Utility Committee Regular Meeting Agenda Packet (PDF)
Village of Plover · Portage County · meeting of Feb 16, 2026 · Agenda packets
Open the original document More from Village of Plover
This document is no longer listed on Village of Plover's website. We kept the copy we read.
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
Agenda – Water/Wastewater Committee 02/12/26 11:32 AM
WATER/WASTEWATER UTILITY COMMITTEE AGENDA
Plover Municipal Board Room
2400 Post Road
Plover, WI 54467
Monday, February 16, 2026
5:10 p.m.
1. Call to order
2. Approval of the minutes of the meeting of January 19, 2026, as printed
3. Persons wishing to address the Committee
4. Approval of vouchers
Discussion with possible action on the following:
5. Utility Plans – Green Tree Farm Subdivision – Green Tree Construction Inc - Pleasant Drive/CTH R (PIN:
173230826-16.04)
6. Updating Emergency Water Agreement with City of Stevens Point
7. Updating Emergency Water Agreement with Village of Whiting
8. Approval of Well 1 Generator Project Bid
9. Village project change orders, substitutions, or construction approvals
10. Reports
a. Water System Manager
b. Wastewater System Manager
11. Adjournment subject to call of the chair
NOTICE IS HEREBY GIVEN that a majority of the members of the Village Board may attend this meeting to gather information
about a subject over which they have decision-making authority.
VILLAGE OF PLOVER
WATER/WASTEWATER UTILITY COMMITTEE
January 19, 2026
Members Present: Gary Wolf, Ross Ballard, Ken Brekke
Members Unexcused: Adam Raabe, Marv Hopp
Others Present: Karmen Anderson, Adam DeKleyn, Tim Durigan, Steve Fritz, Tracy Karnitz, Steve Kunst, Lyle
Lutz, Julia Mann, Matt Saloun, and Al Tessman
1. Mr. Wolf called the meeting to order at 5:10 p.m.
2. Mr. Brekke moved and Mr. Ballard seconded approval of the minutes of August 18, 2025.
Motion carried; copy attached.
3. There were no persons wishing to address the Committee.
4. Mr. Ballard moved, and Mr. Brekke seconded approval of the vouchers. Mr. Brekke wondered on the
vouchers that show as unpaid. Ms. Mann assured Mr. Brekke that voucher report was run prior to checks
being generated, however, the next meeting’s report will show the updated amounts. Motion carried;
copy attached.
Discussion with possible action on the following:
5. Proposed Empire Estates Subdivision – Plover Rd./Wilson Ave. (PIN 173230828-01.13) Utility
Plans
Mr. Saloun reviewed the request. Water Department recommends approval. Mr. Lutz reviewed the
request. Wastewater Department recommends approval. Mr. Brekke asked about well capacities. Mr.
Saloun stated there will be no impact.
***RECOMMENDATION TO VILLAGE BOARD*** Mr. Brekke moved and Mr. Ballard seconded
approval of Proposed Empire Estates Subdivision – Plover Rd./Wilson Ave. (PIN 173230828-01.13) Utility
Plans. Motion carried; copy attached.
6. 2026 Water Utility Budget
Mr. Saloun reviewed budget memo and the water department budget. The Water Department is looking
to add a fifth operator with a tentative start date in April 2026. Labor costs for the fifth operator are
included in the proposed budget. Capital Outlay includes the Well 1 backup generator project which
aligns with DNR recommendations along with future planning projects. Mr. Brekke inquired about any
anticipated retirements. Discussion ensured regarding the addition of another employee along with
possible PSC rate studies. Mr. Kunst added there will be future discussions regarding rate analysis in
both Water and Wastewater departments.
***RECOMMENDATION TO VILLAGE BOARD***Mr. Brekke moved and Mr. Ballard seconded
approval of the Water Utility Budget as presented. Motion carried; copy attached.
7. 2026 Wastewater Utility Budget
Mr. Lutz reviewed the Wastewater system memo and proposed budget to highlight upcoming
reconstruction of the River Road lift station. Mr. Kunst highlighted the fact that Wastewater utility is
able to cover capital costs by utilizing fund balance reserves. Currently, the utility is working through
facility design review and collection systems master plan. Mr. Brekke inquired about any impact on the
utility from recent renovations at Mullins Whey. Mr. Lutz stated they are not seeing any major effects to
the Wastewater utility as Mullins has their own treatment facility on site.
***RECOMMENDATION TO VILLAGE BOARD***Mr. Brekke moved and Mr. Ballard seconded
approval of the Wastewater Utility Budget as presented. Motion carried; copy attached.
8. There were no Village project change orders, substitutions, or construction approvals.
9. Reports
a. Mr. Saloun reviewed his report to highlight a successful fall season of leak detection throughout the
Village.
b. Mr. Lutz reviewed his report.
10. Mr. Ballard moved and Mr. Brekke seconded adjournment at 5:45 p.m. Motion carried.
Submitted by Tracy Karnitz
Village of Plover Payment Approval Report - Utilities Water Page: 1
Report dates: 1/19/2026-2/12/2026 Feb 13, 2026 08:32AM
Report Criteria:
Detail report.
Invoices with totals above $0.00 included.
Paid and unpaid invoices included.
