TOWN OF COTTAGE GROVE
TOWN BOARD MEETING
NOVEMBER 5, 2026
Page 1 of 3
I. ADMINISTRATIVE
A. Notice of the meeting was posted at the Town Hall and on the Town’s website. Town Chair
Steve Anders and Supervisors Mike Fonger, Troy Eickhoff, Kristi Williams, and Patrick
Buchholz were present, along with Clerk-Treasurer Kim Banigan, Deputy Clerk Jennifer
Millage, Highway Superintendent Dan Dresen and Town Engineer Nick Bubolz. DGEMS
Chief Eric Lang attended virtually. Anders called the meeting to order at 6:30 P.M.
B. Flag Pledge.
C. Discuss/Consider approval of minutes of previous meetings: MOTION by
Williams/Buchholz to approve the minutes of the October 19, 2026 Town Board meeting and
October 22, 2026 Budget Workshop as presented. MOTION CARRIED 5-0. MOTION by
Fonger/Williams to approve the minutes of the October 22, 2026 closed session as presented,
and keep them closed until the 2027 budget is adopted. MOTION CARRIED 5-0.
D. Finance Report and Approval of Bills: MOTION by Fonger/Eickhoff to approve checks
#38954-38982 totaling $75,320.41, EFTs for $31,027.24, voided check #38940 for $203.50,
and scheduled purchase card/ACH payments of $5,256.55. MOTION CARRIED 5-0.
MOTION by Williams/Buchholz to approve October per diem payments as presented.
MOTION CARRIED 5-0.
E. Public Concerns: Village Resident Mark Spahos questioned what value the PAA study
discussed last night at a joint meeting of the Town and Village Boards provides to the
taxpayers, noting that there appeared to be many discrepancies and inaccuracies.
II. BUSINESS
A. Plan Commission Recommendations:
1. Beau Crawley, 1657 S. Jargo Road: Seeking determination of whether a RDU is needed
to correct an illegal land division by the prior owner of parcel 0711-254-8501-0:
Possible rezone options to correct the illegal land division were discussed, with Mr.
Crawley preferring RR-2 for the homesite and FP-1 for the farmland. Anders noted
that Mr. Crawley unknowingly inherited this problem when he purchased the property.
MOTION by Buchholz/Fonger to NOT require a RDU, regardless of what zoning
option is chosen. MOTION CARRIED 5-0. Eickhoff noted that he agrees, even
though it contradicts the motion he made at the Plan Commission meeting.
2. Chris Miller, Petitioner, GT Rentals LLC, property owner, parcels 0711-291-8000-6 and
0711-291-8685-9 on Hope Road: seeking rezone of 8.1081 acres from FP-35 to RR-2 to
create 3 new residential lots, rezone of 6.8354 acres from FP-35 to RR-4 to create 1 new
residential lot from an existing farmstead, and rezone of 1.0034 acres from SFR-1 to FP-
35 to eliminate one residential lot and use the RDU for one of the new lots. The other 3
new lots will use transferred RDUs. (DCPREZ 12362, a reapplication of DCPREZ
12311 tabled on June 24, 2026): Terrence P and Irene Clark of 2690 Hope Road
submitted an email expressing concerns over the GT Rentals and Wittewood Ln.
proposal (Exhibit A). Ms. Clark was present and urged the Town to plan strategically
rather than one plat at a time, and to consider the impacts of not only development in the
Town, but also impacts of Village development using Town roads. There was discussion
about lot configuration and sizes and driveway placement. MOTION by
Eickhoff/Anders to accept the Plan Commission’s recommendation to approve the
rezone as proposed, subject to the five conditions on page 5 of Roffers’ review letter, and
with all road right-of-way dedicated to the Town on the final CSM. Developer to work
TOWN OF COTTAGE GROVE
TOWN BOARD MEETING
NOVEMBER 5, 2026
Page 2 of 3
with Roffers to create building sites. They should determine the best spot for the
driveway(s), and combine all three if necessary. MOTION CARRIED 4-2 (Buchholz
and Williams opposed).
