Division of Transportation
System Development
Northwest Region – Spooner Office
W7102 Green Valley Road
Spooner, WI 54801
Governor Tony Evers
Secretary Kristina Boardman
Internet: wisconsindot.gov
Telephone: (715) 635-2184
Facsimile (FAX): (715) 635-2309
Email: nwr.dtsd@dot.wi.gov
Date: Friday, Nov. 21, 2025
Subject: Public Involvement Meeting Notice
Project ID: 1580-00-02/72
HWY: US 8
Title: Cameron - Ladysmith
Limits: County SS South to 480’ east of County SS North
County: Barron County
The Wisconsin Department of Transportation (WisDOT), in cooperation with Short Elliott Hendrickson Inc. (SEH), will hold a
public involvement meeting at the date and time listed below. The meeting is regarding the roadway project on US 8 within
the village of Cameron, WI. This meeting is for property owners and others interested in the project.
• Time: 5:30 to 7:30 p.m.
o A brief presentation is planned for 5:45 p.m.
• Date: Wednesday, Dec. 3, 2025
• Location: Mosaic Technologies -- Mosaic Conference Room
401 S. 1st St., Cameron, WI 54822
The informational meeting is meant to provide the public with an opportunity to learn about and comment on the proposed
project. Following the presentation, the meeting will follow an open-house format during which representatives from WisDOT
and SEH will be available to answer questions about the proposed scope of work.
WisDOT is proposing to reconstruct the existing roadway with 8.5 inches of concrete pavement. Existing curb ramps will be
replaced to meet current Americans With Disabilities Act (ADA) standards. New sidewalk will be added to complete the
existing network. A two-way left-turn lane (TWLTL) is proposed to be installed from Sunnyside Avenue to County W. Storm
sewer along the route is also proposed to be replaced as are the existing traffic signals at the intersection of US 8/County
W/County SS.
During construction, work also is proposed at the railroad crossing just north of the intersection of US 8/County W/County SS.
The proposed work at the rail crossing surface includes signal replacement and the addition of a 100-foot concrete median
and new crossing surface. The village of Cameron also plans to replace the sanitary sewer and water mainline utilities and
services along the roadway.
Construction is proposed to be completed with this segment of US 8 closed to through traffic and detoured. A proposed
signed detour for through traffic on existing County SS would utilize County OO south of Cameron, US 53 and County O in
Rice Lake. Existing US 8 traffic is proposed to be detoured on County W. Work within the intersection of US 8/County
SS/County W is proposed to be staged to maintain traffic in the area as much as possible. A short-term full closure of County
SS, north of the intersection with County W, may be required to complete work on the railroad crossing surface. Temporary
pedestrian facilities are proposed to be provided where existing sidewalks are impacted by work. The contractor would be
required to provide access to any properties along the work zone, however, there may be very short periods where driveway
access is disrupted.
If you have questions or concerns that may contribute to the development of this project, we encourage you to provide
comments by Dec. 18, 2025. We also encourage you to share this information with others who may be affected by this
project. Comments may be provided by email (preferred) or phone to:
• Matthew VanNatta, WisDOT project manager: matthew.vannatta@dot.wi.gov or (715) 392-7966
• Vance Powers, WisDOT consultant project manager: vpowers@sehinc.com or (715) 861-1945
Please visit the project website to keep up with project details as they progress: https://wisconsindot.gov/Pages/projects/by-
region/nw/us8cameron/default.aspx.
Sincerely,
Matthew VanNatta
Matthew VanNatta, P.E.