[Report].GL Account Number (3 Characters) = "700"
Vendor Vendor Name Invoice Number Description Invoice Date Net Amount Paid Date Paid Voided
Invoice Amount
700
122 AMERICAN WATER WORKS AS SO279047 AMERICAN WATER WORKS AS 12/19/2025 260.00 260.00 01/30/2026
123 AMERICAN WELDING & GAS IN 0010326845 AMERICAN WELDING & GAS IN 08/31/2024 31.00 31.00 02/05/2026
123 AMERICAN WELDING & GAS IN 845063 WELDING GAS 02/04/2026 80.23 .00
195 AT&T- NEW PHONES 831-001- 20 4542580116 JANUARY 01/22/2026 108.43 108.43 01/22/2026
311 BIG IRON EQUIPMENT INC 90659 METER TEST METAL 01/30/2026 27.00 27.00 01/30/2026
311 BIG IRON EQUIPMENT INC 90716 METER TESTING HOSE 02/06/2026 54.03 .00
311 BIG IRON EQUIPMENT INC 90759 STORAGE ACCESSORY 02/11/2026 319.57 .00
331 BOARDMAN CLARK LAW FIRM 312668 DISK TOWER NSIGHT 01/21/2026 1,232.00 1,232.00 01/30/2026
331 BOARDMAN CLARK LAW FIRM 312669 DISK TOWER-AT&T 01/21/2026 346.50 346.50 01/30/2026
422 CARGILL INC - SALT DIVISION 2911964933 CARGILL INC - SALT DIVISION 01/21/2026 7,537.30 7,537.30 01/30/2026
446 CELLCOM 659610 CELLPHONES 01/23/2026 427.85 427.85 01/30/2026
682 DAKOTA SUPPLY GROUP S105390233.0 UNIT HEATER HANGER 01/26/2026 1,016.10 1,016.10 01/30/2026
682 DAKOTA SUPPLY GROUP S105403319.0 UNIT HEATER HANGER 01/30/2026 32.69 32.69 02/05/2026
1192 HEARTLAND BUSINESS SYSTE 860032-H BARRACUDA BACKUP 2026 02/10/2026 64.10 .00
1192 HEARTLAND BUSINESS SYSTE 860032-H BARRACUDA BACKUP 2026 02/10/2026 1,923.08 .00
1192 HEARTLAND BUSINESS SYSTE 860032-H BARRACUDA EMAIL 2026 02/10/2026 35.72 .00
1192 HEARTLAND BUSINESS SYSTE 860032-H BARRACUDA EMAIL 2026 02/10/2026 500.08 .00
3669 INVOICE CLOUD, INC 2822-2026_1 JANUARY 02/05/2026 243.17 243.17 02/05/2026
1464 KRAMAR CHAD CK_0128_2026 KRAMAR, CHAD 01/28/2026 122.70 122.70 01/30/2026
1464 KRAMAR CHAD CK_0201_2026 KRAMAR, CHAD 02/01/2026 253.16 253.16 02/05/2026
1488 KWIK TRIP INC JANUARY 202 JANUARY FUEL 02/04/2026 892.46 892.46 02/05/2026
1652 MARTELLE WATER TREATMEN 30816 MARTELLE WATER TREATMEN 01/12/2026 1,496.62 1,496.62 01/22/2026
1692 MENARDS INC 35308 SHELVING BOARDS 01/13/2026 135.92 135.92 01/22/2026
1692 MENARDS INC 35671 METER CART 01/20/2026 49.61 49.61 01/22/2026
1692 MENARDS INC 35755 CLEANING SUPPLIES 01/21/2026 103.84 103.84 01/22/2026
1692 MENARDS INC 35970 CEILING FURNACE 01/26/2026 53.52 53.52 01/30/2026
1692 MENARDS INC 36123 METER TESTING BENCH 01/29/2026 10.48 10.48 02/05/2026
1692 MENARDS INC 36188 METER TESTING 01/30/2026 114.06 114.06 02/05/2026
1692 MENARDS INC 36201 METER TESTING 01/30/2026 10.86 10.86 02/05/2026
1692 MENARDS INC 36352 CABINET 02/03/2026 496.78 496.78 02/05/2026
1692 MENARDS INC 36359 VEHICLE SHELVES 02/03/2026 59.97 .00
1692 MENARDS INC 36391 PAINTING 02/03/2026 52.40 52.40 02/05/2026
1692 MENARDS INC 36420 GARAGE DOOR BATTERY 02/04/2026 4.48 .00
1692 MENARDS INC 36474 CLAMPS 02/05/2026 12.99 .00
1692 MENARDS INC 36491 PAINTING 02/05/2026 151.22 .00
1692 MENARDS INC 36534 BREAKROOM REMODEL 02/06/2026 113.23 .00
1692 MENARDS INC 36548 HOSE CLAMPS 02/06/2026 14.99 .00
1692 MENARDS INC 36701 WELL 3 PAINTING 02/10/2026 74.97 .00
1692 MENARDS INC 36764 BREAKROOM REMODEL 02/11/2026 119.99 .00
1692 MENARDS INC 36765 COUNTERTOP 02/11/2026 97.98- .00
1692 MENARDS INC 36770 TOOLS 02/11/2026 4.99 .00
3682 METRON FARNIER LLC 992408640 METERS 01/29/2026 7,949.61 7,949.61 01/30/2026
1716 MID-STATE TECHNICAL COLLE MSW40825 AHA CARDS 01/26/2026 120.00 120.00 01/30/2026
1890 NORTHWAY COMMUNICATIONS 186463 RADIO NEW TRUCK 01/21/2026 1,386.50 1,386.50 01/22/2026
1890 NORTHWAY COMMUNICATIONS 186513 TRUCK RADIO 01/30/2026 1,094.00 1,094.00 02/05/2026