3. Dave Witte, applicant, Moms CG Farm LLC, property owner, parcels 0711-301-8000-0
and 0711-292-8502-0 between Wittewood Ln and Hope Rd: Rezone and Preliminary
Plat to create a 10-lot residential subdivision with a transfer of development rights
(DCPREZ-12295 tabled on May 27, 2026): Dave Witte was present with Johnathan
Lilley from Vierbicher. Mr. Witte provided copies of an informal traffic study of Hope
Road that he had performed himself (Exhibit B). An email from Bubolz (Exhibit C)
recommended that the existing stormwater basin be restored to its original as-built
condition within one year after construction of the adjacent new stormwater facilities, to
ensure that the combined stormwater system begins its service life in a known and
properly functioning condition. Going forward, the Town would be expected to
maintain the entire system, with costs assessed on the existing lots south of Wittewood
as well as the new lots created by this subdivision. Anders noted the Town has learned
that Wittes still own the existing and there is no maintenance agreement in place for it.
He recommended that the Wittes be responsible not only for the cost of inspecting it, but
also for the cost to bring it back to its original condition. There was much discussion
about driveway access for lots 7 and 8. The Plan Commission resolution assumed a
shared driveway onto Hope Road, and required a site line determination for the best
location. There were questions about siting of a home, septic and driveway on lot 8
considering the pipeline location and setback requirements. Mr. Witte provided
assurance that there was room for all of it. Eickhoff suggested combining lots 7 and 8
and extending the cul-de-sac so the combined lot could have a driveway on it. But there
would not be enough room on the cul-de-sac for all of the lots to have the County’s
minimum 30-foot frontage on it. MOTION by Anders/Buchholz to adopt resolution
2026-11-05 granting conditional approval of the Preliminary Plat for Wittewood Lane.
MOTION CARRIED 3-2 (Buchholz and Eickhoff opposed).
B. Discuss/Consider approval of MOU between the Deer-Grove Emergency Medical Services
District and International Association of Firefighters Local 311- DeerGrove Paramedics
creating a lateral/experienced hiring program: Chief Lang explained that the version before
the Town Board has been vetted by attorneys for the Villages of Cottage Grove and Deerfield,
and the DGEMS district, as well as approved by both Village boards. It is slightly different
than what was approved by the DGEMS Commission due to changes suggested by one of the
attorneys, and the Commission will need to consider this version at their next meeting.
MOTION by Williams/Eickhoff to approve the MOU as presented. MOTION CARRIED
5-0.
C. Discuss/Consider approval of proposal from Professional Pest Control for service to the
Police Station (tabled from October 19th meeting): MOTION by Eickhoff/Williams to
approve the revised proposal. MOTION CARRIED 5-0.
D. Discuss/Consider whether to pursue a WDNR grant to sample for PFAS: MOTION by
Fonger/Buchholz to not pursue the grant. MOTION CARRIED 5-0.
E. Discuss/Consider Management Discussion and Analysis options for the 2026 audit:
MOTION by Anders/Buchholz to remove the MDA from the 2026 audit. MOTION
CARRIED 5-0.
TOWN OF COTTAGE GROVE
TOWN BOARD MEETING
NOVEMBER 5, 2026
Page 3 of 3
F. Discuss/Consider the Clerk-Treasurer position description: Samples were reviewed.
MOTION by Williams/Eickhoff to draft the position description as discussed, and provide it
by email to Board members with a deadline to reply with suggested edits. MOTION
CARRIED 5-0.
G. Discuss/Consider Clerk-Treasurer hiring process: The Clerk-Treasurer’s office was directed
to advertise with the Wisconsin Municipal Clerk’s Association, Wisconsin Towns Association
and Dane County Towns Association to start with, to hopefully attract someone with
experience.
H. Discuss/Consider replacing rock and split rail fence south of the Town Hall: MOTION by
Fonger/Anders to approve up to $500 to replace the rock and split rail fence. MOTION
CARRIED 5-0.
