Construction Notice Start Letter_Belmont Ave_Belmont Ct_Merged 20240301
City of Neenah · Winnebago County · meeting of Mar 11, 2024 · Notices
Open the original document More from City of Neenah
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
Neenah
W I S C O N S I N
Department of Public Works
211 Walnut St., P.O. Box 426, Neenah, WI 54957-0426
Phone: 920-886-6240 Fax: 920-886-6250
March 1, 2024
KEVIN LECLAIRE
564 BELMONT AVE
NEENAH WI 54956
RE: 564 BELMONT AVE
The City's contractor, David Tenor Corporation, will begin utility and street construction on
Belmont Avenue, Belmont Court, Cedar Street, and Stevens Street in the next week(s).
Construction will be completed by November 2024. We will need your help to make this a
successful project.
General Project Sequence
The project will consist of the following work:
Install new sanitary sewer main
Install new water main
Install new sanitary laterals and water services
Install new storm sewer
Rest period (Contractor will not work for 1 month to allow trenches to settle more than
can be achieved with mechanical compaction)
Remove existing roadway (asphalt, and the existing stone base)
Install geogrid and new aggregate road base
Install/repair concrete curb & gutter and place concrete pavement
Repair/replace existing concrete sidewalk/driveway aprons and install new sidewalk
Restore terrace areas with topsoil, grass seed, fertilizer, and hydro-mulch
Install new hot mix asphalt roadway (two lifts)
Garbage / Postal Service / Emergency Services
During construction, refuse and recycling pick-up will continue on your regularly
scheduled day. Please have your carts out before 6:30 A.M. when the construction crew
is working on your street. Carts should be placed on the street or terrace area.
The postal service will continue delivering and collecting mail as usual.
Emergency services have been notified of the construction activity and will plan
accordingly.
February 28, 2024
P a g e | 2
Parking and Accessibility
The streets will be open to local traffic only and residents will have access to their driveways
during the majority of the project. Parking will not be permitted on the streets during the
construction day (7 AM to 5 PM). Parking is available on adjacent streets. Other than NO
PARKING zones, standard parking restrictions will be waived on adjacent streets for those
vehicles displaying one of the enclosed Construction Parking Permits. There will be a period
of time when residents will not have access to their driveways. This will occur during the
concrete street paving and during, curb/gutter and driveway construction, and will last
approximately 3 weeks. At least 24 hours advance notice will be given when limiting driveway
access.
Terrace Restoration
The contractor will complete the terrace restoration adjacent to your property. After topsoil is
placed and leveled, a mix of grass seed, fertilizer and mulch will be placed. Please water this
daily to keep the soil moist until the new grass is well established. Please mow the grass and
weeds when they reach 6". The grass should overtake the weeds with continued watering and
mowing. The contractor will notify you when to begin watering.
Private Sewer Lateral Replacement
Please return your Property Owner Authorization Form (pink sheet) if you have not
already done so. All sanitary laterals will be replaced to the homes unless previously relayed.
The cost estimate for the sanitary lateral for the property owner share is approximately
$3,000.00.
Water Services Replacement
If there is lead or galvanized pipe on the Utility-owned portion of the service line (from the
main to the curb stop), this portion will be replaced at no cost to you. However, the
replacement of the private lead or galvanized service (from the curb stop to the water meter) is
the responsibility of the property owner. Property owners have the choice of replacing the
water service before construction begins or having the service line replaced as part of the
construction contract. Generally, having the service line replaced as part of the construction
contract is easier and less expensive. The cost of replacing a private service line during a
construction event and in conjunction with a sanitary lateral replacement is estimated to be
approximately $1,500.00.
Carriage Walk
If a carriage walk exists adjacent to your property, between the City sidewalk and roadway, it
will be removed with our project. If you would like to pay for this to remain, please contact the
City for an estimated cost.
During the course of this project, there will be inconveniences such as noise, travel delays,
dust, and other issues associated with street construction. The City of Neenah and the
contractor are committed to working with the property owners to make this project run as
smoothly as possible.
February 28, 2024
P a g e | 3
If you would like to receive weekly emails on construction updates, you can sign up for the
Construction Newsletter on the City of Neenah webpage (www.ci.neenah.wi.us) under the
Department of Public Works. We thank you for your help and patience during this construction
project. Please contact our department if you require special consideration for accessibility. If
you have any questions, contact the individuals listed below or the Public Works Department at
920-886-6240.
City of Neenah Engineer ............... Jason Eckhart ......................... 920-886-6246
City of Neenah Engineer ............... Heath Kummerow ................. 920-886-6245
David Tenor Corporation... ........... David Tenor ........................... 920-360-9246
Sincerely,
Gerry Kaiser, PE
Director of Public Works
cc: Mayor Lang
Police Chief Olson
Fire Chief Kloehn
Aldermen
Neenah
W I S C O N S I N
Department of Public Works
211 Walnut St., P.O. Box 426, Neenah, WI 54957-0426
Phone: 920-886-6240 Fax: 920-886-6250
March 1, 2024
DIANE JANSEN
558 BELMONT AVE
NEENAH WI 54956
RE: 558 BELMONT AVE
The City's contractor, David Tenor Corporation, will begin utility and street construction on
Belmont Avenue, Belmont Court, Cedar Street, and Stevens Street in the next week(s).
Construction will be completed by November 2024. We will need your help to make this a
successful project.
General Project Sequence
The project will consist of the following work:
Install new sanitary sewer main
Install new water main
Install new sanitary laterals and water services
Install new storm sewer
Rest period (Contractor will not work for 1 month to allow trenches to settle more than
can be achieved with mechanical compaction)
Remove existing roadway (asphalt, and the existing stone base)
Install geogrid and new aggregate road base
Install/repair concrete curb & gutter and place concrete pavement
Repair/replace existing concrete sidewalk/driveway aprons and install new sidewalk
Restore terrace areas with topsoil, grass seed, fertilizer, and hydro-mulch
Install new hot mix asphalt roadway (two lifts)
Garbage / Postal Service / Emergency Services
During construction, refuse and recycling pick-up will continue on your regularly
scheduled day. Please have your carts out before 6:30 A.M. when the construction crew
is working on your street. Carts should be placed on the street or terrace area.
The postal service will continue delivering and collecting mail as usual.
Emergency services have been notified of the construction activity and will plan
accordingly.
February 28, 2024
P a g e | 2
Parking and Accessibility
The streets will be open to local traffic only and residents will have access to their driveways
during the majority of the project. Parking will not be permitted on the streets during the
construction day (7 AM to 5 PM). Parking is available on adjacent streets. Other than NO
PARKING zones, standard parking restrictions will be waived on adjacent streets for those
vehicles displaying one of the enclosed Construction Parking Permits. There will be a period
of time when residents will not have access to their driveways. This will occur during the
concrete street paving and during, curb/gutter and driveway construction, and will last
approximately 3 weeks. At least 24 hours advance notice will be given when limiting driveway
access.
Terrace Restoration
The contractor will complete the terrace restoration adjacent to your property. After topsoil is
placed and leveled, a mix of grass seed, fertilizer and mulch will be placed. Please water this
daily to keep the soil moist until the new grass is well established. Please mow the grass and
weeds when they reach 6". The grass should overtake the weeds with continued watering and
mowing. The contractor will notify you when to begin watering.
Private Sewer Lateral Replacement
Please return your Property Owner Authorization Form (pink sheet) if you have not
already done so. All sanitary laterals will be replaced to the homes unless previously relayed.
The cost estimate for the sanitary lateral for the property owner share is approximately
$3,000.00.
Water Services Replacement
If there is lead or galvanized pipe on the Utility-owned portion of the service line (from the
main to the curb stop), this portion will be replaced at no cost to you. However, the
replacement of the private lead or galvanized service (from the curb stop to the water meter) is
the responsibility of the property owner. Property owners have the choice of replacing the
water service before construction begins or having the service line replaced as part of the
construction contract. Generally, having the service line replaced as part of the construction
contract is easier and less expensive. The cost of replacing a private service line during a
construction event and in conjunction with a sanitary lateral replacement is estimated to be
approximately $1,500.00.
Carriage Walk
If a carriage walk exists adjacent to your property, between the City sidewalk and roadway, it
will be removed with our project. If you would like to pay for this to remain, please contact the
City for an estimated cost.
During the course of this project, there will be inconveniences such as noise, travel delays,
dust, and other issues associated with street construction. The City of Neenah and the
contractor are committed to working with the property owners to make this project run as
smoothly as possible.
February 28, 2024
P a g e | 3
If you would like to receive weekly emails on construction updates, you can sign up for the
Construction Newsletter on the City of Neenah webpage (www.ci.neenah.wi.us) under the
Department of Public Works. We thank you for your help and patience during this construction
project. Please contact our department if you require special consideration for accessibility. If
you have any questions, contact the individuals listed below or the Public Works Department at
920-886-6240.
City of Neenah Engineer ............... Jason Eckhart ......................... 920-886-6246
City of Neenah Engineer ............... Heath Kummerow ................. 920-886-6245
David Tenor Corporation... ........... David Tenor ........................... 920-360-9246
Sincerely,
Gerry Kaiser, PE
Director of Public Works
cc: Mayor Lang
Police Chief Olson
Fire Chief Kloehn
Aldermen
Neenah
W I S C O N S I N
Department of Public Works
211 Walnut St., P.O. Box 426, Neenah, WI 54957-0426
Phone: 920-886-6240 Fax: 920-886-6250
March 1, 2024
DAVID & JANE PETRI
552 BELMONT AVE
NEENAH WI 54956
RE: 552 BELMONT AVE
The City's contractor, David Tenor Corporation, will begin utility and street construction on
Belmont Avenue, Belmont Court, Cedar Street, and Stevens Street in the next week(s).
Construction will be completed by November 2024. We will need your help to make this a
successful project.