2196 PUBLIC SERVICE COMMISSION 2512-I-04737 4737-CW-106 WELL 1 GENERAT 01/16/2026 591.96 591.96 01/22/2026
2312 ROBERTS IRRIGATION CO INC AR00009715 WELL PACKING 01/16/2026 39.68 39.68 02/05/2026
2383 SALOUN MATT MS0122_2026 SALOUN, MATT 01/22/2026 274.10 274.10 01/30/2026
3443 SCHMEISER, NICHOLAS 01162026 WRENCHES 01/16/2026 105.45 105.45 01/22/2026
2471 SIGNS & DESIGNS / COPY CON 3140 DECALS 09/17/2025 60.00 60.00 01/30/2026
Village of Plover Payment Approval Report - Utilities Water Page: 2
Report dates: 1/19/2026-2/12/2026 Feb 13, 2026 08:32AM
Vendor Vendor Name Invoice Number Description Invoice Date Net Amount Paid Date Paid Voided
Invoice Amount
2471 SIGNS & DESIGNS / COPY CON 3168 DECALS 01/19/2026 60.00 60.00 01/30/2026
2528 SPEE DEE DELIVERY SERVICE 1408633 FLUORIDE 01/31/2026 7.88 .00
2802 TRUCKSHOP USA 887008 ACCESSORIES 01/21/2026 520.00 520.00 01/30/2026
2841 US BANK - VILLAGE VISA CHAR DECEMBER 2 AMAZON 01/27/2026 437.79 437.79 01/30/2026
2841 US BANK - VILLAGE VISA CHAR DECEMBER 2 AMAZON 01/27/2026 149.38 149.38 01/30/2026
2841 US BANK - VILLAGE VISA CHAR DECEMBER 2 AMAZON 01/27/2026 90.84 90.84 01/30/2026
2841 US BANK - VILLAGE VISA CHAR DECEMBER 2 AMAZON 01/27/2026 90.84- 90.84- 01/30/2026
2841 US BANK - VILLAGE VISA CHAR DECEMBER 2 AMAZON 01/27/2026 94.89 94.89 01/30/2026
2841 US BANK - VILLAGE VISA CHAR DECEMBER 2 VEOLIA ENVIRONMENTAL 01/27/2026 166.68 166.68 01/30/2026
3735 UTILITY SERVICE CO INC 641312 DISK TOWER MAINTENANCE 01/01/2026 131,556.00 131,556.00 01/22/2026
3748 VMC LLC 1650 DISK AT&T 11/25/2025 1,379.38 1,379.38 02/05/2026
3748 VMC LLC 1650 DISK NSIGHT 11/25/2025 1,379.37 1,379.37 02/05/2026
3071 WI DEPT NATURAL RESOURCE C.GAYLORD O COLTEN GAYLORD OPERATOR 01/29/2026 25.00 25.00 01/30/2026
3169 WI PUBLIC SERVICE CORPORA DECEMBER 2 DECEMBER 01/21/2026 8,728.10 8,728.10 01/22/2026
3169 WI PUBLIC SERVICE CORPORA JANUARY 202 JANUARY 02/03/2026 10,091.75 10,091.75 02/05/2026
3183 WI STATE LAB OF HYGIENE - A 833451 FLUORIDE TESTING 01/31/2026 31.00 31.00 02/05/2026
3245 WISCONSIN RURAL WATER AS 1.23.2026 2026 TECH CONFERENCE 01/23/2026 540.00 540.00 01/30/2026
3245 WISCONSIN RURAL WATER AS WRWA_0129_ TRAINING 01/27/2026 240.00 240.00 01/30/2026
3245 WISCONSIN RURAL WATER AS WRWA_0211_ TRAINING 02/11/2026 70.00 .00
3245 WISCONSIN RURAL WATER AS WRWA_0218_ TRAINING 01/27/2026 240.00 240.00 01/30/2026
Total 700: 185,828.63 182,315.09
Grand Totals: 185,828.63 182,315.09
Village of Plover Payment Approval Report - Utilities Water Page: 3
Report dates: 1/19/2026-2/12/2026 Feb 13, 2026 08:32AM
Vendor Vendor Name Invoice Number Description Invoice Date Net Amount Paid Date Paid Voided
Invoice Amount
Dated:
______________________________________________________
Village President: Gary Wolf
_____________________________________________________
Village Board :
Steve Fritz: ______________________________________________________
Tim Durigan: ______________________________________________________
Ross Ballard: ______________________________________________________
Adam Raabe: ______________________________________________________
Al Haga: ______________________________________________________
Al Tessman: ______________________________________________________
Administrator: Steve Kunst
_____________________________________________________
Village of Plover Payment Approval Report - Utilities Water Page: 4
Report dates: 1/19/2026-2/12/2026 Feb 13, 2026 08:32AM
Vendor Vendor Name Invoice Number Description Invoice Date Net Amount Paid Date Paid Voided
Invoice Amount
Report Criteria:
Detail report.