I. Discuss/Consider rescheduling December Town Board Meeting dates: No change was
approved. The December meetings will be held on the 7th and 21st as regularly scheduled.
III. PUBLIC WORKS ACTIVITY UPDATE:
A. Report of Road Right-of-Way permits issued: Two permits were issued since the last
meeting: 1) to Alliant for new gas service in the entire Meadow Grove subdivision, and 2) to
TDS to install new fiber at 4155 Vilas Road.
B. Ditch mowing is almost complete. They have been working on truck and equipment
maintenance. The yard waste site will close after November 16th, and they will put snow
removal equipment on the trucks.
IV. CLERK-TREASURER’S OFFICE UPDATE: There were 2217 voters in the General Election held
on November 3rd, including 755 absentee voters. Only 13 absentee applicants did not return
ballots, and some of them voted in person on election day.
V. BOARD REPORTS AND COMMUNICATIONS:
A. Anders reported that the Hope Cemetery Association has informed him they are experiencing
financial difficulties and asked for assistance from the Town in the form of snowplowing
cemetery roads this winter. Written advice from Atty. Chris Nelson was that the Town would
need to charge for the service, and suggested doing via a special assessment on the property.
This will be on the November 16th agenda for action. Anders also reported that Dane County
OA-6 has been put into indefinite abeyance.
VI. COMMITTEE REPORTS: None.
VII. Adjournment: MOTION by Williams/Eickhoff to adjourn. MOTION CARRIED 5-0. The
meeting ended at 9:35 P.M.
Kim Banigan, Clerk-Treasurer
Approved 11-16-2026
Kim Banigan <clerk@towncg.net>
Wittewood Lane Stormwater Management Devices Maintenance
Nickolas Bubolz <nbubolz@tcengineers.net> Fri, Oct 30, 2026 at 1:20 PM
To: Kim Banigan <clerk@towncg.net>
Kim,
Based on discussions with Jason Tuggle of Dane County, there does not appear to be a recorded maintenance
agreement for the existing Wittewood stormwater basin; however, the basin remains subject to county maintenance
obligations. Jason Tuggle also recommended that the Town require an inspection and maintenance assessment from the
developer’s engineer of the basin.
In addition, if the Town is ultimately expected to maintain both the existing basin and the proposed stormwater
management facilities, I recommend that the Town restores the existing basin to its original as-built condition within one
year after the developer completes construction of the new stormwater management facilities adjacent to the basin. This
would ensure that the combined stormwater system begins its service life in a known and properly functioning condition.
Restoring the basin to its original design capacity would also provide a fair allocation of future maintenance costs. Once
the existing and proposed stormwater management facilities are functioning as a single system within the outlot, all
benefiting property owners, including both the new subdivision lots and the existing properties on Wittewood Lane, would
share in the long-term maintenance responsibility associated with the outlot and its stormwater management facilities.
Nick Bubolz
Nick Bubolz, P.E.
nbubolz@tcengineers.net
Town & Country Engineering, Inc.
6264 Nesbitt Road
Madison, WI 53719
(608) 273-3350
---------- Forwarded message ----------
From: "Tuggle, Jason" <Tuggle.Jason@danecounty.gov>
To: Nickolas Bubolz <nbubolz@tcengineers.net>
Cc: "Banigan, Kim" <clerk@tn.cottagegrove.wi.gov>, "Mergen, Elliott" <Mergen.Elliott@danecounty.gov>
Bcc:
Date: Fri, 30 Oct 2026 15:22:08 +0000
Subject: RE: Existing storm water pond maintenance agreement
Hi Nick,
11/4/26, 9:34 AM Town of Cottage Grove Mail - Wittewood Lane Stormwater Management Devices Maintenance
https://mail.google.com/mail/u/0/?ik=2d5bdb824f&view=pt&search=all&permmsgid=msg-f:1880499873092290516&simpl=msg-f:18804998730922905… 1/4
After our conversation I did some more digging and was able to locate the plans for the basin. You can download the
report and plans
here. There doesn’t appear to be a recorded maintenance agreement, which was not uncommon
at the time. However, maintenance would still be enforceable by the county under this permit.
