Plan Commission Meeting — Minutes
Town of Merton · Waukesha County · Plan Commission Meeting · meeting of Oct 21, 2026 · Minutes
Open the original document More from Town of Merton
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
Town of Merton
Plan Commission Meeting
Minutes of October 21st, 2026
• Meeting Called to Order by Chairman Klink at 5:30 p.m.
• Pledge of Allegiance led by Chairman Klink
• Minutes September 16th, 2026 Plan Commission Meeting. A motion to approve the minutes as written was
made by Commissioners Good/Queoff. Motion carried.
Present: Chairman Klink, Commissioners Griffin, Queoff, Olson, and Good, Attorney Van Kleunen, Planner Haroldson,
and Deputy Clerk Claas
Absent: Commissioners Siepmann and Caliendo
Also Present: Mike Duffek, Erik Semb, Dan Groskopf, Chad Lindmark, Shan Amin, Joe Lindmark, Marty Iverson
& others
Old Business: None
New Business:
Request to Update the Plan of Operation and to Build an 11,000 SF Addition to Their Existing Building with a Site
Plan - Requested by Duffek Construction – on Behalf of Chad and Joe Lindmark – Hartland Overhead Door – County
Road Vv – MRTT0346-993-003 – Planner Haroldson stated they are proposing an addition to the existing building
that is 11,995 sq. ft. They are zoned B-3 district, they have 1.9 acres, and they are under the 50% allowable Floor
Area Ratio. They meet all the criteria for the zoning district. No new sign is requested and downward lights will be
on the building.
Conditions for this addition are:
• They need to have plans for the addition submitted to the Building Inspector and approved for a permit
• They will need an updated Preliminary Site Evaluation
• They need a stormwater permit and erosion control
• They will need to pay the Fire Impact Fee
• They will need to allow the Fire Inspector to inspect the property after it’s constructed
Chairman Klink asked if the shipping containers will be removed. Chad Lindmark responded yes. Commissioner
Good asked if they are removing asphalt for stormwater. Chad Lindmark responded yes.
A motion to approve this subject to the conditions was made by Commissioners Griffin/Olson. Motion carried.
Plan of Operation and Site Plan for a New Building for Residential and Offices – Zoned B-2, as Requested by Dan
Groskopf – Groskopf Construction – on Behalf of the Wenthur Law Group LLP, CTH K, MRTT0361-982-001 – Planner
Haroldson is zoned B-2 Business District which allows for mixed use. It’s 20,000 sq. ft lot. The building is 5,334 sq. ft.,
the garage is 1,263 sq. ft., and the one-bedroom studio over the garage is 1,208 sq. ft. They will have office hours
from 9 to 5 every day, Monday through Friday with two full-time employees and two seasonal employees.
Groskopf said it’s a family law office. They are based out of California, but the owner is from this area. The owner’s
hope is some of his kids, who are also attorneys, will live there and occasionally bring some of the California workers
here to Wisconsin and have a spot to work.
Planner Haroldson stated if they have a sign, they will need to get a sign permit and supply the Town with details
about that sign. Planner Haroldson questioned if he got approval from Waukesha County for moving the access to
the building. Groskopf responded that he submitted an access permit to Waukesha County. Groskopf said they had
to put in a new septic, and they have the sanitary permit. Planner Haroldson said if they plan to construct an in-law
suite, they will need a conditional use permit.
Planner Haroldson said they have to allow the Fire Inspector to inspect the property. Chairman Klink questioned
signage and parking. Groskopf stated he thought it would be a stand-alone sign but there are no details yet, and
they don’t anticipate any walk in traffic. It’s mostly a remote location. Planner Haroldson clarified with Groskopf
that he is aware that they need a certified survey map to convey that road right-of-way per legal opinion. Planner
Haroldson said they have 60 days to submit that and 90 days for approval to get the certified survey map recorded.
They can start the project without the certified survey map after the approval of the Building Inspector.
A motion to approve this building application based on all comments and conditions from the staff including a
certified survey map was made by Commissioners Good/Queoff. Motion carried.
Certified Survey Map – to Divide Combine 2.25 Acres – Zoned R-1 – into Two (2) Parcels – County Road KC (Merton
Avenue), Requested by Jahnke and Jahnke Associates LLC – on Behalf of E Villarreal Properties – MRTT0425-996-001
– The property is zoned R-2 and it requires a minimum lot size of 30,000 sq. ft. They have a 2.25-acre lot, and they
want to divide it into two parcels. Lot 1 will be 1.20 acres and Lot 2 will be 1.08 acres. They meet the minimum
average width and the size requirements. They have to have a shared access on the asphalt driveway because the
County won’t let them have another access to Merton Avenue. Planner Haroldson said the survey will need to show
the shared access, Waukesha County can be deleted from sheet 5, topographical lines need to be on the survey per
the checklist, and any new house on lot 2 will need to pay a Park Impact Fee and the Fire Impact Fee.
Chairman Klink questioned if they should have an agreement for the shared easement. Planner Haroldson agreed
that they should have an easement agreement. Attorney Van Kleunen asked if lot 2 is going to be developed right
away. Planner Haroldson responded that she has no idea. Attorney Van Kleunen said he would add that if and when
a building permit is pulled for Lot 2 there needs to be an easement agreement for access. Commissioner Griffin said
there’s a lot going on, and he thinks they should bring the certified survey back.
Chairman Klink requested Planner Haroldson to notify the owners that the certified survey map is on hold.