Invoices with totals above $0.00 included.
Paid and unpaid invoices included.
[Report].GL Account Number (3 Characters) = "700"
Village of Plover Payment Approval Report - Utilities WWTP Page: 1
Report dates: 1/19/2026-2/12/2026 Feb 13, 2026 08:33AM
Report Criteria:
Detail report.
Invoices with totals above $0.00 included.
Paid and unpaid invoices included.
[Report].GL Account Number (3 Characters) = "600"
Vendor Vendor Name Invoice Number Description Invoice Date Net Amount Paid Date Paid Voided
Invoice Amount
600
123 AMERICAN WELDING & GAS IN 0011413645 WELDING GAS 01/30/2026 30.62 30.62 02/05/2026
154 APPLIED INDUSTRIAL TECHNO 7033806962 BEARINGS AND SEAL SLEEVES 01/26/2026 307.01 307.01 02/05/2026
186 ASPIRUS MEDICAL GROUP INC 153130 RANDOM DOT POOL 02/02/2026 53.00 53.00 02/05/2026
186 ASPIRUS MEDICAL GROUP INC 154026 JACOBY 02/03/2026 72.50 72.50 02/05/2026
186 ASPIRUS MEDICAL GROUP INC 154026 JEPSON 02/03/2026 72.50 72.50 02/05/2026
195 AT&T- NEW PHONES 831-001- 20 4542580116 JANUARY 01/22/2026 162.64 162.64 01/22/2026
3818 BAY TOWEL INC JANUARY 202 JANUARY UNIFORMS 02/03/2026 427.50 427.50 02/05/2026
446 CELLCOM 662314 CELLCOM 01/23/2026 124.63 124.63 02/05/2026
610 COOPER OIL COMPANY INC 286208 RANDO 32 AIR COMPRESSOR 01/16/2026 179.90 179.90 02/05/2026
660 CT LABORATORIES LLC 201966 INDUSTRIAL FOG TESTING 01/22/2026 750.00 750.00 01/30/2026
919 FASTENAL COMPANY INC WISTE319102 BUILDING/CLEANING SUPPLIE 01/26/2026 144.50 144.50 01/30/2026
1970 GERBER COLLISION & GLASS - 6203512863 INS CLAIM VEH REPAIR 22 F350 02/05/2026 7,378.67 .00
1192 HEARTLAND BUSINESS SYSTE 860032-H BARRACUDA BACKUP 2026 02/10/2026 64.11 .00
1192 HEARTLAND BUSINESS SYSTE 860032-H BARRACUDA BACKUP 2026 02/10/2026 1,923.08 .00
1192 HEARTLAND BUSINESS SYSTE 860032-H BARRACUDA EMAIL 2026 02/10/2026 35.72 .00
1192 HEARTLAND BUSINESS SYSTE 860032-H BARRACUDA EMAIL 2026 02/10/2026 500.08 .00
3669 INVOICE CLOUD, INC 2822-2026_1 JANUARY 02/05/2026 243.17 243.17 02/05/2026
1488 KWIK TRIP INC JANUARY 202 JANUARY FUEL 02/04/2026 273.31 273.31 02/05/2026
1493 L&S ELECTRIC INC 0048946 ROOTS BLOWER REBUILD 01/20/2026 11,975.00 11,975.00 01/22/2026
1692 MENARDS INC 35759 DIESEL DEF 01/21/2026 61.92 61.92 01/22/2026
1692 MENARDS INC 35759 VEHICLE MAINT 01/21/2026 17.53 17.53 01/22/2026
1692 MENARDS INC 35759 MAINT SUPPLIES 01/21/2026 218.47 218.47 01/22/2026
1692 MENARDS INC 36089 PADLOCKS FOR SAFETY LOCK 01/28/2026 27.97 27.97 01/30/2026
1692 MENARDS INC 36134 MAINT. SUPPLIES 01/30/2026 32.38 32.38 02/05/2026
1692 MENARDS INC 36189 LED LIGHT BULBS AND MAINT 01/30/2026 218.63 218.63 02/05/2026
1692 MENARDS INC 36355 LAB REFRIDGERATOR 02/03/2026 158.00 158.00 02/05/2026
1716 MID-STATE TECHNICAL COLLE MSW40825 AHA CARDS 01/26/2026 140.00 140.00 01/30/2026
1811 NAPA - CENTRAL WI AUTO PAR 2601 VEHICLE MAINTENANCE 01/31/2026 85.12 85.12 02/05/2026
3847 NJT AUTOMATION 437 AB MICROLOGIC REFURBISHM 01/30/2026 750.00 750.00 02/05/2026
3710 RIVER AUTOMATION, INC Q26007 PLC TROUBLESHOOTING AND 01/15/2026 1,073.10 1,073.10 01/30/2026
3424 SOLARUS 11881268 WWTF PHONE SERVICE 02/01/2026 17.29 17.29 01/30/2026
2500 SOLENIS LLC 135205597 K144 POLYMER 01/22/2026 10,273.63 .00
2841 US BANK - VILLAGE VISA CHAR DECEMBER 2 AMAZON 01/27/2026 219.00 219.00 01/30/2026
2841 US BANK - VILLAGE VISA CHAR DECEMBER 2 AMAZON 01/27/2026 116.17 116.17 01/30/2026
2841 US BANK - VILLAGE VISA CHAR DECEMBER 2 AMAZON 01/27/2026 22.45 22.45 01/30/2026
2841 US BANK - VILLAGE VISA CHAR DECEMBER 2 FED EX 01/27/2026 205.50 205.50 01/30/2026
2841 US BANK - VILLAGE VISA CHAR DECEMBER 2 AMAZON 01/27/2026 8.14 8.14 01/30/2026
2841 US BANK - VILLAGE VISA CHAR DECEMBER 2 AMAZON 01/27/2026 48.69- 48.69- 01/30/2026
2841 US BANK - VILLAGE VISA CHAR DECEMBER 2 AMAZON 01/27/2026 96.78 96.78 01/30/2026
2841 US BANK - VILLAGE VISA CHAR DECEMBER 2 AMAZON 01/27/2026 63.96 63.96 01/30/2026
2841 US BANK - VILLAGE VISA CHAR DECEMBER 2 AMAZON 01/27/2026 59.49 59.49 01/30/2026
2841 US BANK - VILLAGE VISA CHAR DECEMBER 2 AMAZON WEB 01/27/2026 .52 .52 01/30/2026
2841 US BANK - VILLAGE VISA CHAR DECEMBER 2 APPLE.COM 01/27/2026 13.70 13.70 01/30/2026
2841 US BANK - VILLAGE VISA CHAR DECEMBER 2 EBAY 01/27/2026 194.15 194.15 01/30/2026
2841 US BANK - VILLAGE VISA CHAR DECEMBER 2 AMAZON 01/27/2026 22.75 22.75 01/30/2026
2841 US BANK - VILLAGE VISA CHAR DECEMBER 2 FMCSA D&A 01/27/2026 7.88 7.88 01/30/2026
2841 US BANK - VILLAGE VISA CHAR DECEMBER 2 AMAZON 01/27/2026 242.55 242.55 01/30/2026
2843 US CELLULAR 783464325 JANUARY PHONES 01/27/2026 82.23 82.23 01/30/2026
2856 USA BLUEBOOK INV00941468 CHEM PMP PARTS 01/21/2026 61.25 61.25 01/22/2026
2856 USA BLUEBOOK INV00942584 POLYMER CLEANING SOLUTIO 01/22/2026 271.94 271.94 01/30/2026
Village of Plover Payment Approval Report - Utilities WWTP Page: 2
Report dates: 1/19/2026-2/12/2026 Feb 13, 2026 08:33AM
Vendor Vendor Name Invoice Number Description Invoice Date Net Amount Paid Date Paid Voided
Invoice Amount
3029 WERNER ELECTRIC SUPPLY C S7951944.001 COMPACTLOGIX CONTROLLER 01/15/2026 1,748.02 1,748.02 01/30/2026
3131 WI DEPT OF WORKFORCE DEV 693388-000-1- GRUBER UNEMPLOYMENT 02/09/2026 138.60 .00
3169 WI PUBLIC SERVICE CORPORA DECEMBER 2 DECEMBER 01/21/2026 25,357.13 25,357.13 01/22/2026
3169 WI PUBLIC SERVICE CORPORA DECEMBER 2 DECEMBER 01/21/2026 2,828.76 2,828.76 01/22/2026
3169 WI PUBLIC SERVICE CORPORA JANUARY 202 JANUARY 02/03/2026 26,750.41 26,750.41 02/05/2026
3169 WI PUBLIC SERVICE CORPORA JANUARY 202 JANUARY 02/03/2026 4,616.99 4,616.99 02/05/2026
3183 WI STATE LAB OF HYGIENE - A 30038098 PROFICIENCY TESTING 10/01/2025 292.00 292.00 02/05/2026
Total 600: 101,163.66 80,849.77
Grand Totals: 101,163.66 80,849.77
Village of Plover Payment Approval Report - Utilities WWTP Page: 3
Report dates: 1/19/2026-2/12/2026 Feb 13, 2026 08:33AM
Vendor Vendor Name Invoice Number Description Invoice Date Net Amount Paid Date Paid Voided
Invoice Amount
Dated:
______________________________________________________
Village President: Gary Wolf
_____________________________________________________
Village Board :
Steve Fritz: ______________________________________________________
Tim Durigan: ______________________________________________________
Ross Ballard: ______________________________________________________
Adam Raabe: ______________________________________________________
Al Haga: ______________________________________________________
Al Tessman: ______________________________________________________
Administrator: Steve Kunst
_____________________________________________________
Village of Plover Payment Approval Report - Utilities WWTP Page: 4
Report dates: 1/19/2026-2/12/2026 Feb 13, 2026 08:33AM
Vendor Vendor Name Invoice Number Description Invoice Date Net Amount Paid Date Paid Voided
Invoice Amount
Report Criteria:
Detail report.
Invoices with totals above $0.00 included.
Paid and unpaid invoices included.
[Report].GL Account Number (3 Characters) = "600"
Plover Water System, 300 Waters Way, P.O. Box 37, Plover, WI 54467 345-5250, 345-5248
Green Tree Subdvision Memo- 2026 Page 1 of 1 Printed: 2/13/2026 8:44:00 AM
Agenda Item:
