Highway Safety Minutes 07-16-2026
Buffalo County · Buffalo County · meeting of Jul 16, 2026 · Minutes
Open the original document More from Buffalo County
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
P:\Highway Safety\2026\7.16.2026 Highway Safety Meeting\07-16-2026 Draft HS Minutes.docx 1
HIGHWAY SAFETY COMMISSION MEETING
Committee/Board: HIGHWAY SAFETY COMMISSION
Date of Meeting: Thursday , July 1 6 th , 202 6
Location: 3 rd Floor Conference Room
Buffalo County Courthouse - Alma , Wisconsin
Buffalo County Highway Safety Commission members present were:
NAME: REPRESENTING
Josh Reed -Excused School Districts
Jake Laehn Sheriff ’s Office
Dan Kontos WI DOT
Rick Tumaniec WI DOT
Jerilyn Baures Population
Beth Sass Medical
Kelly Johnston Highway Department
Steve Wall Emergency Management
Jason Bakken WI State Patrol
Kasondra Serum Coordinator, Sheriff ’s Office
Jamie Weaver Public Health
Others : In person: Ryan Howell , Lee Engfer, Gill Adams
#1 /2 . Call to Order/Roll call :
Jerilyn Baures called the meeting to order at 1:00 pm.
#3. Verification of Open Meetings Law Compliance:
Kassie advised that the agenda had been posted.
#4. Approve Agenda:
There were no changes to the agenda. Kelly Johnston made a motion to approve the
agenda, seconded by Rick Tumaniec.
# 5 . Approval of Previous Meeting Minutes:
There were no changes to the previous meeting minutes.
Jamie Weaver made a motion to appro ve the previous minutes , seconded by Steve Wall .
#6. Public Comment :
None
P:\Highway Safety\2026\7.16.2026 Highway Safety Meeting\07-16-2026 Draft HS Minutes.docx 2
# 7 . Jake Laehn – Sheriff ’s Office upda te :
Jake Laehn stated they have had a recent extra patrol CAD for County Rd A for the Culvert
report for speeding. La e hn stated there have been 3 fatal motorcycle accidents this quarter
and Ryan Howell will give more information on them. Howell said the first motorcycle
accident was on April 22 and it was a 89-year-old male that was wearing a helmet and he
missed a turn, the second one was on May 30 th on Hy 37 and they had lost control and they
were not wearing a helmet, and the last one was on June 6 th on hy 37 as well and that one
was caused by a deer running into him and throwing him off of the bok and he was not
wearing a helmet
# 8 . Steve Wall- Emergency Management Report:
None.
# 9 . Kelly Johnston- Highway Department Update:
Kelly stated that they have one round of mowing completed on the County Roads, and the
state roads are being completed now. After that then round two on the County roads will
start. Count Rd I from County Rd D to center creed is milled and gravel, they are preparing
for paving. Count Rd. AA from County Rd K to Swan Ln is milled and gravel and they are
preparing for paving. County Rd I from County R d . II to Mike Varenick Rd will be getting an
asphalt overlay. Chip Seal operations will be happening in August. County Rd. Z, F, C, XX ,
X, Hagness Rd., Hansen Rd., and Nelson Rd. Highway 10 from Mckinley st to the Pepin
County line they will be finishing up culvert work this week and planning on milling and
paving next week. They will be finishing up the last of the Township grader patching next
week.
# 10 . Dan Kontos -DOT update:
Dan Kontos presented power point that was sent out prior to the meeting.
# 11 . Rick Tumaniec -DOT update:
Rick stated that the Waumandee Creek Bridge overlay project will be staged half at a time
using temporary signals and should be a 60-day project. There is an anticipated August
start after environmental restrictions are over and the tentative completion of September
21 st . The next project is state highway 54 Mn side and WI state line hy 35 resurface project;
traffic will be handled with flagging operations. It started on April 24 th , time was suspended
until August 15 th and there are some punch list items left to complete as well as culvert work
once environmental restrictions are lifted. Hy 35 to Indian Creek Road resurface project,
traffic will be handled with flagging operations. This project started on April 24 th . Time was
suspended until August 15 th and there were some punch list items left to complete as well
as culvert work once environmental restriction has been lifted. The last project updated was
hy 10 Pepin County line to County rd. A resume project. Traffic will be handled with flagging
operations, and this started on June 30 th and is expected to complete in Mid-August.
P:\Highway Safety\2026\7.16.2026 Highway Safety Meeting\07-16-2026 Draft HS Minutes.docx 3
# 1 2 . Jeri Baures-Population update :
Jeri stated that County Rd OO speed limit change to 25MPH has been positive. Jeri also
informed everyone that Blaine Proue, which was the Chief Deputy many years ago had
passed away.
# 1 3 . Josh Reed-Education update: Excused
None.
# 1 4 . Jason Bakken - WSP update:
Bakken stated that Josh Reed wanted state patrol to come into his Drivers Ed class to give
some education, Karl Kent went in and did a speech. Bakken stated they are training new
troopers, the class started on Monday, and they had 37 and are down to 35 in the first week,
and there is 21 weeks to go. They are looking at doing a lateral class. Bakken stated they
are still short on Troopers. They have BOTS OWI coming up.
#1 5 . Beth Sass - Medical update:
None.
#16. Jamie Weaver-Public Health Update:
Jamie said that if anyone runs into the issue of someone not having a car seat to reach out
to Health and Human Services, they have some.
#17. Future Agenda Items:
Jason Bakken would like the flood run listed on the agenda for the next meeting in October.
#1 8 . Next meeting date and time :
The next meeting is set for October 1 5 th at 1pm.
#1 9 . Adjournment:
A djourn ed at 1:45 p.m.
P:\Highway Safety\2026\7.16.2026 Highway Safety Meeting\07-16-2026 Draft HS Minutes.docx 4
Respectfully
submitted:
____________________________
__
Kasondra Serum , Co ordinator
Source: Buffalo County website. First collected Oct 14, 2026.