Request by the Town DPW Director to Recommend Approval of a Driveway that is Less than 6 ft from the Side Lot
Line – Hasslinger Drive – MRTT0405-008 – Commissioner Griffin stated the owner has only 35’ of access on
Hasslinger Drive and he asked if DPW Director Griffin could approve it. Commissioner Griffin wanted this to come
before the Plan Commission for approval and stated that there are numerous driveways on that road that are not 6’
from the lot line. DPW Director Griffin doesn’t have a problem with it, but he thought it needed to come to the Plan
Commission for approval.
A motion to approve the request of the Town DPW Director recommending approval of locating a driveway less
than 6 ft. from the property line on Hasslinger Drive was made by Commissioners Queoff/Good. Motion carried.
Update with the President of Milwaukee Wave – Shan Amini – Regarding the Soccer Lease and Responsibilities on
the Merton Soccer Field Park - Champion Drive – MRTT0347-051 – Amini stated that the soccer park is not being
heavily utilized. This year they put in a bunch of smaller fields, and they had eight U8 teams playing and two U10
teams. Those teams will slowly age up and being taken over to some of the bigger fields. This is the first year they
made Merton an actual offering to try to create a community club instead of asking people to come out to Merton
and play.
Their spring season basically goes from April 1st until June 15th, and the fall season is August 1st to November 15th,
but it’s usually done by Halloween. They are part of the Milwaukee Wave Organization Profession Indoor Team.
They had 30 camps at various locations in southeastern Wisconsin. They will host two of them in Merton to try to
bring people in the community in to get them interested in soccer. This is typically for ages 4 years old through 13
years old. At this time the fields are underutilized, but they are hoping the steps they are taking will get them back
to the utilization the Town needs.
Chairman Klink mentioned the neighbors had concerns. Amini said if there are any issues whatsoever, to reach out
to him, and they will make sure it gets addressed right away. If anything looks in disrepair, let him know. There are
port-a-johns and a dumpster out there.
Commissioner Griffin said the weeds that have taken the place over. Amini said they try to mow as short as possible
because they have a lot of parents that are concerned about the toxins that are put onto the chemicals on the
fields. They know it’s not as aesthetically pleasing. Commissioner Griffin asked if their first session is April to June,
could they do it right after their first session. They have camps during the summer, so Amini asked if they could do it
beforehand or late in the year when everyone is done. Commissioner Griffin said once it’s dry, it should be fine and
stated if they could treat it right after the last session, he thinks that might help a little bit. Commissioner Griffin said
he would talk to Frontier Supply about how good it would be if they treat it the first week of November. Amini asked
if they could look into early, early spring too and stated they could push back the Spring session a little bit if they
had to.
Recommendation to the Town Board – Request from Marty Iverson – on Behalf of Monches Rec Club – For New
Playground Equipment for the Monches Park – County Road E – MRTT0297-976-001 – Planner Haroldson passed out
information for the playground equipment and Iverson would like this to be recommended to the Town Board for
safety reasons. Planner Haroldson said he’s not applying for any impact fees; he’s just asking the Park Committee to
recommend this to the Town Board. The impact fees cannot be used to repair swing sets per the accountant.
Commissioner Griffin asked if Iverson is asking to repair it or replace it all. Planner Haroldson said the information
has numbers to repair it and he has the same numbers available to replace it. Commissioner Griffin asked if any of
the Plan Commissioners have gone to Monches Park and said he did. Commissioner Griffin said there is about six
pieces of playground equipment there and the red swing should be totally replaced. The slide that goes down the
pole could be replaced, but the rest of it is fine. There are probably 4 or 5 posts that have got water in them and are
cracked and should be replaced. He walked through that whole playground twice, and its way better than the stuff
at North Lake Park or the stuff that’s in Stone Bank, and it’s newer. He would not spend the money to replace it all.
He would fix what’s there.
Chairman Klink asked Iverson if they were planning to replace everything. Iverson responded that all of the
equipment is 20 years old, there are posts in the ground that are failing, and the big center piece of that whole
playground is starting to fall apart and break. Iverson referred to the pictures of the tire apparatus and stated the
steel treads in the tire are starting to come through, and they had one person get injured on posts. It was
recommended by the three people that they brought out to look that the playground be torn out and started over
and all the equipment should be replaced. The average life they said is 15 to 20 years.
Commissioner Griffin asked if they can’t just replace that slide. Iverson said there’s more than just the slide that’s
broken. Commissioner Griffin agreed that some of the equipment needs to be replaced, but he wouldn’t think they
would need to rip the whole thing out. Iverson said this is a liability issue for them and for the Town. Chairman Klink
asked if there was any talk about possibly fixing some of the equipment and replacing others. Iverson responded
that the original number they looked at was repairing some of the pieces was quoted at around $100,000, and that
was before they found the big piece of equipment damaged.
Chairman Klink said he would prefer they have a committee meet out there with them to go over stuff. The Plan
Commission agreed. Iverson said Dawn and Earl Cull have been the heads in this, and they met with every
contractor out there. Commissioners Good and Griffin and Chairman Klink will be the committee. Iverson will
contact Dawn and Earl Cull to set a date and time.
Planner Report – Marilyn Haroldson – stated on November 18th the Plan Commission would have a joint public
hearing with Waukesha County to address a rezone for Halquist Stone.
DPW Report – Paul Griffin – had nothing to report.
A motion to adjourn was made by Commissioners Olson/Queoff. Motion carried. Meeting adjourned at 6:17 p.m.
Respectfully submitted,
Holly R Claas
Deputy Clerk