Discussion/Action: Utility Plans-Green Tree Farm Subdivision- Green Tree
Constuction Inc-Pleasant Drive/ CTH R
a. The Water Department has reviewed the water utility plans submitted
for the Green Tree Farm Subdivision located at Pleasant Drive/ CTH
R. Plans meet installation standards and Village specifications.
Recommendation: Approval of plans submitted by Green Tree
Construction Inc
Water System Memo
To: Utility Committee, President Wolf, Steve Kunst
From: Matt Saloun, Water System Manager
Date: 02/16/2026
Subject: Green Tree Subdivision-2026
STAMP/SIGNATURE:SCALE NOTE:SURVEYED BY: DV, TV, & CBDESIGNER: DUSTIN VREELANDFILE NO.: 25-0579 ENGINEERINGPROJECT:LOCATION:REVISIONSDATEBYDESCRIPTION
SHEETSCALE:DATE: NOVEMBER 24TH, 2025
TITLE PAGE:
PREPARED FOR:PLAN DATE:C1NO SCALE
EBFOSSSS
SS SSSSFOFO G
G UMT
STSS
MWMPGGMCFTAC
SK
FOFOTSWPWEEMETEOEBWF
STAMP/SIGNATURE:SCALE NOTE:SURVEYED BY: DV, TV, & CBDESIGNER: DUSTIN VREELANDFILE NO.: 25-0579 ENGINEERINGPROJECT:LOCATION:REVISIONSDATEBYDESCRIPTION
SHEETSCALE:DATE: NOVEMBER 24TH, 2025
TITLE PAGE:
PREPARED FOR:PLAN DATE:C21" = 50'
EBFOSSSS
SS SSSSFOFO G
G
STAMP/SIGNATURE:SCALE NOTE:SURVEYED BY: DV, TV, & CBDESIGNER: DUSTIN VREELANDFILE NO.: 25-0579 ENGINEERINGPROJECT:LOCATION:REVISIONSDATEBYDESCRIPTION
SHEETSCALE:DATE: NOVEMBER 24TH, 2025
TITLE PAGE:
PREPARED FOR:PLAN DATE:C31" = 50'
EBFOSSSS
SS SSSSFOFO G
G
STAMP/SIGNATURE:SCALE NOTE:SURVEYED BY: DV, TV, & CBDESIGNER: DUSTIN VREELANDFILE NO.: 25-0579 ENGINEERINGPROJECT:LOCATION:REVISIONSDATEBYDESCRIPTION
SHEETSCALE:DATE: NOVEMBER 24TH, 2025
TITLE PAGE:
PREPARED FOR:PLAN DATE:C41" = 50'
EBFOSSSS
SS SSSSFOFO G
G
STAMP/SIGNATURE:SCALE NOTE:SURVEYED BY: DV, TV, & CBDESIGNER: DUSTIN VREELANDFILE NO.: 25-0579 ENGINEERINGPROJECT:LOCATION:REVISIONSDATEBYDESCRIPTION
SHEETSCALE:DATE: NOVEMBER 24TH, 2025
TITLE PAGE:
PREPARED FOR:PLAN DATE:C51" = 50'
SSFOFO
STAMP/SIGNATURE:SCALE NOTE:SURVEYED BY: DV, TV, & CBDESIGNER: DUSTIN VREELANDFILE NO.: 25-0579 ENGINEERINGPROJECT:LOCATION:REVISIONSDATEBYDESCRIPTION
SHEETSCALE:DATE: NOVEMBER 24TH, 2025
TITLE PAGE:
PREPARED FOR:PLAN DATE:C61" = 20'
STAMP/SIGNATURE:SCALE NOTE:SURVEYED BY: DV, TV, & CBDESIGNER: DUSTIN VREELANDFILE NO.: 25-0579 ENGINEERINGPROJECT:LOCATION:REVISIONSDATEBYDESCRIPTION
SHEETSCALE:DATE: NOVEMBER 24TH, 2025
TITLE PAGE:
PREPARED FOR:PLAN DATE:C71" = 20'
STAMP/SIGNATURE:SCALE NOTE:SURVEYED BY: DV, TV, & CBDESIGNER: DUSTIN VREELANDFILE NO.: 25-0579 ENGINEERINGPROJECT:LOCATION:REVISIONSDATEBYDESCRIPTION
SHEETSCALE:DATE: NOVEMBER 24TH, 2025
TITLE PAGE:
PREPARED FOR:PLAN DATE:C81" = 20'
STAMP/SIGNATURE:SCALE NOTE:SURVEYED BY: DV, TV, & CBDESIGNER: DUSTIN VREELANDFILE NO.: 25-0579 ENGINEERINGPROJECT:LOCATION:REVISIONSDATEBYDESCRIPTION
SHEETSCALE:DATE: NOVEMBER 24TH, 2025
TITLE PAGE:
PREPARED FOR:PLAN DATE:C91" = 20'
G
STAMP/SIGNATURE:SCALE NOTE:SURVEYED BY: DV, TV, & CBDESIGNER: DUSTIN VREELANDFILE NO.: 25-0579 ENGINEERINGPROJECT:LOCATION:REVISIONSDATEBYDESCRIPTION
SHEETSCALE:DATE: NOVEMBER 24TH, 2025
TITLE PAGE:
PREPARED FOR:PLAN DATE:C101" = 20'
STAMP/SIGNATURE:SCALE NOTE:SURVEYED BY: DV, TV, & CBDESIGNER: DUSTIN VREELANDFILE NO.: 25-0579 ENGINEERINGPROJECT:LOCATION:REVISIONSDATEBYDESCRIPTION
SHEETSCALE:DATE: NOVEMBER 24TH, 2025
TITLE PAGE:
PREPARED FOR:PLAN DATE:C111" = 20'
STAMP/SIGNATURE:SCALE NOTE:SURVEYED BY: DV, TV, & CBDESIGNER: DUSTIN VREELANDFILE NO.: 25-0579 ENGINEERINGPROJECT:LOCATION:REVISIONSDATEBYDESCRIPTION
SHEETSCALE:DATE: NOVEMBER 24TH, 2025
TITLE PAGE:
PREPARED FOR:PLAN DATE:C121" = 20'
STAMP/SIGNATURE:SCALE NOTE:SURVEYED BY: DV, TV, & CBDESIGNER: DUSTIN VREELANDFILE NO.: 25-0579 ENGINEERINGPROJECT:LOCATION:REVISIONSDATEBYDESCRIPTION
SHEETSCALE:DATE: NOVEMBER 24TH, 2025
TITLE PAGE:
PREPARED FOR:PLAN DATE:C51" = 20'
EBFOSSSS
SS SSSSFOFO G
G
STAMP/SIGNATURE:SCALE NOTE:SURVEYED BY: DV, TV, & CBDESIGNER: DUSTIN VREELANDFILE NO.: 25-0579 ENGINEERINGPROJECT:LOCATION:REVISIONSDATEBYDESCRIPTION
SHEETSCALE:DATE: NOVEMBER 24TH, 2025
TITLE PAGE:
PREPARED FOR:PLAN DATE:C141" = 50'
STAMP/SIGNATURE:SCALE NOTE:SURVEYED BY: DV, TV, & CBDESIGNER: DUSTIN VREELANDFILE NO.: 25-0579 ENGINEERINGPROJECT:LOCATION:REVISIONSDATEBYDESCRIPTION
SHEETSCALE:DATE: NOVEMBER 24TH, 2025
TITLE PAGE:
PREPARED FOR:PLAN DATE:C151" = 10'
SSFOFO
STAMP/SIGNATURE:SCALE NOTE:SURVEYED BY: DV, TV, & CBDESIGNER: DUSTIN VREELANDFILE NO.: 25-0579 ENGINEERINGPROJECT:LOCATION:REVISIONSDATEBYDESCRIPTION
SHEETSCALE:DATE: NOVEMBER 24TH, 2025
TITLE PAGE:
PREPARED FOR:PLAN DATE:C161" = 20'