I haven’t seen the stormwater plan for the new plat, but if it discharges to the Wittewood basin that additional runoff
would need to be accounted for. I would also suggest that the town require the developer’s engineer provide a
maintenance inspection report of the Wittewood basin before assuming maintenance responsibilities. I’m copying
Elliott Mergen in case he’s already provided comment on the preliminary plat.
Thanks,
Jason Tuggle
Water Resource Engineering Division
Phone: (608) 516-2275
https://lwrd.danecounty.gov/
From: Tuggle, Jason
Sent: Friday, October 30, 2026 7:55 AM
To: 'Nickolas Bubolz' <nbubolz@tcengineers.net>
Cc: Banigan, Kim <clerk@tn.cottagegrove.wi.gov>
Subject: RE: Existing storm water pond maintenance agreement
Hi Nick,
Our Land Conservation staff have had some history with the Witte farm at 2924 Hope Road. The area of interest was
part of a milkhouse waste septic/drain field. There’s an old transfer line from the farmstead across the road to that
area. It is not in operation anymore and I believe the buildings are being demolished right now. I’ve been trying to
contact someone about the building demo. If you have a current contact please let me know.
Thanks,
11/4/26, 9:34 AM Town of Cottage Grove Mail - Wittewood Lane Stormwater Management Devices Maintenance
https://mail.google.com/mail/u/0/?ik=2d5bdb824f&view=pt&search=all&permmsgid=msg-f:1880499873092290516&simpl=msg-f:18804998730922905… 2/4
Jason Tuggle
Water Resource Engineering Division
Phone: (608) 516-2275
https://lwrd.danecounty.gov/
From: Tuggle, Jason
Sent: Thursday, October 29, 2026 11:05 AM
To: 'Nickolas Bubolz' <nbubolz@tcengineers.net>
Cc: Banigan, Kim <clerk@tn.cottagegrove.wi.gov>
Subject: RE: Existing storm water pond maintenance agreement
Hi Nick,
I wasn’t able to find any records, but it looks like it was constructed around the time the ordinance went into effect.
I’ll do some checking with our Land Conservation staff and get back to you. It may have been something they worked
on.
Thanks,
Jason Tuggle
Water Resource Engineering Division
Phone: (608) 516-2275
https://lwrd.danecounty.gov/
11/4/26, 9:34 AM Town of Cottage Grove Mail - Wittewood Lane Stormwater Management Devices Maintenance
https://mail.google.com/mail/u/0/?ik=2d5bdb824f&view=pt&search=all&permmsgid=msg-f:1880499873092290516&simpl=msg-f:18804998730922905… 3/4
From: Nickolas Bubolz <nbubolz@tcengineers.net>
Sent: Wednesday, October 28, 2026 8:06 PM
To: Tuggle, Jason <Tuggle.Jason@danecounty.gov>
Cc: Banigan, Kim <clerk@tn.cottagegrove.wi.gov>
Subject: Existing storm water pond maintenance agreement
Jason, Do you know anything about this existing storm water management device, particular maintenance agreement or record plans? Nick Bubolz Nick Bubolz, P. E. nbubolz@ tcengineers. net Town & Country Engineering, Inc. 6264 Nesbitt Road Madison,
Jason,
Do you know anything about this existing storm water management device, particular maintenance
agreement or record plans?
Nick Bubolz
Nick Bubolz, P.E.
nbubolz@tcengineers.net
Town & Country Engineering, Inc.