General Project Sequence
The project will consist of the following work:
Install new sanitary sewer main
Install new water main
Install new sanitary laterals and water services
Install new storm sewer
Rest period (Contractor will not work for 1 month to allow trenches to settle more than
can be achieved with mechanical compaction)
Remove existing roadway (asphalt, and the existing stone base)
Install geogrid and new aggregate road base
Install/repair concrete curb & gutter and place concrete pavement
Repair/replace existing concrete sidewalk/driveway aprons and install new sidewalk
Restore terrace areas with topsoil, grass seed, fertilizer, and hydro-mulch
Install new hot mix asphalt roadway (two lifts)
Garbage / Postal Service / Emergency Services
During construction, refuse and recycling pick-up will continue on your regularly
scheduled day. Please have your carts out before 6:30 A.M. when the construction crew
is working on your street. Carts should be placed on the street or terrace area.
The postal service will continue delivering and collecting mail as usual.
Emergency services have been notified of the construction activity and will plan
accordingly.
February 28, 2024
P a g e | 2
Parking and Accessibility
The streets will be open to local traffic only and residents will have access to their driveways
during the majority of the project. Parking will not be permitted on the streets during the
construction day (7 AM to 5 PM). Parking is available on adjacent streets. Other than NO
PARKING zones, standard parking restrictions will be waived on adjacent streets for those
vehicles displaying one of the enclosed Construction Parking Permits. There will be a period
of time when residents will not have access to their driveways. This will occur during the
concrete street paving and during, curb/gutter and driveway construction, and will last
approximately 3 weeks. At least 24 hours advance notice will be given when limiting driveway
access.
Terrace Restoration
The contractor will complete the terrace restoration adjacent to your property. After topsoil is
placed and leveled, a mix of grass seed, fertilizer and mulch will be placed. Please water this
daily to keep the soil moist until the new grass is well established. Please mow the grass and
weeds when they reach 6". The grass should overtake the weeds with continued watering and
mowing. The contractor will notify you when to begin watering.
Private Sewer Lateral Replacement
Please return your Property Owner Authorization Form (pink sheet) if you have not
already done so. All sanitary laterals will be replaced to the homes unless previously relayed.
The cost estimate for the sanitary lateral for the property owner share is approximately
$3,000.00.
Water Services Replacement
If there is lead or galvanized pipe on the Utility-owned portion of the service line (from the
main to the curb stop), this portion will be replaced at no cost to you. However, the
replacement of the private lead or galvanized service (from the curb stop to the water meter) is
the responsibility of the property owner. Property owners have the choice of replacing the
water service before construction begins or having the service line replaced as part of the
construction contract. Generally, having the service line replaced as part of the construction
contract is easier and less expensive. The cost of replacing a private service line during a
construction event and in conjunction with a sanitary lateral replacement is estimated to be
approximately $1,500.00.
Carriage Walk
If a carriage walk exists adjacent to your property, between the City sidewalk and roadway, it
will be removed with our project. If you would like to pay for this to remain, please contact the
City for an estimated cost.
During the course of this project, there will be inconveniences such as noise, travel delays,
dust, and other issues associated with street construction. The City of Neenah and the
contractor are committed to working with the property owners to make this project run as
smoothly as possible.
February 28, 2024
P a g e | 3
If you would like to receive weekly emails on construction updates, you can sign up for the
Construction Newsletter on the City of Neenah webpage (www.ci.neenah.wi.us) under the
Department of Public Works. We thank you for your help and patience during this construction
project. Please contact our department if you require special consideration for accessibility. If
you have any questions, contact the individuals listed below or the Public Works Department at
920-886-6240.
City of Neenah Engineer ............... Jason Eckhart ......................... 920-886-6246
City of Neenah Engineer ............... Heath Kummerow ................. 920-886-6245
David Tenor Corporation... ........... David Tenor ........................... 920-360-9246
Sincerely,
Gerry Kaiser, PE
Director of Public Works
cc: Mayor Lang
Police Chief Olson
Fire Chief Kloehn
Aldermen
Neenah
W I S C O N S I N
Department of Public Works
211 Walnut St., P.O. Box 426, Neenah, WI 54957-0426
Phone: 920-886-6240 Fax: 920-886-6250
March 1, 2024
MICHAEL SYSINGER
546 BELMONT AVE
NEENAH WI 54956
RE: 546 BELMONT AVE
The City's contractor, David Tenor Corporation, will begin utility and street construction on
Belmont Avenue, Belmont Court, Cedar Street, and Stevens Street in the next week(s).
Construction will be completed by November 2024. We will need your help to make this a
successful project.
General Project Sequence
The project will consist of the following work:
Install new sanitary sewer main
Install new water main
Install new sanitary laterals and water services
Install new storm sewer
Rest period (Contractor will not work for 1 month to allow trenches to settle more than
can be achieved with mechanical compaction)
Remove existing roadway (asphalt, and the existing stone base)
Install geogrid and new aggregate road base
Install/repair concrete curb & gutter and place concrete pavement
Repair/replace existing concrete sidewalk/driveway aprons and install new sidewalk
Restore terrace areas with topsoil, grass seed, fertilizer, and hydro-mulch
Install new hot mix asphalt roadway (two lifts)
Garbage / Postal Service / Emergency Services
During construction, refuse and recycling pick-up will continue on your regularly
scheduled day. Please have your carts out before 6:30 A.M. when the construction crew
is working on your street. Carts should be placed on the street or terrace area.
The postal service will continue delivering and collecting mail as usual.
Emergency services have been notified of the construction activity and will plan
accordingly.
February 28, 2024
P a g e | 2
Parking and Accessibility
The streets will be open to local traffic only and residents will have access to their driveways
during the majority of the project. Parking will not be permitted on the streets during the
construction day (7 AM to 5 PM). Parking is available on adjacent streets. Other than NO
PARKING zones, standard parking restrictions will be waived on adjacent streets for those
vehicles displaying one of the enclosed Construction Parking Permits. There will be a period
of time when residents will not have access to their driveways. This will occur during the
concrete street paving and during, curb/gutter and driveway construction, and will last
approximately 3 weeks. At least 24 hours advance notice will be given when limiting driveway
access.
Terrace Restoration
The contractor will complete the terrace restoration adjacent to your property. After topsoil is
placed and leveled, a mix of grass seed, fertilizer and mulch will be placed. Please water this
daily to keep the soil moist until the new grass is well established. Please mow the grass and
weeds when they reach 6". The grass should overtake the weeds with continued watering and
mowing. The contractor will notify you when to begin watering.
Private Sewer Lateral Replacement
Please return your Property Owner Authorization Form (pink sheet) if you have not
already done so. All sanitary laterals will be replaced to the homes unless previously relayed.
The cost estimate for the sanitary lateral for the property owner share is approximately
$3,000.00.
Water Services Replacement
If there is lead or galvanized pipe on the Utility-owned portion of the service line (from the
main to the curb stop), this portion will be replaced at no cost to you. However, the
replacement of the private lead or galvanized service (from the curb stop to the water meter) is
the responsibility of the property owner. Property owners have the choice of replacing the
water service before construction begins or having the service line replaced as part of the
construction contract. Generally, having the service line replaced as part of the construction
contract is easier and less expensive. The cost of replacing a private service line during a
construction event and in conjunction with a sanitary lateral replacement is estimated to be
approximately $1,500.00.
Carriage Walk
If a carriage walk exists adjacent to your property, between the City sidewalk and roadway, it
will be removed with our project. If you would like to pay for this to remain, please contact the
City for an estimated cost.
During the course of this project, there will be inconveniences such as noise, travel delays,
dust, and other issues associated with street construction. The City of Neenah and the
contractor are committed to working with the property owners to make this project run as
smoothly as possible.
February 28, 2024
P a g e | 3
If you would like to receive weekly emails on construction updates, you can sign up for the
Construction Newsletter on the City of Neenah webpage (www.ci.neenah.wi.us) under the
Department of Public Works. We thank you for your help and patience during this construction
project. Please contact our department if you require special consideration for accessibility. If
you have any questions, contact the individuals listed below or the Public Works Department at
920-886-6240.
City of Neenah Engineer ............... Jason Eckhart ......................... 920-886-6246
City of Neenah Engineer ............... Heath Kummerow ................. 920-886-6245
David Tenor Corporation... ........... David Tenor ........................... 920-360-9246
Sincerely,
Gerry Kaiser, PE
Director of Public Works
cc: Mayor Lang
Police Chief Olson
Fire Chief Kloehn
Aldermen
Neenah
W I S C O N S I N
Department of Public Works
211 Walnut St., P.O. Box 426, Neenah, WI 54957-0426
Phone: 920-886-6240 Fax: 920-886-6250
March 1, 2024
DANIEL & MEGAN MILLER
534 BELMONT AVE
NEENAH WI 54956
RE: 534 BELMONT AVE
The City's contractor, David Tenor Corporation, will begin utility and street construction on
Belmont Avenue, Belmont Court, Cedar Street, and Stevens Street in the next week(s).
Construction will be completed by November 2024. We will need your help to make this a
successful project.
General Project Sequence
The project will consist of the following work:
Install new sanitary sewer main
Install new water main
Install new sanitary laterals and water services
Install new storm sewer
Rest period (Contractor will not work for 1 month to allow trenches to settle more than
can be achieved with mechanical compaction)
Remove existing roadway (asphalt, and the existing stone base)
Install geogrid and new aggregate road base
Install/repair concrete curb & gutter and place concrete pavement
Repair/replace existing concrete sidewalk/driveway aprons and install new sidewalk
Restore terrace areas with topsoil, grass seed, fertilizer, and hydro-mulch
Install new hot mix asphalt roadway (two lifts)
Garbage / Postal Service / Emergency Services
During construction, refuse and recycling pick-up will continue on your regularly
scheduled day. Please have your carts out before 6:30 A.M. when the construction crew
is working on your street. Carts should be placed on the street or terrace area.
The postal service will continue delivering and collecting mail as usual.
Emergency services have been notified of the construction activity and will plan
accordingly.
February 28, 2024
P a g e | 2
Parking and Accessibility
The streets will be open to local traffic only and residents will have access to their driveways
during the majority of the project. Parking will not be permitted on the streets during the
construction day (7 AM to 5 PM). Parking is available on adjacent streets. Other than NO
PARKING zones, standard parking restrictions will be waived on adjacent streets for those
vehicles displaying one of the enclosed Construction Parking Permits. There will be a period
of time when residents will not have access to their driveways. This will occur during the
concrete street paving and during, curb/gutter and driveway construction, and will last
approximately 3 weeks. At least 24 hours advance notice will be given when limiting driveway
access.