STAMP/SIGNATURE:SCALE NOTE:SURVEYED BY: DV, TV, & CBDESIGNER: DUSTIN VREELANDFILE NO.: 25-0579 ENGINEERINGPROJECT:LOCATION:REVISIONSDATEBYDESCRIPTION
SHEETSCALE:DATE: NOVEMBER 24TH, 2025
TITLE PAGE:
PREPARED FOR:PLAN DATE:C171" = 20'
STAMP/SIGNATURE:SCALE NOTE:SURVEYED BY: DV, TV, & CBDESIGNER: DUSTIN VREELANDFILE NO.: 25-0579 ENGINEERINGPROJECT:LOCATION:REVISIONSDATEBYDESCRIPTION
SHEETSCALE:DATE: NOVEMBER 24TH, 2025
TITLE PAGE:
PREPARED FOR:PLAN DATE:C181" = 20'
GSTAMP/SIGNATURE:SCALE NOTE:SURVEYED BY: DV, TV, & CBDESIGNER: DUSTIN VREELANDFILE NO.: 25-0579 ENGINEERINGPROJECT:LOCATION:REVISIONSDATEBYDESCRIPTION
SHEETSCALE:DATE: NOVEMBER 24TH, 2025
TITLE PAGE:
PREPARED FOR:PLAN DATE:C191" = 10'
SSSS FOG STAMP/SIGNATURE:SCALE NOTE:SURVEYED BY: DV, TV, & CBDESIGNER: DUSTIN VREELANDFILE NO.: 25-0579 ENGINEERINGPROJECT:LOCATION:REVISIONSDATEBYDESCRIPTION
SHEETSCALE:DATE: NOVEMBER 24TH, 2025
TITLE PAGE:
PREPARED FOR:PLAN DATE:C201" = 20'
G STAMP/SIGNATURE:SCALE NOTE:SURVEYED BY: DV, TV, & CBDESIGNER: DUSTIN VREELANDFILE NO.: 25-0579 ENGINEERINGPROJECT:LOCATION:REVISIONSDATEBYDESCRIPTION
SHEETSCALE:DATE: NOVEMBER 24TH, 2025
TITLE PAGE:
PREPARED FOR:PLAN DATE:C211" = 20'
EB SSSS
SSSSSS FOFOG
G STAMP/SIGNATURE:SCALE NOTE:SURVEYED BY: DV, TV, & CBDESIGNER: DUSTIN VREELANDFILE NO.: 25-0579 ENGINEERINGPROJECT:LOCATION:REVISIONSDATEBYDESCRIPTION
SHEETSCALE:DATE: NOVEMBER 24TH, 2025
TITLE PAGE:
PREPARED FOR:PLAN DATE:C221" = 50'
EROSION CONTROL SCHEDULING1.INSTALL PERIMETER EROSION CONTROL.2.BEGIN DEMOLITION.3.BEGIN ROUGH GRADING AND UTILITY INSTALLATION.4.GRADE DITCHES AND STORMWATER INFILTRATION BASINS.5.INSTALL BASE, CURB & GUTTER, AND ASPHALT.6.CLEANUP AND FINISH DISTURB SOIL AREAS WITH TOPSOIL, SEED, MULCH,FERTILIZER AND EROSION MAT AS NEEDED.7.DURING GRADING ACTIVITIES EXISTING GRASS AND VEGETATION, TO BEREMOVED, SHALL REMAIN IN PLACE FOR AS LONG AS POSSIBLE, TOAVOID SEDIMENT TRANSPORT.8.ALL DISTURBED AREAS SHALL BE STABILIZED, TEMPORARILY AND/ORPERMANENT, WITHIN 30 DAYS OF DISTURBANCE, OR PERMANENTLY STABILIZED WITHIN 7 DAYS OF ACHIEVING FINISHED GRADE.9.IF DISTURBED AREAS MUST BE LEFT OVER WINTER, AN ANIONICPOLYACRYLAMIDE SHALL BE APPLIED TO ALL DISTURBED AREAS PRIORTO GROUND FREEZE. SEE SPECIFICATIONS FOR DETAILS.
PROPOSED EROSION CONTROL ACTIVITIES1.CONTACT DIGGER'S HOTLINE 5 WORKING DAYS PRIOR TO THE START OFDEMOLTION/CONSTRUCTION.2.NOTIFY THE LOCAL MUNICIPALITY AT LEAST 2 WORKING DAYS PRIOR TO THESTART OF SOIL DISTURBING ACTIVITIES.3.KEEP A COPY OF THE EROSION CONTROL PLANS AND STORMWATER &EROSION CONTROL MANANGEMENT PLAN ON SITE THROUGHOUT THEPROJECT.4.INSTALL ALL TEMPORARY EROSION CONTROL ELEMENTS PRIOR TO THE STARTOF DEMOLITION/CONSTRUCTION.5.ALL ACTIVITIES SHALL BE CONDUCTED IN A LOGICAL SEQUENCE AS TOMINIMIZE THE AMOUNT OF BARE SOIL EXPOSED AT ANY ONE TIME. MAINTAINEXISTING VEGETATION AS LONG AS POSSIBLE.6.CRUSHED ROCK DRIVES FOR SEDIMENT TRACKING UTILIZING 3" CRUSHEDROCK SHALL BE MAINTAINED AT ALL CONSTRUCTION ENTRANCES TO THE SITE.THE ROCK DRIVE SHALL BE A MINIMUM OF 12" THICK AND BE A MINIMUM OF 50FEET IN LENGTH BY THE WIDTH OF THE DRIVEWAY.7.PIPE DITCH CHECK SHALL BE PLACE AT ALL INLET FLOW LOCATIONS OFCULVERTS.8.CONCRETE WASHOUT TO BE PER EPA STANDARDS.9.ALL SLOPES GREATER THAN 5' HORIZONTAL TO 1' VERTICAL SHALL HAVEEROSION MAT INSTALLED.10.OFF SITE SEDIMENT DEPOSITS OCCURRING AS A RESULT OF A STORM EVENTSHALL BE CLEANED UP BY THE END OF THE NEXT WORK DAY. ALL OFF SITESEDIMENT DEPOSITS OCCURRING AS A RESULT OF CONSTRUCTIONACTIVITIES, INCLUDING SOIL TRACKED BY CONSTRUCTION TRAFFIC, SHALL ATA MINIMUM BE CLEANED BY THE END OF EACH WORK DAY. EXCESSIVEAMOUNTS OF SEDIMENT OR OTHER DEBRIS TRACKED ONTO ADJACENTSTREETS SHALL BE CLEANED BY THE END OF EACH WORK DAY. EXCESSIVEAMOUNTS OF SEDIMENT OR OTHER DEBRIS TRACKED ONTO ADJACENTSTREETS SHALL BE CLEANED IMMEDIATELY. FINE SEDIMENT ACCUMULATIONSSHALL BE CLEANED FROM ADJACENT STREETS BY THE USE OF MECHANICALOR MANUAL SWEEPING OPERATIONS ONCE A WEEK AT A MINIMUM ANDBEFORE IMMINENT RAIN EVENTS.11.DISTURBED GROUND OUTSIDE OF THE EVERYDAY CONSTRUCTION AREAS,INCLUDING SOIL STOCKPILES, THAT ARE LEFT INACTIVE FOR MORE THAN 7DAYS SHALL BE TEMPORARILY STABILIZED BY SEEDING/MULCHING OR OTHERAPPROVED METHODS.12.WASTE MATERIAL THAT IS GENERATED ON THE CONSTRUCTION SITE SHALL BEPROPERLY DISPOSED OF AND NOT ALLOWED TO RUN INTO RECEIVINGWATERS. ANY SEDIMENT OR TRASH THAT HAS MOVED OFF-SITE SHALL BESWEPT OR CLEANED UP BEFORE THE END OF THE WORK DAY.13.EROSION CONTROL DEVICES DESTROYED AS A RESULT OF CONSTRUCTIONACTIVITIES