6264 Nesbitt Road
Madison, WI 53719
(608) 273-3350
RE: Existing storm water pond maintenance agreement.eml
72K
11/4/26, 9:34 AM Town of Cottage Grove Mail - Wittewood Lane Stormwater Management Devices Maintenance
https://mail.google.com/mail/u/0/?ik=2d5bdb824f&view=pt&search=all&permmsgid=msg-f:1880499873092290516&simpl=msg-f:18804998730922905… 4/4
TOWN OF COTTAGE GROVE
TOWN BOARD
RESOLUTION 2026-11-05
GRANTING CONDITIONAL APPROVAL OF THE
PRELIMINARY PLAT FOR WITTEWOOD LANE
WHEREAS, Mom CG Farm, LLC (the "Developer") has submitted an application for
preliminary plat approval to the Town, for Wittewood Lane, a single-family residential
development;
WHEREAS, the proposed Wittewood Lane preliminary plat attached hereto as Exhibit A,
consists of Lots 1-10 for single family residential development, one Outlot containing storm water
management facilities, and publicly dedicated right-of-way, and is located in parts of the NW¼ of
the NW ¼ of Section 29 and the NE % of Section 30, all in Town 7 North, Range 11 East, Town
of Cottage Grove, Dane County, Wisconsin;
WHEREAS, the proposed Wittewood Lane preliminary plat has been reviewed by the
Town Engineer and Town Planner, who have determined the Developer's application for
preliminary plat approval meets the Town's requirements for preliminary plat approval;
WHEREAS, on October 28, 2026, the Plan Commission recommend the Town Board
approve the preliminary plat ofWittewood Lane with conditions;
WHEREAS, the proposed Wittewood Lane preliminary plat generally conforms to the
requirements of Town Ordinance§ 15.07;
NOW, THEREFORE, BE IT RESOLVED by the Town Board of the Town of Cottage
Grove as follows:
1. The Town Board hereby approves the preliminary plat for Wittewood Lane subject to the
following conditions:
a. The Developer is required to develop the preliminary plat in compliance with all
applicable State statutes and Town ordinances and in accordance with generally
accepted engineering standards and practices.
b. The Developer shall provide proof of rezoning by Dane County for the Wittewood
Lane preliminary plat, specifically the rezoning of Lots 1-10 to SFR-01.
c. The Developer shall obtain from County Land and Water Resources Department
(LWRD") all reviews and permits necessary for: (a) soil and erosion control within
the preliminary plat; and, (b) stormwater management facilities that fully satisfy
County requirements and address any stormwater runoff issues related to the
preliminary plat.
Page 1 of 3
d. The Developer shall provide to the Town written certification from the Developer's
engineer, in the same format as required by County LWRD, that the stormwater
management facilities as-built are in compliance with all applicable permits and are
operating in accordance with the approved design.
e. No lot in the Wittewood Lane preliminary plat may use a holding tank as a means
of sanitary waste disposal.
f. Pursuant to Town Ordinance§ 15.06(2), the Developer shall provide a report from
a soil/environmental scientist that reviews the plat for septic suitability.
g. The Developer shall dedicate Outlot 1 to the public on the proposed final plat.
h. The Developer shall provide the Town with a maintenance inspection report of all
stormwater maintenance facilities servicing the Wittewood Lane plat prior to the
Town assuming any ownership, control, possession, or maintenance responsibilities
regarding said facilities.
1. The Developer shall enter a Development Agreement with the Town regarding the
development of the preliminary plat acceptable to the Town Attorney. The
Development Agreement shall be drafted by the Town Attorney and reviewed by
the Town Engineer and Town Board. When approved by the Town Board, the
Development Agreement shall be executed by and between the Developer and
Town. The Final Plat shall not be signed by the Town until the Development
Agreement is fully executed.
j. The Developer shall obtain approval of the preliminary plat from the Cottage Grove
Fire Department and the Deer-Grove EMS District and present such approval to the
Town.
k. The Developer shall contact the local Postmaster to determine the required
configuration and placement of mailboxes to serve the new homes in the plat.
1. The Developer shall promptly reimburse the Town for all costs and expenses
incurred by the Town in connection with the review and approval of the preliminary
plat, including, but not limited to, the costs of professional services incurred by the
Town for the review and preparation of required documents, attendance at
meetings, or other related professional services.
m. The Developer shall address all comments in Paragraphs 2, 4, 5, 6, 7 of the Town
Planner's memorandum dated October 22, 2026.
n. The Developer shall address all of the Town Engineer's comments in his letter dated
October 22, 2026, to the satisfaction of the Town Engineer.