Terrace Restoration
The contractor will complete the terrace restoration adjacent to your property. After topsoil is
placed and leveled, a mix of grass seed, fertilizer and mulch will be placed. Please water this
daily to keep the soil moist until the new grass is well established. Please mow the grass and
weeds when they reach 6". The grass should overtake the weeds with continued watering and
mowing. The contractor will notify you when to begin watering.
Private Sewer Lateral Replacement
Please return your Property Owner Authorization Form (pink sheet) if you have not
already done so. All sanitary laterals will be replaced to the homes unless previously relayed.
The cost estimate for the sanitary lateral for the property owner share is approximately
$3,000.00.
Water Services Replacement
If there is lead or galvanized pipe on the Utility-owned portion of the service line (from the
main to the curb stop), this portion will be replaced at no cost to you. However, the
replacement of the private lead or galvanized service (from the curb stop to the water meter) is
the responsibility of the property owner. Property owners have the choice of replacing the
water service before construction begins or having the service line replaced as part of the
construction contract. Generally, having the service line replaced as part of the construction
contract is easier and less expensive. The cost of replacing a private service line during a
construction event and in conjunction with a sanitary lateral replacement is estimated to be
approximately $1,500.00.
Carriage Walk
If a carriage walk exists adjacent to your property, between the City sidewalk and roadway, it
will be removed with our project. If you would like to pay for this to remain, please contact the
City for an estimated cost.
During the course of this project, there will be inconveniences such as noise, travel delays,
dust, and other issues associated with street construction. The City of Neenah and the
contractor are committed to working with the property owners to make this project run as
smoothly as possible.
February 28, 2024
P a g e | 3
If you would like to receive weekly emails on construction updates, you can sign up for the
Construction Newsletter on the City of Neenah webpage (www.ci.neenah.wi.us) under the
Department of Public Works. We thank you for your help and patience during this construction
project. Please contact our department if you require special consideration for accessibility. If
you have any questions, contact the individuals listed below or the Public Works Department at
920-886-6240.
City of Neenah Engineer ............... Jason Eckhart ......................... 920-886-6246
City of Neenah Engineer ............... Heath Kummerow ................. 920-886-6245
David Tenor Corporation... ........... David Tenor ........................... 920-360-9246
Sincerely,
Gerry Kaiser, PE
Director of Public Works
cc: Mayor Lang
Police Chief Olson
Fire Chief Kloehn
Aldermen
Neenah
W I S C O N S I N
Department of Public Works
211 Walnut St., P.O. Box 426, Neenah, WI 54957-0426
Phone: 920-886-6240 Fax: 920-886-6250
March 1, 2024
DANIEL & BETTE MCINTOSH
234 LAKESHORE DR
NEENAH WI 54956
RE: 572 BELMONT AVE
The City's contractor, David Tenor Corporation, will begin utility and street construction on
Belmont Avenue, Belmont Court, Cedar Street, and Stevens Street in the next week(s).
Construction will be completed by November 2024. We will need your help to make this a
successful project.
General Project Sequence
The project will consist of the following work:
Install new sanitary sewer main
Install new water main
Install new sanitary laterals and water services
Install new storm sewer
Rest period (Contractor will not work for 1 month to allow trenches to settle more than
can be achieved with mechanical compaction)
Remove existing roadway (asphalt, and the existing stone base)
Install geogrid and new aggregate road base
Install/repair concrete curb & gutter and place concrete pavement
Repair/replace existing concrete sidewalk/driveway aprons and install new sidewalk
Restore terrace areas with topsoil, grass seed, fertilizer, and hydro-mulch
Install new hot mix asphalt roadway (two lifts)
Garbage / Postal Service / Emergency Services
During construction, refuse and recycling pick-up will continue on your regularly
scheduled day. Please have your carts out before 6:30 A.M. when the construction crew
is working on your street. Carts should be placed on the street or terrace area.
The postal service will continue delivering and collecting mail as usual.
Emergency services have been notified of the construction activity and will plan
accordingly.
February 28, 2024
P a g e | 2
Parking and Accessibility
The streets will be open to local traffic only and residents will have access to their driveways
during the majority of the project. Parking will not be permitted on the streets during the
construction day (7 AM to 5 PM). Parking is available on adjacent streets. Other than NO
PARKING zones, standard parking restrictions will be waived on adjacent streets for those
vehicles displaying one of the enclosed Construction Parking Permits. There will be a period
of time when residents will not have access to their driveways. This will occur during the
concrete street paving and during, curb/gutter and driveway construction, and will last
approximately 3 weeks. At least 24 hours advance notice will be given when limiting driveway
access.
Terrace Restoration
The contractor will complete the terrace restoration adjacent to your property. After topsoil is
placed and leveled, a mix of grass seed, fertilizer and mulch will be placed. Please water this
daily to keep the soil moist until the new grass is well established. Please mow the grass and
weeds when they reach 6". The grass should overtake the weeds with continued watering and
mowing. The contractor will notify you when to begin watering.
Private Sewer Lateral Replacement
Please return your Property Owner Authorization Form (pink sheet) if you have not
already done so. All sanitary laterals will be replaced to the homes unless previously relayed.
The cost estimate for the sanitary lateral for the property owner share is approximately
$3,000.00.
Water Services Replacement
If there is lead or galvanized pipe on the Utility-owned portion of the service line (from the
main to the curb stop), this portion will be replaced at no cost to you. However, the
replacement of the private lead or galvanized service (from the curb stop to the water meter) is
the responsibility of the property owner. Property owners have the choice of replacing the
water service before construction begins or having the service line replaced as part of the
construction contract. Generally, having the service line replaced as part of the construction
contract is easier and less expensive. The cost of replacing a private service line during a
construction event and in conjunction with a sanitary lateral replacement is estimated to be
approximately $1,500.00.
Carriage Walk
If a carriage walk exists adjacent to your property, between the City sidewalk and roadway, it
will be removed with our project. If you would like to pay for this to remain, please contact the
City for an estimated cost.
During the course of this project, there will be inconveniences such as noise, travel delays,
dust, and other issues associated with street construction. The City of Neenah and the
contractor are committed to working with the property owners to make this project run as
smoothly as possible.
February 28, 2024
P a g e | 3
If you would like to receive weekly emails on construction updates, you can sign up for the
Construction Newsletter on the City of Neenah webpage (www.ci.neenah.wi.us) under the
Department of Public Works. We thank you for your help and patience during this construction
project. Please contact our department if you require special consideration for accessibility. If
you have any questions, contact the individuals listed below or the Public Works Department at
920-886-6240.
City of Neenah Engineer ............... Jason Eckhart ......................... 920-886-6246
City of Neenah Engineer ............... Heath Kummerow ................. 920-886-6245
David Tenor Corporation... ........... David Tenor ........................... 920-360-9246
Sincerely,
Gerry Kaiser, PE
Director of Public Works
cc: Mayor Lang
Police Chief Olson
Fire Chief Kloehn
Aldermen
Neenah
W I S C O N S I N
Department of Public Works
211 Walnut St., P.O. Box 426, Neenah, WI 54957-0426
Phone: 920-886-6240 Fax: 920-886-6250
March 1, 2024
CURRENT OCCUPANT
572 BELMONT AVE
NEENAH WI 54956
RE: 572 BELMONT AVE
The City's contractor, David Tenor Corporation, will begin utility and street construction on
Belmont Avenue, Belmont Court, Cedar Street, and Stevens Street in the next week(s).
Construction will be completed by November 2024. We will need your help to make this a
successful project.
General Project Sequence
The project will consist of the following work:
Install new sanitary sewer main
Install new water main
Install new sanitary laterals and water services
Install new storm sewer
Rest period (Contractor will not work for 1 month to allow trenches to settle more than
can be achieved with mechanical compaction)
Remove existing roadway (asphalt, and the existing stone base)
Install geogrid and new aggregate road base
Install/repair concrete curb & gutter and place concrete pavement
Repair/replace existing concrete sidewalk/driveway aprons and install new sidewalk
Restore terrace areas with topsoil, grass seed, fertilizer, and hydro-mulch
Install new hot mix asphalt roadway (two lifts)
Garbage / Postal Service / Emergency Services
During construction, refuse and recycling pick-up will continue on your regularly
scheduled day. Please have your carts out before 6:30 A.M. when the construction crew
is working on your street. Carts should be placed on the street or terrace area.
The postal service will continue delivering and collecting mail as usual.
Emergency services have been notified of the construction activity and will plan
accordingly.
February 28, 2024
P a g e | 2
Parking and Accessibility
The streets will be open to local traffic only and residents will have access to their driveways
during the majority of the project. Parking will not be permitted on the streets during the
construction day (7 AM to 5 PM). Parking is available on adjacent streets. Other than NO
PARKING zones, standard parking restrictions will be waived on adjacent streets for those
vehicles displaying one of the enclosed Construction Parking Permits. There will be a period
of time when residents will not have access to their driveways. This will occur during the
concrete street paving and during, curb/gutter and driveway construction, and will last
approximately 3 weeks. At least 24 hours advance notice will be given when limiting driveway
access.
Terrace Restoration
The contractor will complete the terrace restoration adjacent to your property. After topsoil is
placed and leveled, a mix of grass seed, fertilizer and mulch will be placed. Please water this
daily to keep the soil moist until the new grass is well established. Please mow the grass and
weeds when they reach 6". The grass should overtake the weeds with continued watering and
mowing. The contractor will notify you when to begin watering.
Private Sewer Lateral Replacement
Please return your Property Owner Authorization Form (pink sheet) if you have not
already done so. All sanitary laterals will be replaced to the homes unless previously relayed.
The cost estimate for the sanitary lateral for the property owner share is approximately
$3,000.00.
Water Services Replacement
If there is lead or galvanized pipe on the Utility-owned portion of the service line (from the
main to the curb stop), this portion will be replaced at no cost to you. However, the
replacement of the private lead or galvanized service (from the curb stop to the water meter) is
the responsibility of the property owner. Property owners have the choice of replacing the
water service before construction begins or having the service line replaced as part of the
construction contract. Generally, having the service line replaced as part of the construction
contract is easier and less expensive. The cost of replacing a private service line during a
construction event and in conjunction with a sanitary lateral replacement is estimated to be
approximately $1,500.00.
