Chairperson Michael Wandschneider called the meeting to order at 6:00 p.m. Roll call
was taken: Michael Wandschneider, Brett Edgerle and Kelly Kasten were present. Staff
members present: Mike Kitzerow and Cindi Gamb.
Public Comment – none.
Approval of Meeting Minutes from December 8, 2025 – Motion by Brett Edgerle, second
by Kelly Kasten to approve the meeting minutes from December 8, 2025. Motion
carried.
Business
1. Review and Recommend:
a. Approve Woodland Road paving project - $160,000 budgeted, estimate from the
Sheboygan County Highway Department is $164,000. This includes pulverizing
and overlay from northern Village limits south to the Highway 23 overpass on
Woodland Road. Motion by Mike Wandschneider, second by Brett Edgerle to
recommend the Village Board approve the Woodland Road paving project for
$164,000. Motion carried.
b. Purchase loader attachment for tractor - $5,800 budgeted. Motion by Brett
Edgerle, second by Mike Wandschneider to recommend the Village Board
approve the purchase of a loader attachment from Feldmann Sales and Service,
Inc. for $5,625. Motion carried.
c. Purchase brush cutter – $6,500 budgeted. DPW has been renting a brush cutter
for maintaining retention ponds. Motion by Brett Edgerle, second by Mike
Wandschneider to recommend the Village Board approve the purchase of a
brush cutter for $6,500 from Bruggink’s Construction Equipment Inc. Motion
carried.
d. Approve agreement with Excel Engineering for Village Hall HVAC engineering –
$25,700 budgeted. The HVAC system in Village Hall is an outdated air-controlled
system, and it is becoming harder to find companies that can service the system.
Also, with the Police Department addition a few years ago, the air conditioning
unit is not large enough for the building. Motion by Mike Wandschneider, second
by Brett Edgerle to recommend the Village Board approve the contract with Excel
Engineering, Inc. for $25,700 to design and assess the HVAC at Village Hall.
Motion carried.
e. Approve Greenfield Drive crosswalk project – $32,000 budgeted. Cost is to
purchase equipment and have it programmed; the Department of Public Works
will complete the installation. Motion by Mike Wandschneider, second by Kelly
Kasten to recommend the Village Board approve the quote from TAPCO for
replacement of crosswalk equipment for a cost not to exceed $31,000. Motion
carried.
f. Approve Ravine Park storm line project – $20,000 budgeted. Motion by Brett
Edgerle, second by Kelly Kasten to recommend the Village Board approve the
quote from Korff Plumbing for the Ravine Park storm line for an amount not to
exceed $17,000. Motion carried.
g. Approve Lost Woods Park parking lot blacktop project – $45,000 budgeted,
estimate from Sheboygan County Highway Department is $45,000 to regrade
and blacktop the gravel parking lot. Motion by Brett Edgerle to recommend the
Village Board approve an amount not to exceed $45,000 to blacktop Lost Woods
Park parking lot. Motion failed for lack of second.
h. Approve Ehlers sewer study phases two and three – Motion by Brett Edgerle,
second by Kelly Kasten to recommend the Village Board approve phases two
and three of Ehlers & Associates, Inc. sewer study for $6,250. Motion carried.
Adjournment
Motion by Brett Edgerle, second by Mike Wandschneider to adjourn the meeting at 6:33
p.m. Motion carried.