SHALL BE REPAIRED BY THE END OF EACH WORK DAY.14.INSPECT ALL EROSION CONTROL MEASURES AT LEAST ONCE A WEEK ANDAFTER ANY RAINFALL OF 0.5" OR MORE. MAKE NEEDED REPAIRS ANDDOCUMENT ALL ACTIVITIES AS PER THE REQUIREMENTS OF THE NOTICE OFINTENT SUBMITTED BY THE PROJECT CIVIL ENGINEER.15.ALL TEMPORARY EROSION CONTROL ELEMENTS SHALL REMAIN IN PLACE UNTILA SUFFICIENT GROWTH OF VEGETATION IS ESTABLISHED AND THEN BEREMOVED AS PART OF THE BASE BID.16.IF SEDIMENT LADEN WATER NEEDS TO BE REMOVED FROM THE SITE, FILTERBAGS OR SCREENING SHALL BE USED IN ACCORDANCE WITH THE WI DNRTECHNICAL STANDARDS 1061 TO PREVENT THE DISCHARGE OF SEDIMENT TOTHE MAXIMUM EXTENT PRACTICABLE.17.IF BARE SOIL IS EXPOSED DURING THE WINTER MONTHS, STABILIZATION BYMULCHING OR ANIONIC POLYACRYLAMIDE SHALL OCCUR PRIOR TO SNOW ORFROZEN GROUND.18.SILT FENCE SHALL BE INSTALLED AROUND THE TOPSOIL STOCKPILE.19.THE CONTRACTOR SHALL ONLY USE PHOSPHORUS FREE FERTILIZER FOR ALLLANDSCAPE APPLICATIONS.20.THE CONTRACTOR SHALL BE RESPONSIBLE FOR WATERING PLANTEDDISTURBED AREAS WHENEVER MORE THAN 7 DAYS OF DRY WEATHER OCCUR.21.THE CONTRACTOR SHALL PERFORM INSPECTIONS AND MONITORING OFEROSION CONTROL PRACTICES IN ACCORDANCE WITH THE WI DNR"CONSTRUCTION SITE INSPECTION REPORT" FORM 3400-187. THIS FORM CANBE FOUND ON WISCONSIN DNR WEBSITE OR PROVIDE IF NECESSARY.
STAMP/SIGNATURE:SCALE NOTE:SURVEYED BY: DV, TV, & CBDESIGNER: DUSTIN VREELANDFILE NO.: 25-0579 ENGINEERINGPROJECT:LOCATION:REVISIONSDATEBYDESCRIPTION
SHEETSCALE:DATE: NOVEMBER 24TH, 2025
TITLE PAGE:
PREPARED FOR:PLAN DATE:C23NO SCALE
STAMP/SIGNATURE:SCALE NOTE:SURVEYED BY: DV, TV, & CBDESIGNER: DUSTIN VREELANDFILE NO.: 25-0579 ENGINEERINGPROJECT:LOCATION:REVISIONSDATEBYDESCRIPTION
SHEETSCALE:DATE: NOVEMBER 24TH, 2025
TITLE PAGE:
PREPARED FOR:PLAN DATE:C24NO SCALE
STAMP/SIGNATURE:SCALE NOTE:SURVEYED BY: DV, TV, & CBDESIGNER: DUSTIN VREELANDFILE NO.: 25-0579 ENGINEERINGPROJECT:LOCATION:REVISIONSDATEBYDESCRIPTION
SHEETSCALE:DATE: NOVEMBER 24TH, 2025
TITLE PAGE:
PREPARED FOR:PLAN DATE:C25NO SCALE
STAMP/SIGNATURE:SCALE NOTE:SURVEYED BY: DV, TV, & CBDESIGNER: DUSTIN VREELANDFILE NO.: 25-0579 ENGINEERINGPROJECT:LOCATION:REVISIONSDATEBYDESCRIPTION
SHEETSCALE:DATE: NOVEMBER 24TH, 2025
TITLE PAGE:
PREPARED FOR:PLAN DATE:C26NO SCALE
STAMP/SIGNATURE:SCALE NOTE:SURVEYED BY: DV, TV, & CBDESIGNER: DUSTIN VREELANDFILE NO.: 25-0579 ENGINEERINGPROJECT:LOCATION:REVISIONSDATEBYDESCRIPTION
SHEETSCALE:DATE: NOVEMBER 24TH, 2025
TITLE PAGE:
PREPARED FOR:PLAN DATE:C27NO SCALE
STAMP/SIGNATURE:SCALE NOTE:SURVEYED BY: DV, TV, & CBDESIGNER: DUSTIN VREELANDFILE NO.: 25-0579 ENGINEERINGPROJECT:LOCATION:REVISIONSDATEBYDESCRIPTION
SHEETSCALE:DATE: NOVEMBER 24TH, 2025
TITLE PAGE:
PREPARED FOR:PLAN DATE:C28NO SCALE
STAMP/SIGNATURE:SCALE NOTE:SURVEYED BY: DV, TV, & CBDESIGNER: DUSTIN VREELANDFILE NO.: 25-0579 ENGINEERINGPROJECT:LOCATION:REVISIONSDATEBYDESCRIPTION
SHEETSCALE:DATE: NOVEMBER 24TH, 2025
TITLE PAGE:
PREPARED FOR:PLAN DATE:C29NO SCALE
STAMP/SIGNATURE:SCALE NOTE:SURVEYED BY: DV, TV, & CBDESIGNER: DUSTIN VREELANDFILE NO.: 25-0579 ENGINEERINGPROJECT:LOCATION:REVISIONSDATEBYDESCRIPTION
SHEETSCALE:DATE: NOVEMBER 24TH, 2025
TITLE PAGE:
PREPARED FOR:PLAN DATE:C30NO SCALE
STAMP/SIGNATURE:SCALE NOTE:SURVEYED BY: DV, TV, & CBDESIGNER: DUSTIN VREELANDFILE NO.: 25-0579 ENGINEERINGPROJECT:LOCATION:REVISIONSDATEBYDESCRIPTION
SHEETSCALE:DATE: NOVEMBER 24TH, 2025
TITLE PAGE:
PREPARED FOR:PLAN DATE:C31NO SCALE
STAMP/SIGNATURE:SCALE NOTE:SURVEYED BY: DV, TV, & CBDESIGNER: DUSTIN VREELANDFILE NO.: 25-0579 ENGINEERINGPROJECT:LOCATION:REVISIONSDATEBYDESCRIPTION
SHEETSCALE:DATE: NOVEMBER 24TH, 2025
TITLE PAGE:
PREPARED FOR:PLAN DATE:C30NO SCALE
Plover Water System, 300 Waters Way, P.O. Box 37, Plover, WI 54467 345-5250, 345-5248
Emergency Water Agreements Memo- 2026_0216 Page 1 of 1 Printed: 2/13/2026 7:15:00 AM
Agenda Items:
Discussion/Action: Updating Emergency Water Agreement with the Village of Whiting
Plover and Whiting have an existing agreement to furnish water under emergency circumstances
through two available connection points. The current agreement is renewable under 5-year
increments. The proposed new agreement would delete 5-year renewal cycles. Restated to:
10. This Agreement is active from the date that both parties sign the document until a party decides
to terminate said Agreement. Either party may terminate the Agreement by notifying the other
party, in writing, with at least six (6) months advance notice of the party’s intent to terminate.