Carriage Walk
If a carriage walk exists adjacent to your property, between the City sidewalk and roadway, it
will be removed with our project. If you would like to pay for this to remain, please contact the
City for an estimated cost.
During the course of this project, there will be inconveniences such as noise, travel delays,
dust, and other issues associated with street construction. The City of Neenah and the
contractor are committed to working with the property owners to make this project run as
smoothly as possible.
February 28, 2024
P a g e | 3
If you would like to receive weekly emails on construction updates, you can sign up for the
Construction Newsletter on the City of Neenah webpage (www.ci.neenah.wi.us) under the
Department of Public Works. We thank you for your help and patience during this construction
project. Please contact our department if you require special consideration for accessibility. If
you have any questions, contact the individuals listed below or the Public Works Department at
920-886-6240.
City of Neenah Engineer ............... Jason Eckhart ......................... 920-886-6246
City of Neenah Engineer ............... Heath Kummerow ................. 920-886-6245
David Tenor Corporation... ........... David Tenor ........................... 920-360-9246
Sincerely,
Gerry Kaiser, PE
Director of Public Works
cc: Mayor Lang
Police Chief Olson
Fire Chief Kloehn
Aldermen
Neenah
W I S C O N S I N
Department of Public Works
211 Walnut St., P.O. Box 426, Neenah, WI 54957-0426
Phone: 920-886-6240 Fax: 920-886-6250
March 1, 2024
MICHAEL FREIER
576 BELMONT AVE
NEENAH WI 54956
RE: 576 BELMONT AVE
The City's contractor, David Tenor Corporation, will begin utility and street construction on
Belmont Avenue, Belmont Court, Cedar Street, and Stevens Street in the next week(s).
Construction will be completed by November 2024. We will need your help to make this a
successful project.
General Project Sequence
The project will consist of the following work:
Install new sanitary sewer main
Install new water main
Install new sanitary laterals and water services
Install new storm sewer
Rest period (Contractor will not work for 1 month to allow trenches to settle more than
can be achieved with mechanical compaction)
Remove existing roadway (asphalt, and the existing stone base)
Install geogrid and new aggregate road base
Install/repair concrete curb & gutter and place concrete pavement
Repair/replace existing concrete sidewalk/driveway aprons and install new sidewalk
Restore terrace areas with topsoil, grass seed, fertilizer, and hydro-mulch
Install new hot mix asphalt roadway (two lifts)
Garbage / Postal Service / Emergency Services
During construction, refuse and recycling pick-up will continue on your regularly
scheduled day. Please have your carts out before 6:30 A.M. when the construction crew
is working on your street. Carts should be placed on the street or terrace area.
The postal service will continue delivering and collecting mail as usual.
Emergency services have been notified of the construction activity and will plan
accordingly.
February 28, 2024
P a g e | 2
Parking and Accessibility
The streets will be open to local traffic only and residents will have access to their driveways
during the majority of the project. Parking will not be permitted on the streets during the
construction day (7 AM to 5 PM). Parking is available on adjacent streets. Other than NO
PARKING zones, standard parking restrictions will be waived on adjacent streets for those
vehicles displaying one of the enclosed Construction Parking Permits. There will be a period
of time when residents will not have access to their driveways. This will occur during the
concrete street paving and during, curb/gutter and driveway construction, and will last
approximately 3 weeks. At least 24 hours advance notice will be given when limiting driveway
access.
Terrace Restoration
The contractor will complete the terrace restoration adjacent to your property. After topsoil is
placed and leveled, a mix of grass seed, fertilizer and mulch will be placed. Please water this
daily to keep the soil moist until the new grass is well established. Please mow the grass and
weeds when they reach 6". The grass should overtake the weeds with continued watering and
mowing. The contractor will notify you when to begin watering.
Private Sewer Lateral Replacement
Please return your Property Owner Authorization Form (pink sheet) if you have not
already done so. All sanitary laterals will be replaced to the homes unless previously relayed.
The cost estimate for the sanitary lateral for the property owner share is approximately
$3,000.00.
Water Services Replacement
If there is lead or galvanized pipe on the Utility-owned portion of the service line (from the
main to the curb stop), this portion will be replaced at no cost to you. However, the
replacement of the private lead or galvanized service (from the curb stop to the water meter) is
the responsibility of the property owner. Property owners have the choice of replacing the
water service before construction begins or having the service line replaced as part of the
construction contract. Generally, having the service line replaced as part of the construction
contract is easier and less expensive. The cost of replacing a private service line during a
construction event and in conjunction with a sanitary lateral replacement is estimated to be
approximately $1,500.00.
Carriage Walk
If a carriage walk exists adjacent to your property, between the City sidewalk and roadway, it
will be removed with our project. If you would like to pay for this to remain, please contact the
City for an estimated cost.
During the course of this project, there will be inconveniences such as noise, travel delays,
dust, and other issues associated with street construction. The City of Neenah and the
contractor are committed to working with the property owners to make this project run as
smoothly as possible.
February 28, 2024
P a g e | 3
If you would like to receive weekly emails on construction updates, you can sign up for the
Construction Newsletter on the City of Neenah webpage (www.ci.neenah.wi.us) under the
Department of Public Works. We thank you for your help and patience during this construction
project. Please contact our department if you require special consideration for accessibility. If
you have any questions, contact the individuals listed below or the Public Works Department at
920-886-6240.
City of Neenah Engineer ............... Jason Eckhart ......................... 920-886-6246
City of Neenah Engineer ............... Heath Kummerow ................. 920-886-6245
David Tenor Corporation... ........... David Tenor ........................... 920-360-9246
Sincerely,
Gerry Kaiser, PE
Director of Public Works
cc: Mayor Lang
Police Chief Olson
Fire Chief Kloehn
Aldermen
Neenah
W I S C O N S I N
Department of Public Works
211 Walnut St., P.O. Box 426, Neenah, WI 54957-0426
Phone: 920-886-6240 Fax: 920-886-6250
March 1, 2024
SCOTT & REBECCA DAWSON
557 BELMONT AVE
NEENAH WI 54956
RE: 557 BELMONT AVE
The City's contractor, David Tenor Corporation, will begin utility and street construction on
Belmont Avenue, Belmont Court, Cedar Street, and Stevens Street in the next week(s).
Construction will be completed by November 2024. We will need your help to make this a
successful project.
General Project Sequence
The project will consist of the following work:
Install new sanitary sewer main
Install new water main
Install new sanitary laterals and water services
Install new storm sewer
Rest period (Contractor will not work for 1 month to allow trenches to settle more than
can be achieved with mechanical compaction)
Remove existing roadway (asphalt, and the existing stone base)
Install geogrid and new aggregate road base
Install/repair concrete curb & gutter and place concrete pavement
Repair/replace existing concrete sidewalk/driveway aprons and install new sidewalk
Restore terrace areas with topsoil, grass seed, fertilizer, and hydro-mulch
Install new hot mix asphalt roadway (two lifts)
Garbage / Postal Service / Emergency Services
During construction, refuse and recycling pick-up will continue on your regularly
scheduled day. Please have your carts out before 6:30 A.M. when the construction crew
is working on your street. Carts should be placed on the street or terrace area.
The postal service will continue delivering and collecting mail as usual.
Emergency services have been notified of the construction activity and will plan
accordingly.
February 28, 2024
P a g e | 2
Parking and Accessibility
The streets will be open to local traffic only and residents will have access to their driveways
during the majority of the project. Parking will not be permitted on the streets during the
construction day (7 AM to 5 PM). Parking is available on adjacent streets. Other than NO
PARKING zones, standard parking restrictions will be waived on adjacent streets for those
vehicles displaying one of the enclosed Construction Parking Permits. There will be a period
of time when residents will not have access to their driveways. This will occur during the
concrete street paving and during, curb/gutter and driveway construction, and will last
approximately 3 weeks. At least 24 hours advance notice will be given when limiting driveway
access.
Terrace Restoration
The contractor will complete the terrace restoration adjacent to your property. After topsoil is
placed and leveled, a mix of grass seed, fertilizer and mulch will be placed. Please water this
daily to keep the soil moist until the new grass is well established. Please mow the grass and
weeds when they reach 6". The grass should overtake the weeds with continued watering and
mowing. The contractor will notify you when to begin watering.
Private Sewer Lateral Replacement
Please return your Property Owner Authorization Form (pink sheet) if you have not
already done so. All sanitary laterals will be replaced to the homes unless previously relayed.
The cost estimate for the sanitary lateral for the property owner share is approximately
$3,000.00.
Water Services Replacement
If there is lead or galvanized pipe on the Utility-owned portion of the service line (from the
main to the curb stop), this portion will be replaced at no cost to you. However, the
replacement of the private lead or galvanized service (from the curb stop to the water meter) is
the responsibility of the property owner. Property owners have the choice of replacing the
water service before construction begins or having the service line replaced as part of the
construction contract. Generally, having the service line replaced as part of the construction
contract is easier and less expensive. The cost of replacing a private service line during a
construction event and in conjunction with a sanitary lateral replacement is estimated to be
approximately $1,500.00.
Carriage Walk
If a carriage walk exists adjacent to your property, between the City sidewalk and roadway, it
will be removed with our project. If you would like to pay for this to remain, please contact the
City for an estimated cost.
During the course of this project, there will be inconveniences such as noise, travel delays,
dust, and other issues associated with street construction. The City of Neenah and the
contractor are committed to working with the property owners to make this project run as
smoothly as possible.
February 28, 2024
P a g e | 3
If you would like to receive weekly emails on construction updates, you can sign up for the
Construction Newsletter on the City of Neenah webpage (www.ci.neenah.wi.us) under the
Department of Public Works. We thank you for your help and patience during this construction
project. Please contact our department if you require special consideration for accessibility. If
you have any questions, contact the individuals listed below or the Public Works Department at
920-886-6240.