Page 2 of 3
o. The Developer shall order a site distance determination of the optimal placement
of a joint driveway for Lots 7 and 8.
p. The proposed final plat shall delineate buildable areas for Lots 9 and 10.
q. In addition to those outlined above, the Developer shall obtain all required
approvals from other approving authorities, as required by law.
r. The Town Board may refuse to approve any final plat if not submitted within the
time allotted in Wis. Stat. § 236.11 ( 1 )(b).
This Resolution was duly adopted btte Town Boar? of the Town of Cottage Grove , Dane
County, Wisconsin at a meeting on 0/ , Ze2k , by a vote o£ in
favor, Z-opposed, and _Onot voting.
TOWN OF COTTAGE
Attested by:
Ki
Incorporated by Reference:
Preliminary Plat for Wittewood Lane
Page 3 of 3
Clerk
Larry & Debra
Gausmann
FP-35
Michigan Wisconsin Pipe
Line, Doc. 1140873
Refernced to the Dane County
Coordinate System, with the West
line of the NW 1 /4 of Section 29
bearing S0008'55"W
Vertical datum = NAO 83 (2011)
Current Zoning is RR-8 and FP-35
proposed zoning is SFR-08, Petition #12295
Plat boundary = 18.904 acres
Dwg. No._050426 Date 6/1or2026
Sheet 1 of 1 rev. 9/28/26
DAVID
RIESOP
S-1551
DEERFIELD
WISCONSIN
Moms CG Farm LLC
FP-35
384.28'
$87°5331"W
16" x 20" CMP, North
invert = 864.50'
South invert = 865.38'
Prepared for Moms CG Farm LLC,
David Witte,
5802 Winnequah Road
Monona, Wi. 53716
Parts of the NW¼ of the NW¼ of Section 29 and the NE¼ of the NE¼ of Section 30, all
in Town 7 North, Range 11 East, Town of Cottage Grove, Dane County, Wisconsin
Preliminary Plat of
Wittewool Lame
David C. Riesop 5-1551
Surveyors Certificate
I, David C. Riesop, Wisconsin Registered Land Surveyor, hereby certify that I have surveyed, mapped
and monumented the lands as described hereon, and that such map is a true and correct
representation of the boundaries of the lands surveyed, and that I have fully complied with the State
of Wisconsin Administrative Code and Chapter 15 of the Land Division and Planning code of the Town
of Cottage Grove, in surveying and mapping the same, to the best of my knowledge and belief.
Wisconsin Mapping, LL.C
* ·urveying and mopping service
306 West Quarry Street, Deerfield, Wisconsin 53531
(608) 764-5602
• 6
1.2 acre
Jeffrey & Leah
Rhodes SFR-08
Amy J. Zap
FP-35
4.4
160'
%69
5
1.4 acre
c co
Verizon Fiber Optics
" along road r/w
16" x 20" CMP, North
invert = 863.42'
South invert = 864.49'
Barton Rev. Trust
SFR-08
4
1.4 acre
551.78'
.sen
3
1.4 acre
$87°54'23"W 939.82'
(N8728'40'E, 939.76'
HOPE ROAD
Hope Road to be dedicated
1 O' utility
easement. Jr
.t
N8839'20"E
WI e
Fred Witte & Sons Inc.
