them.
Sources
• FEMA Local Mitigation Planning Policy Guide (effective April 11, 2025) — the standard; Appendix A
is the PRT
• FEMA: Create a Hazard Mitigation Plan — Handbook and worksheets
• FEMA Hazard Mitigation Plan Status
• Massachusetts summary of FEMA’s 2025 policy waiver
• APA: FEMA waives equity and climate requirements
• 44 CFR 201.6 (local plan regulation)
• WEM: April 2026 disaster declaration
• WEM: BRIC FY24/25 funding notice
• Bayfield County Risk MAP meeting slides, Dec 2025
• Citizen Portal: March 16, 2026 Sheriff’s Committee summary (AI-generated summary; verify against
official minutes)
• 2020 Bayfield County All-Hazard Mitigation Plan
Source: Bayfield County website. First collected Nov 19, 2026.