Public Involvement Meeting
US 8, Barron County
County SS South to 480’ East of County SS North
WisDOT Project ID: 1580-00-02 (72)
Dec. 3, 2025
Agenda
1) Project Location
2) Purpose and Need
3) Proposed Improvements
4) Traffic Impacts
5) Detour
6) Other Impacts
7) Project Timeline
8) Project Contacts
9) Public Input
Project Location
Begin Project Location
County SS South
End Project Location
480 feet east of County SS North
Project Location
Railroad Crossing Work
County SS North, north of US 8
Purpose and Need
• Purpose: To preserve the function, operation and safety of this route in the
overall transportation system.
• Needs:
Pavement Deterioration
Substandard Curb Ramps
Drainage Deficiencies
Aging Village Utilities
Railroad Crossing Needs
Proposed Improvements
• WisDOT work includes:
Reconstructing roadway with 8.5-inches concrete pavement
Replacing storm sewer
Replacing curb, gutter and curb ramps
Adding sidewalk at several locations
Widening the US 8/County W/County SS intersection and replacing traffic
signals
Adding a two-way left-turn lane (TWLTL) from Sunnyside Avenue to County W
Proposed Improvements
• Village of Cameron work includes:
Replacing sanitary sewer and water main
• Work at the railroad crossing on the north leg of County SS includes:
Replacing the crossing surface
Replacing the crossing signals
Adding a 100-foot concrete median
Traffic Impacts
• During construction:
US 8 will be closed from County SS South to County W, and through
traffic will be detoured.
US 8/County SS/County W intersection construction will be staged to
maintain traffic as much as possible.
Motorists will encounter short-term closure of the US 8/County
SS South intersection for pavement work and County SS north
of US 8 for railroad crossing work.
Detour: US 8
• Through traffic on US 8 will be detoured using County W.
• The US 8/County SS/County W intersection will be kept open
for east and westbound traffic.
Detour: County SS
• North- and southbound traffic on County SS will be detoured
using County OO, US 53 and County O.
Northbound on
County SS
Southbound on
County SS
Other Impacts
• During construction:
Temporary pedestrian facilities will be provided where
sidewalk improvements are proposed.
There will be periods where driveway access is disrupted, but the
contractor will provide advanced notice of any access restrictions
to property owners.
Project Timeline
• December 2025: Hold local officials and public involvement meetings
on Dec. 3 and solicit public comments on work through Dec. 18
• August 2026: Project plans approximately 60% complete
• November 2026: Identify right-of-way needs
• Fall/Winter 2026: Reach out to the public again for input
• May 2028: Submit final plans
• 2029: Complete construction
Project Contacts
• Andrew Peterson, P.E.
WisDOT Consultant Project Manager
(608) 792-6851 or apeterson@correinc.com
• Matt Van Natta, P.E.
WisDOT Project Supervisor
(715) 392-7966 or matthew.vannatta@dot.wi.gov
• Vance Powers, P.E.
SEH Project Manager
(715) 861-1945 or vpowers@sehinc.com
Public Input
• Submit comments on the proposed project by Dec. 18, 2025, by:
Email: matthew.vannatta@dot.wi.gov
Mail: Wisconsin Department of Transportation
W7102 Green Valley Road
Spooner, WI 54801
Attn.: Matt Van Natta
Comment form:
wisconsindot.gov/Pages/projects/by-
region/nw/us8cameron/default.aspx