City of Neenah Engineer ............... Jason Eckhart ......................... 920-886-6246
City of Neenah Engineer ............... Heath Kummerow ................. 920-886-6245
David Tenor Corporation... ........... David Tenor ........................... 920-360-9246
Sincerely,
Gerry Kaiser, PE
Director of Public Works
cc: Mayor Lang
Police Chief Olson
Fire Chief Kloehn
Aldermen
Neenah
W I S C O N S I N
Department of Public Works
211 Walnut St., P.O. Box 426, Neenah, WI 54957-0426
Phone: 920-886-6240 Fax: 920-886-6250
March 1, 2024
BRANDON & GINGER REINTJES
629 BELMONT CT
NEENAH WI 54956
RE: 629 BELMONT CT
The City's contractor, David Tenor Corporation, will begin utility and street construction on
Belmont Avenue, Belmont Court, Cedar Street, and Stevens Street in the next week(s).
Construction will be completed by November 2024. We will need your help to make this a
successful project.
General Project Sequence
The project will consist of the following work:
Install new sanitary sewer main
Install new water main
Install new sanitary laterals and water services
Install new storm sewer
Rest period (Contractor will not work for 1 month to allow trenches to settle more than
can be achieved with mechanical compaction)
Remove existing roadway (asphalt, and the existing stone base)
Install geogrid and new aggregate road base
Install/repair concrete curb & gutter and place concrete pavement
Repair/replace existing concrete sidewalk/driveway aprons and install new sidewalk
Restore terrace areas with topsoil, grass seed, fertilizer, and hydro-mulch
Install new hot mix asphalt roadway (two lifts)
Garbage / Postal Service / Emergency Services
During construction, refuse and recycling pick-up will continue on your regularly
scheduled day. Please have your carts out before 6:30 A.M. when the construction crew
is working on your street. Carts should be placed on the street or terrace area.
The postal service will continue delivering and collecting mail as usual.
Emergency services have been notified of the construction activity and will plan
accordingly.
February 28, 2024
P a g e | 2
Parking and Accessibility
The streets will be open to local traffic only and residents will have access to their driveways
during the majority of the project. Parking will not be permitted on the streets during the
construction day (7 AM to 5 PM). Parking is available on adjacent streets. Other than NO
PARKING zones, standard parking restrictions will be waived on adjacent streets for those
vehicles displaying one of the enclosed Construction Parking Permits. There will be a period
of time when residents will not have access to their driveways. This will occur during the
concrete street paving and during, curb/gutter and driveway construction, and will last
approximately 3 weeks. At least 24 hours advance notice will be given when limiting driveway
access.
Terrace Restoration
The contractor will complete the terrace restoration adjacent to your property. After topsoil is
placed and leveled, a mix of grass seed, fertilizer and mulch will be placed. Please water this
daily to keep the soil moist until the new grass is well established. Please mow the grass and
weeds when they reach 6". The grass should overtake the weeds with continued watering and
mowing. The contractor will notify you when to begin watering.
Private Sewer Lateral Replacement
Please return your Property Owner Authorization Form (pink sheet) if you have not
already done so. All sanitary laterals will be replaced to the homes unless previously relayed.
The cost estimate for the sanitary lateral for the property owner share is approximately
$3,000.00.
Water Services Replacement
If there is lead or galvanized pipe on the Utility-owned portion of the service line (from the
main to the curb stop), this portion will be replaced at no cost to you. However, the
replacement of the private lead or galvanized service (from the curb stop to the water meter) is
the responsibility of the property owner. Property owners have the choice of replacing the
water service before construction begins or having the service line replaced as part of the
construction contract. Generally, having the service line replaced as part of the construction
contract is easier and less expensive. The cost of replacing a private service line during a
construction event and in conjunction with a sanitary lateral replacement is estimated to be
approximately $1,500.00.
Carriage Walk
If a carriage walk exists adjacent to your property, between the City sidewalk and roadway, it
will be removed with our project. If you would like to pay for this to remain, please contact the
City for an estimated cost.
During the course of this project, there will be inconveniences such as noise, travel delays,
dust, and other issues associated with street construction. The City of Neenah and the
contractor are committed to working with the property owners to make this project run as
smoothly as possible.
February 28, 2024
P a g e | 3
If you would like to receive weekly emails on construction updates, you can sign up for the
Construction Newsletter on the City of Neenah webpage (www.ci.neenah.wi.us) under the
Department of Public Works. We thank you for your help and patience during this construction
project. Please contact our department if you require special consideration for accessibility. If
you have any questions, contact the individuals listed below or the Public Works Department at
920-886-6240.
City of Neenah Engineer ............... Jason Eckhart ......................... 920-886-6246
City of Neenah Engineer ............... Heath Kummerow ................. 920-886-6245
David Tenor Corporation... ........... David Tenor ........................... 920-360-9246
Sincerely,
Gerry Kaiser, PE
Director of Public Works
cc: Mayor Lang
Police Chief Olson
Fire Chief Kloehn
Aldermen
Neenah
W I S C O N S I N
Department of Public Works
211 Walnut St., P.O. Box 426, Neenah, WI 54957-0426
Phone: 920-886-6240 Fax: 920-886-6250
March 1, 2024
JOSEPH & REBECCA HENRY
661 BELMONT CT
NEENAH WI 54596
RE: 661 BELMONT CT
The City's contractor, David Tenor Corporation, will begin utility and street construction on
Belmont Avenue, Belmont Court, Cedar Street, and Stevens Street in the next week(s).
Construction will be completed by November 2024. We will need your help to make this a
successful project.
General Project Sequence
The project will consist of the following work:
Install new sanitary sewer main
Install new water main
Install new sanitary laterals and water services
Install new storm sewer
Rest period (Contractor will not work for 1 month to allow trenches to settle more than
can be achieved with mechanical compaction)
Remove existing roadway (asphalt, and the existing stone base)
Install geogrid and new aggregate road base
Install/repair concrete curb & gutter and place concrete pavement
Repair/replace existing concrete sidewalk/driveway aprons and install new sidewalk
Restore terrace areas with topsoil, grass seed, fertilizer, and hydro-mulch
Install new hot mix asphalt roadway (two lifts)
Garbage / Postal Service / Emergency Services
During construction, refuse and recycling pick-up will continue on your regularly
scheduled day. Please have your carts out before 6:30 A.M. when the construction crew
is working on your street. Carts should be placed on the street or terrace area.
The postal service will continue delivering and collecting mail as usual.
Emergency services have been notified of the construction activity and will plan
accordingly.
February 28, 2024
P a g e | 2
Parking and Accessibility
The streets will be open to local traffic only and residents will have access to their driveways
during the majority of the project. Parking will not be permitted on the streets during the
construction day (7 AM to 5 PM). Parking is available on adjacent streets. Other than NO
PARKING zones, standard parking restrictions will be waived on adjacent streets for those
vehicles displaying one of the enclosed Construction Parking Permits. There will be a period
of time when residents will not have access to their driveways. This will occur during the
concrete street paving and during, curb/gutter and driveway construction, and will last
approximately 3 weeks. At least 24 hours advance notice will be given when limiting driveway
access.
Terrace Restoration
The contractor will complete the terrace restoration adjacent to your property. After topsoil is
placed and leveled, a mix of grass seed, fertilizer and mulch will be placed. Please water this
daily to keep the soil moist until the new grass is well established. Please mow the grass and
weeds when they reach 6". The grass should overtake the weeds with continued watering and
mowing. The contractor will notify you when to begin watering.
Private Sewer Lateral Replacement
Please return your Property Owner Authorization Form (pink sheet) if you have not
already done so. All sanitary laterals will be replaced to the homes unless previously relayed.
The cost estimate for the sanitary lateral for the property owner share is approximately
$3,000.00.
Water Services Replacement
If there is lead or galvanized pipe on the Utility-owned portion of the service line (from the
main to the curb stop), this portion will be replaced at no cost to you. However, the
replacement of the private lead or galvanized service (from the curb stop to the water meter) is
the responsibility of the property owner. Property owners have the choice of replacing the
water service before construction begins or having the service line replaced as part of the
construction contract. Generally, having the service line replaced as part of the construction
contract is easier and less expensive. The cost of replacing a private service line during a
construction event and in conjunction with a sanitary lateral replacement is estimated to be
approximately $1,500.00.
Carriage Walk
If a carriage walk exists adjacent to your property, between the City sidewalk and roadway, it
will be removed with our project. If you would like to pay for this to remain, please contact the
City for an estimated cost.
During the course of this project, there will be inconveniences such as noise, travel delays,
dust, and other issues associated with street construction. The City of Neenah and the
contractor are committed to working with the property owners to make this project run as
smoothly as possible.
February 28, 2024
P a g e | 3
If you would like to receive weekly emails on construction updates, you can sign up for the
Construction Newsletter on the City of Neenah webpage (www.ci.neenah.wi.us) under the
Department of Public Works. We thank you for your help and patience during this construction
project. Please contact our department if you require special consideration for accessibility. If
you have any questions, contact the individuals listed below or the Public Works Department at
920-886-6240.
City of Neenah Engineer ............... Jason Eckhart ......................... 920-886-6246
City of Neenah Engineer ............... Heath Kummerow ................. 920-886-6245
David Tenor Corporation... ........... David Tenor ........................... 920-360-9246
Sincerely,
Gerry Kaiser, PE
Director of Public Works
cc: Mayor Lang
Police Chief Olson
Fire Chief Kloehn
Aldermen
Neenah
W I S C O N S I N
Department of Public Works
211 Walnut St., P.O. Box 426, Neenah, WI 54957-0426
Phone: 920-886-6240 Fax: 920-886-6250
March 1, 2024
CARL & ELSIE EVENSON
657 BELMONT CT
NEENAH WI 54956
RE: 657 BELMONT CT
The City's contractor, David Tenor Corporation, will begin utility and street construction on
Belmont Avenue, Belmont Court, Cedar Street, and Stevens Street in the next week(s).
Construction will be completed by November 2024. We will need your help to make this a
successful project.
General Project Sequence
The project will consist of the following work:
Install new sanitary sewer main
Install new water main
Install new sanitary laterals and water services
Install new storm sewer
Rest period (Contractor will not work for 1 month to allow trenches to settle more than
can be achieved with mechanical compaction)
Remove existing roadway (asphalt, and the existing stone base)
Install geogrid and new aggregate road base
Install/repair concrete curb & gutter and place concrete pavement
Repair/replace existing concrete sidewalk/driveway aprons and install new sidewalk
Restore terrace areas with topsoil, grass seed, fertilizer, and hydro-mulch
Install new hot mix asphalt roadway (two lifts)
Garbage / Postal Service / Emergency Services
During construction, refuse and recycling pick-up will continue on your regularly
scheduled day. Please have your carts out before 6:30 A.M. when the construction crew
is working on your street. Carts should be placed on the street or terrace area.