FP-35
t w
buried electric and phone along S. r/w line
Mike Kersels & Kathryn Grassel
RR-f
CSM 2646
Part of the NW¼ of the NW¼ of 5ection29 and the NE¼ of the NE¼ of Section 30, all in Town 7
North, Range 11 East, Town of Cottage Grove, Dane County, Wisconsin, described as follows:
Commencing at the Northwest corner of Section 29; thence S00°09'57"W along the West line of the
NW%-NW%, 656.74 feet to the centerline of Hope Road, and the point of beginning; thence
N88°16'16"E along said centerline, 139.40 feet; thence N8839'20"E, 551.78 feet along said centerline
of the point of curvature of a curve to the left, said curve having a central angle of 1630'38" and a
radius of 2240.00 feet; thence long chord of which bears N8024'01"E, 643.26 feet; thence
Northeasterly along the arc of said curve and centerline, 645.49 feet to its intersection with the East
line of the NW ¼ of the NW¼; thence S0018'16"W along said line, 739.69 feet to the Southeast
corner of said %- %; thence 587°53'31"W, 384.28 feet to the Southeast corner of Certified Survey
Map number 2646; thence N02"04'57"W, 177.76 feet to the point of curvature of a curve to the right,
said curve having a central angle of 909'15" and a radius of 251.00 feet, the long chord of which
bears $8308'59" W, 40.06 feet; thence Southwesterly along the arc of said curve, 40.10 feet; thence
N02°03'49"W, 66.00 feet to the North line of Wittewood Lane; thence 587°56'11"W along said line,
1004.50 feet to the point of curvature of a curve to the left, said curve having a central angle of
15°03'22" and a radius of 366.00 feet, the long chord of which bears 580°22'55"W, 95.90 feet; thence
Southwesterly along the arc of said curve and North line, 96.18 feet to a point of curvature of a curve
to the right, said curve having a central angle of 81 °35'49" and a radius of 25.00 feet, the long chord
of which bears N66°26'45"W, 32.67 feet; thence Northwesterly along the arc of said curve, 35.60 feet
to the East line of South Hope Road; thence 564°19'13"W, 33.00 feet to the centerline of said road;
thence N24°35'47"W along said centerline, 384.50 feet to the point of curvature of a curve to the
right, said curve having a central angle of 33°23'23" and a radius of 200.00 feet, the long chord of
which bears N07°54'01"W, 114.91 feet; thence Northwesterly along the arc of said curve and
centerline, 116.55 feet to its intersection with the centerline of Hope Road and the point of curvature
of a curve to the left, said curve having a central angle of 33°18'22" and a radius of 200.00 feet, the
long chord of which bears 575°04'31"E, 114.63 feet; thence Southeasterly along the arc of said curve
and centerline, 116.26 feet; thence N88°16'16"E along said Hope Road centerline, 474.05 feet to the
point of beginning. The above described containing 18.904 acres, being subject to rights of way for
Hope and South Hope Roads.
160'
art
0711-292-8 00-0
N
": (I)
o t :
o c cN
E
(I)
VJ
Northwest corner
of Section 29, Brass cap
monument found, 18" down
� Si uo to co
Lo O
io % .C
2 do z �
N88° 16'16"E
139.40'
160'
l'-1 � � co
o
0
o o z
0
c
II"'
m C
0
• & 4
u ¢
0
u .#
1 2
1.4 acre o 1.4 acre
co co
• • !I"'
·" n
Outlot 1
0711-301-8002-0
474.05'
2 x2.5 RCP,
South Invert =
858.43'
w } corner
Sec.29-7-11,
Aluminum Monument
found
a determined
ficial wetland and
excepted from
regulations. WI DNR
9/14/26
N88°16'16"E
354.6s°
SW 1/4-NW 1/4
30 29
19 20
Location Sketch
E 1/2 of NE 1/4, 30-7-11
W 1/2 of NW 1/4, 29-7-11
1" = 1000'
Kim Banigan, Town Clerk
Legend
= 1" iron pipe found, unless
otherwise noted
= }" diameter by 18" long rebar set
= transformer and phone pedastal
When different, parenthesis indicate recorded
as values
Donals & Theresa
Dummer FP-1
Towonship Approval
This Preliminary Plat has been approved per Town of Cottage Grove
Plan Commission action of_and Township Board
action dated _
Scale 1"= 100'
0���5�011111111111111111�0;::;0����20.0
18" CMP
East invert = 853.56'
West Invert= 853.67'
South Hope Road to
be dedicated
26" x 48" RCP. West
invert = 854.11'
East invert = 853.50'
V weir = 853.63'
•
0
a
Source: Town of Cottage Grove website. First collected Nov 23, 2026.