US 8 Roadway Project Information
1580-00-02 Page 1
Project ID 1580-00-02
Cameron – Ladysmith
County SS S to 480’ East of County SS N
US 8
Barron County
Purpose of Project
The purpose of the proposed project is to address the deficiencies on US 8 to provide a safe
and efficient transportation system.
The need for the proposed project is to address the deteriorating US 8 pavement, which was
last resurfaced in 2003, update substandard curb ramps, drainage deficiencies, sanitary and
water utilities and railroad crossing signals.
Project Information
The Wisconsin Department of Transportation is proposing to reconstruct US 8 within the project
limits with concrete pavement. Curb & gutter would be replaced to improve drainage. Curb
ramps at designated sidewalk crossings would be replaced to meet current ADA standards.
Some new sidewalk is also proposed to be added. A Two Way Left Turn Lane (TWLTL) is
proposed to be installed from Sunnyside Ave to the intersection with County W. Traffic signals
at the intersection of US 8 / County W / County SS are also proposed to be replaced. Work
would take place on the railroad crossing on CTH SS including replacing the crossing surface
and signals. The Village plans to replace sanitary sewer and water mainlines and services as
part of the project. See the attached project location map on the next page. The black lines
represent the anticipated edge or roadway, back of curb and gutter, and/or sidewalk. Larger
displays will be presented at the Public Involvement Meeting.
Project Location
The proposed project is approximately 0.9 miles long along existing US 8, starting from the
south intersection with County SS, along US 8 to the north, ending on US 8 just to the east of
the north intersection with County SS.
Project Timeline
November/December 2025
• Hold local officials and public involvement meetings
• Complete 30% plans
• Complete environmental document
August 2026
• Complete 60% plans
• Submit design study report
November 2026
• Complete right-of-way plat and begin right-of-way process
US 8 Roadway Project Information
1580-00-02 Page 2
May 2028
• Submit final plans
Spring 2029
• Start construction (anticipated)