The postal service will continue delivering and collecting mail as usual.
Emergency services have been notified of the construction activity and will plan
accordingly.
February 28, 2024
P a g e | 2
Parking and Accessibility
The streets will be open to local traffic only and residents will have access to their driveways
during the majority of the project. Parking will not be permitted on the streets during the
construction day (7 AM to 5 PM). Parking is available on adjacent streets. Other than NO
PARKING zones, standard parking restrictions will be waived on adjacent streets for those
vehicles displaying one of the enclosed Construction Parking Permits. There will be a period
of time when residents will not have access to their driveways. This will occur during the
concrete street paving and during, curb/gutter and driveway construction, and will last
approximately 3 weeks. At least 24 hours advance notice will be given when limiting driveway
access.
Terrace Restoration
The contractor will complete the terrace restoration adjacent to your property. After topsoil is
placed and leveled, a mix of grass seed, fertilizer and mulch will be placed. Please water this
daily to keep the soil moist until the new grass is well established. Please mow the grass and
weeds when they reach 6". The grass should overtake the weeds with continued watering and
mowing. The contractor will notify you when to begin watering.
Private Sewer Lateral Replacement
Please return your Property Owner Authorization Form (pink sheet) if you have not
already done so. All sanitary laterals will be replaced to the homes unless previously relayed.
The cost estimate for the sanitary lateral for the property owner share is approximately
$3,000.00.
Water Services Replacement
If there is lead or galvanized pipe on the Utility-owned portion of the service line (from the
main to the curb stop), this portion will be replaced at no cost to you. However, the
replacement of the private lead or galvanized service (from the curb stop to the water meter) is
the responsibility of the property owner. Property owners have the choice of replacing the
water service before construction begins or having the service line replaced as part of the
construction contract. Generally, having the service line replaced as part of the construction
contract is easier and less expensive. The cost of replacing a private service line during a
construction event and in conjunction with a sanitary lateral replacement is estimated to be
approximately $1,500.00.
Carriage Walk
If a carriage walk exists adjacent to your property, between the City sidewalk and roadway, it
will be removed with our project. If you would like to pay for this to remain, please contact the
City for an estimated cost.
During the course of this project, there will be inconveniences such as noise, travel delays,
dust, and other issues associated with street construction. The City of Neenah and the
contractor are committed to working with the property owners to make this project run as
smoothly as possible.
February 28, 2024
P a g e | 3
If you would like to receive weekly emails on construction updates, you can sign up for the
Construction Newsletter on the City of Neenah webpage (www.ci.neenah.wi.us) under the
Department of Public Works. We thank you for your help and patience during this construction
project. Please contact our department if you require special consideration for accessibility. If
you have any questions, contact the individuals listed below or the Public Works Department at
920-886-6240.
City of Neenah Engineer ............... Jason Eckhart ......................... 920-886-6246
City of Neenah Engineer ............... Heath Kummerow ................. 920-886-6245
David Tenor Corporation... ........... David Tenor ........................... 920-360-9246
Sincerely,
Gerry Kaiser, PE
Director of Public Works
cc: Mayor Lang
Police Chief Olson
Fire Chief Kloehn
Aldermen
Neenah
W I S C O N S I N
Department of Public Works
211 Walnut St., P.O. Box 426, Neenah, WI 54957-0426
Phone: 920-886-6240 Fax: 920-886-6250
March 1, 2024
LOREN & KAREN WAHL
653 BELMONT CT
NEENAH WI 54956
RE: 653 BELMONT CT
The City's contractor, David Tenor Corporation, will begin utility and street construction on
Belmont Avenue, Belmont Court, Cedar Street, and Stevens Street in the next week(s).
Construction will be completed by November 2024. We will need your help to make this a
successful project.
General Project Sequence
The project will consist of the following work:
Install new sanitary sewer main
Install new water main
Install new sanitary laterals and water services
Install new storm sewer
Rest period (Contractor will not work for 1 month to allow trenches to settle more than
can be achieved with mechanical compaction)
Remove existing roadway (asphalt, and the existing stone base)
Install geogrid and new aggregate road base
Install/repair concrete curb & gutter and place concrete pavement
Repair/replace existing concrete sidewalk/driveway aprons and install new sidewalk
Restore terrace areas with topsoil, grass seed, fertilizer, and hydro-mulch
Install new hot mix asphalt roadway (two lifts)
Garbage / Postal Service / Emergency Services
During construction, refuse and recycling pick-up will continue on your regularly
scheduled day. Please have your carts out before 6:30 A.M. when the construction crew
is working on your street. Carts should be placed on the street or terrace area.
The postal service will continue delivering and collecting mail as usual.
Emergency services have been notified of the construction activity and will plan
accordingly.
February 28, 2024
P a g e | 2
Parking and Accessibility
The streets will be open to local traffic only and residents will have access to their driveways
during the majority of the project. Parking will not be permitted on the streets during the
construction day (7 AM to 5 PM). Parking is available on adjacent streets. Other than NO
PARKING zones, standard parking restrictions will be waived on adjacent streets for those
vehicles displaying one of the enclosed Construction Parking Permits. There will be a period
of time when residents will not have access to their driveways. This will occur during the
concrete street paving and during, curb/gutter and driveway construction, and will last
approximately 3 weeks. At least 24 hours advance notice will be given when limiting driveway
access.
Terrace Restoration
The contractor will complete the terrace restoration adjacent to your property. After topsoil is
placed and leveled, a mix of grass seed, fertilizer and mulch will be placed. Please water this
daily to keep the soil moist until the new grass is well established. Please mow the grass and
weeds when they reach 6". The grass should overtake the weeds with continued watering and
mowing. The contractor will notify you when to begin watering.
Private Sewer Lateral Replacement
Please return your Property Owner Authorization Form (pink sheet) if you have not
already done so. All sanitary laterals will be replaced to the homes unless previously relayed.
The cost estimate for the sanitary lateral for the property owner share is approximately
$3,000.00.
Water Services Replacement
If there is lead or galvanized pipe on the Utility-owned portion of the service line (from the
main to the curb stop), this portion will be replaced at no cost to you. However, the
replacement of the private lead or galvanized service (from the curb stop to the water meter) is
the responsibility of the property owner. Property owners have the choice of replacing the
water service before construction begins or having the service line replaced as part of the
construction contract. Generally, having the service line replaced as part of the construction
contract is easier and less expensive. The cost of replacing a private service line during a
construction event and in conjunction with a sanitary lateral replacement is estimated to be
approximately $1,500.00.
Carriage Walk
If a carriage walk exists adjacent to your property, between the City sidewalk and roadway, it
will be removed with our project. If you would like to pay for this to remain, please contact the
City for an estimated cost.
During the course of this project, there will be inconveniences such as noise, travel delays,
dust, and other issues associated with street construction. The City of Neenah and the
contractor are committed to working with the property owners to make this project run as
smoothly as possible.
February 28, 2024
P a g e | 3
If you would like to receive weekly emails on construction updates, you can sign up for the
Construction Newsletter on the City of Neenah webpage (www.ci.neenah.wi.us) under the
Department of Public Works. We thank you for your help and patience during this construction
project. Please contact our department if you require special consideration for accessibility. If
you have any questions, contact the individuals listed below or the Public Works Department at
920-886-6240.
City of Neenah Engineer ............... Jason Eckhart ......................... 920-886-6246
City of Neenah Engineer ............... Heath Kummerow ................. 920-886-6245
David Tenor Corporation... ........... David Tenor ........................... 920-360-9246
Sincerely,
Gerry Kaiser, PE
Director of Public Works
cc: Mayor Lang
Police Chief Olson
Fire Chief Kloehn
Aldermen
Neenah
W I S C O N S I N
Department of Public Works
211 Walnut St., P.O. Box 426, Neenah, WI 54957-0426
Phone: 920-886-6240 Fax: 920-886-6250
March 1, 2024
WILLIAM & SARAH BLACKBURN
649 BELMONT CT
NEENAH WI 54956
RE: 649 BELMONT CT
The City's contractor, David Tenor Corporation, will begin utility and street construction on
Belmont Avenue, Belmont Court, Cedar Street, and Stevens Street in the next week(s).
Construction will be completed by November 2024. We will need your help to make this a
successful project.
General Project Sequence
The project will consist of the following work:
Install new sanitary sewer main
Install new water main
Install new sanitary laterals and water services
Install new storm sewer
Rest period (Contractor will not work for 1 month to allow trenches to settle more than
can be achieved with mechanical compaction)
Remove existing roadway (asphalt, and the existing stone base)
Install geogrid and new aggregate road base
Install/repair concrete curb & gutter and place concrete pavement
Repair/replace existing concrete sidewalk/driveway aprons and install new sidewalk
Restore terrace areas with topsoil, grass seed, fertilizer, and hydro-mulch
Install new hot mix asphalt roadway (two lifts)
Garbage / Postal Service / Emergency Services
During construction, refuse and recycling pick-up will continue on your regularly
scheduled day. Please have your carts out before 6:30 A.M. when the construction crew
is working on your street. Carts should be placed on the street or terrace area.
The postal service will continue delivering and collecting mail as usual.
Emergency services have been notified of the construction activity and will plan
accordingly.
February 28, 2024
P a g e | 2
Parking and Accessibility
The streets will be open to local traffic only and residents will have access to their driveways
during the majority of the project. Parking will not be permitted on the streets during the
construction day (7 AM to 5 PM). Parking is available on adjacent streets. Other than NO
PARKING zones, standard parking restrictions will be waived on adjacent streets for those
vehicles displaying one of the enclosed Construction Parking Permits. There will be a period
of time when residents will not have access to their driveways. This will occur during the
concrete street paving and during, curb/gutter and driveway construction, and will last
approximately 3 weeks. At least 24 hours advance notice will be given when limiting driveway
access.
Terrace Restoration
The contractor will complete the terrace restoration adjacent to your property. After topsoil is
placed and leveled, a mix of grass seed, fertilizer and mulch will be placed. Please water this
daily to keep the soil moist until the new grass is well established. Please mow the grass and
weeds when they reach 6". The grass should overtake the weeds with continued watering and
mowing. The contractor will notify you when to begin watering.
Private Sewer Lateral Replacement
Please return your Property Owner Authorization Form (pink sheet) if you have not
already done so. All sanitary laterals will be replaced to the homes unless previously relayed.
The cost estimate for the sanitary lateral for the property owner share is approximately
$3,000.00.
Water Services Replacement
If there is lead or galvanized pipe on the Utility-owned portion of the service line (from the
main to the curb stop), this portion will be replaced at no cost to you. However, the
replacement of the private lead or galvanized service (from the curb stop to the water meter) is
the responsibility of the property owner. Property owners have the choice of replacing the
water service before construction begins or having the service line replaced as part of the
construction contract. Generally, having the service line replaced as part of the construction
contract is easier and less expensive. The cost of replacing a private service line during a
construction event and in conjunction with a sanitary lateral replacement is estimated to be
approximately $1,500.00.
Carriage Walk
If a carriage walk exists adjacent to your property, between the City sidewalk and roadway, it
will be removed with our project. If you would like to pay for this to remain, please contact the
City for an estimated cost.
During the course of this project, there will be inconveniences such as noise, travel delays,
dust, and other issues associated with street construction. The City of Neenah and the
contractor are committed to working with the property owners to make this project run as
smoothly as possible.
February 28, 2024
P a g e | 3
If you would like to receive weekly emails on construction updates, you can sign up for the
Construction Newsletter on the City of Neenah webpage (www.ci.neenah.wi.us) under the
Department of Public Works. We thank you for your help and patience during this construction
project. Please contact our department if you require special consideration for accessibility. If
you have any questions, contact the individuals listed below or the Public Works Department at
920-886-6240.
City of Neenah Engineer ............... Jason Eckhart ......................... 920-886-6246
City of Neenah Engineer ............... Heath Kummerow ................. 920-886-6245
David Tenor Corporation... ........... David Tenor ........................... 920-360-9246
Sincerely,
Gerry Kaiser, PE
Director of Public Works
cc: Mayor Lang
Police Chief Olson
Fire Chief Kloehn
Aldermen
Neenah
W I S C O N S I N
Department of Public Works
211 Walnut St., P.O. Box 426, Neenah, WI 54957-0426
Phone: 920-886-6240 Fax: 920-886-6250
March 1, 2024
THOMAS & BARBARA BARTZ
645 BELMONT CT
NEENAH WI 54956
RE: 645 BELMONT CT
The City's contractor, David Tenor Corporation, will begin utility and street construction on
Belmont Avenue, Belmont Court, Cedar Street, and Stevens Street in the next week(s).
Construction will be completed by November 2024. We will need your help to make this a
successful project.
General Project Sequence
The project will consist of the following work:
Install new sanitary sewer main
Install new water main
Install new sanitary laterals and water services
Install new storm sewer
Rest period (Contractor will not work for 1 month to allow trenches to settle more than
can be achieved with mechanical compaction)
Remove existing roadway (asphalt, and the existing stone base)
Install geogrid and new aggregate road base
Install/repair concrete curb & gutter and place concrete pavement
Repair/replace existing concrete sidewalk/driveway aprons and install new sidewalk
Restore terrace areas with topsoil, grass seed, fertilizer, and hydro-mulch
Install new hot mix asphalt roadway (two lifts)
Garbage / Postal Service / Emergency Services
During construction, refuse and recycling pick-up will continue on your regularly
scheduled day. Please have your carts out before 6:30 A.M. when the construction crew
is working on your street. Carts should be placed on the street or terrace area.
The postal service will continue delivering and collecting mail as usual.
Emergency services have been notified of the construction activity and will plan
accordingly.
February 28, 2024
P a g e | 2
Parking and Accessibility
The streets will be open to local traffic only and residents will have access to their driveways
during the majority of the project. Parking will not be permitted on the streets during the
construction day (7 AM to 5 PM). Parking is available on adjacent streets. Other than NO
PARKING zones, standard parking restrictions will be waived on adjacent streets for those
vehicles displaying one of the enclosed Construction Parking Permits. There will be a period
of time when residents will not have access to their driveways. This will occur during the
concrete street paving and during, curb/gutter and driveway construction, and will last
approximately 3 weeks. At least 24 hours advance notice will be given when limiting driveway
access.
Terrace Restoration
The contractor will complete the terrace restoration adjacent to your property. After topsoil is
placed and leveled, a mix of grass seed, fertilizer and mulch will be placed. Please water this
daily to keep the soil moist until the new grass is well established. Please mow the grass and
weeds when they reach 6". The grass should overtake the weeds with continued watering and
mowing. The contractor will notify you when to begin watering.
Private Sewer Lateral Replacement
Please return your Property Owner Authorization Form (pink sheet) if you have not
already done so. All sanitary laterals will be replaced to the homes unless previously relayed.
The cost estimate for the sanitary lateral for the property owner share is approximately
$3,000.00.
Water Services Replacement
If there is lead or galvanized pipe on the Utility-owned portion of the service line (from the
main to the curb stop), this portion will be replaced at no cost to you. However, the
replacement of the private lead or galvanized service (from the curb stop to the water meter) is
the responsibility of the property owner. Property owners have the choice of replacing the
water service before construction begins or having the service line replaced as part of the
construction contract. Generally, having the service line replaced as part of the construction
contract is easier and less expensive. The cost of replacing a private service line during a
construction event and in conjunction with a sanitary lateral replacement is estimated to be
approximately $1,500.00.
Carriage Walk
If a carriage walk exists adjacent to your property, between the City sidewalk and roadway, it
will be removed with our project. If you would like to pay for this to remain, please contact the
City for an estimated cost.
During the course of this project, there will be inconveniences such as noise, travel delays,
dust, and other issues associated with street construction. The City of Neenah and the
contractor are committed to working with the property owners to make this project run as
smoothly as possible.
February 28, 2024
P a g e | 3
If you would like to receive weekly emails on construction updates, you can sign up for the
Construction Newsletter on the City of Neenah webpage (www.ci.neenah.wi.us) under the
Department of Public Works. We thank you for your help and patience during this construction
project. Please contact our department if you require special consideration for accessibility. If
you have any questions, contact the individuals listed below or the Public Works Department at
920-886-6240.
City of Neenah Engineer ............... Jason Eckhart ......................... 920-886-6246
City of Neenah Engineer ............... Heath Kummerow ................. 920-886-6245
David Tenor Corporation... ........... David Tenor ........................... 920-360-9246
Sincerely,
Gerry Kaiser, PE
Director of Public Works
cc: Mayor Lang
Police Chief Olson
Fire Chief Kloehn
Aldermen
Neenah
W I S C O N S I N
Department of Public Works
211 Walnut St., P.O. Box 426, Neenah, WI 54957-0426
Phone: 920-886-6240 Fax: 920-886-6250
March 1, 2024
CASSANDRA KRUEGER
641 BELMONT CT
NEENAH WI 54956
RE: 641 BELMONT CT
The City's contractor, David Tenor Corporation, will begin utility and street construction on
Belmont Avenue, Belmont Court, Cedar Street, and Stevens Street in the next week(s).
Construction will be completed by November 2024. We will need your help to make this a
successful project.
General Project Sequence
The project will consist of the following work:
Install new sanitary sewer main
Install new water main
Install new sanitary laterals and water services
Install new storm sewer
Rest period (Contractor will not work for 1 month to allow trenches to settle more than
can be achieved with mechanical compaction)
Remove existing roadway (asphalt, and the existing stone base)
Install geogrid and new aggregate road base
Install/repair concrete curb & gutter and place concrete pavement
Repair/replace existing concrete sidewalk/driveway aprons and install new sidewalk
Restore terrace areas with topsoil, grass seed, fertilizer, and hydro-mulch
Install new hot mix asphalt roadway (two lifts)
Garbage / Postal Service / Emergency Services
During construction, refuse and recycling pick-up will continue on your regularly
scheduled day. Please have your carts out before 6:30 A.M. when the construction crew
is working on your street. Carts should be placed on the street or terrace area.
The postal service will continue delivering and collecting mail as usual.
Emergency services have been notified of the construction activity and will plan
accordingly.
February 28, 2024
P a g e | 2
Parking and Accessibility
The streets will be open to local traffic only and residents will have access to their driveways
during the majority of the project. Parking will not be permitted on the streets during the
construction day (7 AM to 5 PM). Parking is available on adjacent streets. Other than NO
PARKING zones, standard parking restrictions will be waived on adjacent streets for those
vehicles displaying one of the enclosed Construction Parking Permits. There will be a period
of time when residents will not have access to their driveways. This will occur during the
concrete street paving and during, curb/gutter and driveway construction, and will last
approximately 3 weeks. At least 24 hours advance notice will be given when limiting driveway
access.
Terrace Restoration
The contractor will complete the terrace restoration adjacent to your property. After topsoil is
placed and leveled, a mix of grass seed, fertilizer and mulch will be placed. Please water this
daily to keep the soil moist until the new grass is well established. Please mow the grass and
weeds when they reach 6". The grass should overtake the weeds with continued watering and
mowing. The contractor will notify you when to begin watering.
Private Sewer Lateral Replacement
Please return your Property Owner Authorization Form (pink sheet) if you have not
already done so. All sanitary laterals will be replaced to the homes unless previously relayed.
The cost estimate for the sanitary lateral for the property owner share is approximately
$3,000.00.
Water Services Replacement
If there is lead or galvanized pipe on the Utility-owned portion of the service line (from the
main to the curb stop), this portion will be replaced at no cost to you. However, the
replacement of the private lead or galvanized service (from the curb stop to the water meter) is
the responsibility of the property owner. Property owners have the choice of replacing the
water service before construction begins or having the service line replaced as part of the
construction contract. Generally, having the service line replaced as part of the construction
contract is easier and less expensive. The cost of replacing a private service line during a
construction event and in conjunction with a sanitary lateral replacement is estimated to be
approximately $1,500.00.
Carriage Walk
If a carriage walk exists adjacent to your property, between the City sidewalk and roadway, it
will be removed with our project. If you would like to pay for this to remain, please contact the
City for an estimated cost.
During the course of this project, there will be inconveniences such as noise, travel delays,
dust, and other issues associated with street construction. The City of Neenah and the
contractor are committed to working with the property owners to make this project run as
smoothly as possible.
February 28, 2024
P a g e | 3
If you would like to receive weekly emails on construction updates, you can sign up for the
Construction Newsletter on the City of Neenah webpage (www.ci.neenah.wi.us) under the
Department of Public Works. We thank you for your help and patience during this construction
project. Please contact our department if you require special consideration for accessibility. If
you have any questions, contact the individuals listed below or the Public Works Department at
920-886-6240.
City of Neenah Engineer ............... Jason Eckhart ......................... 920-886-6246
City of Neenah Engineer ............... Heath Kummerow ................. 920-886-6245
David Tenor Corporation... ........... David Tenor ........................... 920-360-9246
Sincerely,
Gerry Kaiser, PE
Director of Public Works
cc: Mayor Lang
Police Chief Olson
Fire Chief Kloehn
Aldermen
Neenah
W I S C O N S I N
Department of Public Works
211 Walnut St., P.O. Box 426, Neenah, WI 54957-0426
Phone: 920-886-6240 Fax: 920-886-6250
March 1, 2024
ANDREW & JENNIFER FOUCAULT
637 BELMONT CT
NEENAH WI 54956
RE: 637 BELMONT CT
The City's contractor, David Tenor Corporation, will begin utility and street construction on
Belmont Avenue, Belmont Court, Cedar Street, and Stevens Street in the next week(s).
Construction will be completed by November 2024. We will need your help to make this a
successful project.
General Project Sequence
The project will consist of the following work:
Install new sanitary sewer main
Install new water main
Install new sanitary laterals and water services
Install new storm sewer
Rest period (Contractor will not work for 1 month to allow trenches to settle more than
can be achieved with mechanical compaction)
Remove existing roadway (asphalt, and the existing stone base)
Install geogrid and new aggregate road base
Install/repair concrete curb & gutter and place concrete pavement
Repair/replace existing concrete sidewalk/driveway aprons and install new sidewalk
Restore terrace areas with topsoil, grass seed, fertilizer, and hydro-mulch
Install new hot mix asphalt roadway (two lifts)
Garbage / Postal Service / Emergency Services
During construction, refuse and recycling pick-up will continue on your regularly
scheduled day. Please have your carts out before 6:30 A.M. when the construction crew
is working on your street. Carts should be placed on the street or terrace area.
The postal service will continue delivering and collecting mail as usual.
Emergency services have been notified of the construction activity and will plan
accordingly.
February 28, 2024
P a g e | 2
Parking and Accessibility
The streets will be open to local traffic only and residents will have access to their driveways
during the majority of the project. Parking will not be permitted on the streets during the
construction day (7 AM to 5 PM). Parking is available on adjacent streets. Other than NO
PARKING zones, standard parking restrictions will be waived on adjacent streets for those
vehicles displaying one of the enclosed Construction Parking Permits. There will be a period
of time when residents will not have access to their driveways. This will occur during the
concrete street paving and during, curb/gutter and driveway construction, and will last
approximately 3 weeks. At least 24 hours advance notice will be given when limiting driveway
access.
Terrace Restoration
The contractor will complete the terrace restoration adjacent to your property. After topsoil is
placed and leveled, a mix of grass seed, fertilizer and mulch will be placed. Please water this
daily to keep the soil moist until the new grass is well established. Please mow the grass and
weeds when they reach 6". The grass should overtake the weeds with continued watering and
mowing. The contractor will notify you when to begin watering.
Private Sewer Lateral Replacement
Please return your Property Owner Authorization Form (pink sheet) if you have not
already done so. All sanitary laterals will be replaced to the homes unless previously relayed.
The cost estimate for the sanitary lateral for the property owner share is approximately
$3,000.00.
Water Services Replacement
If there is lead or galvanized pipe on the Utility-owned portion of the service line (from the
main to the curb stop), this portion will be replaced at no cost to you. However, the
replacement of the private lead or galvanized service (from the curb stop to the water meter) is
the responsibility of the property owner. Property owners have the choice of replacing the
water service before construction begins or having the service line replaced as part of the
construction contract. Generally, having the service line replaced as part of the construction
contract is easier and less expensive. The cost of replacing a private service line during a
construction event and in conjunction with a sanitary lateral replacement is estimated to be
approximately $1,500.00.
Carriage Walk
If a carriage walk exists adjacent to your property, between the City sidewalk and roadway, it
will be removed with our project. If you would like to pay for this to remain, please contact the
City for an estimated cost.
During the course of this project, there will be inconveniences such as noise, travel delays,
dust, and other issues associated with street construction. The City of Neenah and the
contractor are committed to working with the property owners to make this project run as
smoothly as possible.
February 28, 2024
P a g e | 3
If you would like to receive weekly emails on construction updates, you can sign up for the
Construction Newsletter on the City of Neenah webpage (www.ci.neenah.wi.us) under the
Department of Public Works. We thank you for your help and patience during this construction
project. Please contact our department if you require special consideration for accessibility. If
you have any questions, contact the individuals listed below or the Public Works Department at
920-886-6240.
City of Neenah Engineer ............... Jason Eckhart ......................... 920-886-6246
City of Neenah Engineer ............... Heath Kummerow ................. 920-886-6245
David Tenor Corporation... ........... David Tenor ........................... 920-360-9246
Sincerely,
Gerry Kaiser, PE
Director of Public Works
cc: Mayor Lang
Police Chief Olson
Fire Chief Kloehn
Aldermen
Neenah
W I S C O N S I N
Department of Public Works
211 Walnut St., P.O. Box 426, Neenah, WI 54957-0426
Phone: 920-886-6240 Fax: 920-886-6250
March 1, 2024
JOEL & KATE HOFF
633 BELMONT CT
NEENAH WI 54956
RE: 633 BELMONT CT
The City's contractor, David Tenor Corporation, will begin utility and street construction on
Belmont Avenue, Belmont Court, Cedar Street, and Stevens Street in the next week(s).
Construction will be completed by November 2024. We will need your help to make this a
successful project.
General Project Sequence
The project will consist of the following work:
Install new sanitary sewer main
Install new water main
Install new sanitary laterals and water services
Install new storm sewer
Rest period (Contractor will not work for 1 month to allow trenches to settle more than
can be achieved with mechanical compaction)
Remove existing roadway (asphalt, and the existing stone base)
Install geogrid and new aggregate road base
Install/repair concrete curb & gutter and place concrete pavement
Repair/replace existing concrete sidewalk/driveway aprons and install new sidewalk
Restore terrace areas with topsoil, grass seed, fertilizer, and hydro-mulch
Install new hot mix asphalt roadway (two lifts)
Garbage / Postal Service / Emergency Services
During construction, refuse and recycling pick-up will continue on your regularly
scheduled day. Please have your carts out before 6:30 A.M. when the construction crew
is working on your street. Carts should be placed on the street or terrace area.
The postal service will continue delivering and collecting mail as usual.
Emergency services have been notified of the construction activity and will plan
accordingly.
February 28, 2024
P a g e | 2
Parking and Accessibility
The streets will be open to local traffic only and residents will have access to their driveways
during the majority of the project. Parking will not be permitted on the streets during the
construction day (7 AM to 5 PM). Parking is available on adjacent streets. Other than NO
PARKING zones, standard parking restrictions will be waived on adjacent streets for those
vehicles displaying one of the enclosed Construction Parking Permits. There will be a period
of time when residents will not have access to their driveways. This will occur during the
concrete street paving and during, curb/gutter and driveway construction, and will last
approximately 3 weeks. At least 24 hours advance notice will be given when limiting driveway
access.
Terrace Restoration
The contractor will complete the terrace restoration adjacent to your property. After topsoil is
placed and leveled, a mix of grass seed, fertilizer and mulch will be placed. Please water this
daily to keep the soil moist until the new grass is well established. Please mow the grass and
weeds when they reach 6". The grass should overtake the weeds with continued watering and
mowing. The contractor will notify you when to begin watering.
Private Sewer Lateral Replacement
Please return your Property Owner Authorization Form (pink sheet) if you have not
already done so. All sanitary laterals will be replaced to the homes unless previously relayed.
The cost estimate for the sanitary lateral for the property owner share is approximately
$3,000.00.
Water Services Replacement
If there is lead or galvanized pipe on the Utility-owned portion of the service line (from the
main to the curb stop), this portion will be replaced at no cost to you. However, the
replacement of the private lead or galvanized service (from the curb stop to the water meter) is
the responsibility of the property owner. Property owners have the choice of replacing the
water service before construction begins or having the service line replaced as part of the
construction contract. Generally, having the service line replaced as part of the construction
contract is easier and less expensive. The cost of replacing a private service line during a
construction event and in conjunction with a sanitary lateral replacement is estimated to be
approximately $1,500.00.
Carriage Walk
If a carriage walk exists adjacent to your property, between the City sidewalk and roadway, it
will be removed with our project. If you would like to pay for this to remain, please contact the
City for an estimated cost.
During the course of this project, there will be inconveniences such as noise, travel delays,
dust, and other issues associated with street construction. The City of Neenah and the
contractor are committed to working with the property owners to make this project run as
smoothly as possible.
February 28, 2024
P a g e | 3
If you would like to receive weekly emails on construction updates, you can sign up for the
Construction Newsletter on the City of Neenah webpage (www.ci.neenah.wi.us) under the
Department of Public Works. We thank you for your help and patience during this construction
project. Please contact our department if you require special consideration for accessibility. If
you have any questions, contact the individuals listed below or the Public Works Department at
920-886-6240.
City of Neenah Engineer ............... Jason Eckhart ......................... 920-886-6246
City of Neenah Engineer ............... Heath Kummerow ................. 920-886-6245
David Tenor Corporation... ........... David Tenor ........................... 920-360-9246
Sincerely,
Gerry Kaiser, PE
Director of Public Works
cc: Mayor Lang
Police Chief Olson
Fire Chief Kloehn
Aldermen
Source: City of Neenah website. First collected Oct 17, 2026.