Upon termination of this Agreement, neither party shall have any obligation to provide
emergency service to the other. Recommendation: Approve Emergency Water Agreement
as stated upon pending legal review
Discussion/Action: Updating Emergency Water Agreement with the City of Stevens Point
Plover and Stevens Point have an existing agreement to furnish water under emergency
circumstances through an existing connection point. The current agreement is renewable under
5-year increments. The proposed new agreement would delete 5-year renewal cycles. Restated
to:
10. This Agreement is active from the date that both parties sign the document until a party decides
to terminate said Agreement. Either party may terminate the Agreement by notifying the other
party, in writing, with at least six (6) months advance notice of the party’s intent to terminate.
Upon termination of this Agreement, neither party shall have any obligation to provide
emergency service to the other. Recommendation: Approve Emergency Water Agreement
as stated upon pending legal review.
Water System Memo
To: Utility Committee, President Wolf, Steve Kunst
From: Matt Saloun, Water System Manager
Date: 02/16/2026
Subject: Emergency Water Agreements
RECIPROCAL EMERGENCY WATER SERVICE AGREEMENT BETWEEN THE CITY OF
STEVENS POINT AND THE VILLAGE OF PLOVER
February XX, 2026
THIS AGREEMENT made and entered into this XXth day of February, 2026, and executed by and
between the City of Stevens Point, hereafter referred to as “City” and the Village of Plover, hereinafter
referred to as “Village”, both municipal corporations of the County of Portage, State of Wisconsin.
WHEREAS, the City and Village are agreeable to providing emergency water service to each other under
certain expressed conditions described herein,
NOW, THEREFORE, IT IS MUTUALLY AGREED by and between the City and Village as follows:
1. The City agrees to provide emergency water service to the Village, and the Village agrees to
provide emergency water service to the City, if and when the following conditions occur:
a. An emergency occurs of such nature and duration as to justify a request by either the
City or Village to have water furnished by the other party; and
b. The party that is requested to provide emergency water service makes its own
determination that an emergency actually exists; and
c. The party that is requested to provide emergency water service determines it has
sufficient excess capacity to provide the service at the time it is requested; and
d. Emergency water service can be provided through mutually agreed on metered
connections which are properly equipped to facilitate the emergency water service
without any adverse impacts to the party providing emergency service or its customers.
2. An “emergency” is defined as a sudden occurrence or rupture which results from equipment
failure or a major transmission water main failure, and the consequential decrease of water
available to supply the permanent customers of the party experiencing the emergency. An
“emergency” may include insufficient water available under a situation that results from plant
maintenance, inadequate storage facilities, insufficient plant capacity or water quality, or some
other long-term occurrence of a similar kind.
3. The party requesting and receiving emergency water service agrees to pay the party providing
emergency service the commodity charge as set forth in the current rate order issued by the
Public Service Commission of Wisconsin for the party providing service. Both the City and
Village agree to request that a standby service charge not be imposed by the Public Service
Commission of Wisconsin.
4. The party that provided emergency service shall submit an invoice to the party that received
such service, and the party that received emergency service shall pay the invoice within thirty
(30) days from the date the invoice is submitted. If the party that received service fails to pay
such invoice within thirty (30) days after submission, this Agreement may be terminated at the
supplier’s discretion and the party that received service shall be liable for all accrued
indebtedness and damages resulting from such breach.
5. The City and Village shall consult and mutually decide whether any mains or other facilities must
be installed to accommodate the provision of emergency service under this agreement. Prior to
installing any mains or other facilities, the parties shall mutually agree on how the costs of such
mains or facilities shall be allocated among the parties.
6. The required water meter maintenance shall be performed according to Wisconsin
Administrative Code Public Service Commission Chapter 185 and costs associated with such will
be paid for jointly by the City and Village. Any future facility maintenance required to the mains,
valves, or other facilities will be paid for by the party owning the facilities with the meter and
meter manhole being a shared maintenance cost.
7. The party receiving emergency water service shall only serve permanent customers within their
normal service boundary.
8. The party providing emergency water supply shall provide water of such quality and pressure
that normally exists in its distribution system at the point of interconnection between the City
and Village. The party receiving emergency water service shall be responsible for maintaining
the water quality and pressure after it is received beyond the point of interconnection.
9. A party providing emergency water service to the other may discontinue such service only after
the party providing service gives the other 24 hours notice of the discontinuation. Service may
be discontinued for any reason.
10. This Agreement is active from the date that both parties sign the document until a party decides
to terminate said Agreement. Either party may terminate the Agreement by notifying the other
party, in writing, with at least six (6) months advance notice of the party’s intent to terminate.
Upon termination of this Agreement, neither party shall have any obligation to provide
emergency service to the other.
11. Neither the City or Village shall be held responsible for any damages relating to furnishing or not
furnishing emergency water service under this Agreement. A party that is requested to provide
water under this Agreement shall be saved and held harmless by the party requesting service
from all claims of damage of any kind which may arise as a result of making this Agreement and
furnishing or not furnishing water hereunder.
12. Neither this Agreement, nor any rights there under, shall be assigned or transferred by the City
or Village to another.
13. In the event that a court of competent jurisdiction or governmental agency with like authority
declares any portion of this Agreement unconstitutional, invalid or otherwise unlawful, then the
entire Agreement shall be deemed terminated.
IN WITNESS WHEREOF, the parties have executed this Agreement pursuant to resolutions adopted by
their respective governing bodies,
CITY OF STEVENS POINT Signed in presence of:
By: By: ____
Public Utilities Director
By: ______________________________ By:__________________________________
Administrative Services Manager
VILLAGE OF PLOVER Signed in presence of:
By: By: ____
Village President
By: ______________________________ By:__________________________________
Village Clerk
RECIPROCAL EMERGENCY WATER SERVICE AGREEMENT BETWEEN THE VILLAGE
OF PLOVER AND THE VILLAGE OF WHITING
February XX, 2026
THIS AGREEMENT made and entered into this XXth day of February, 2026, and executed by and
between the Village of Plover, hereafter referred to as “Plover” and the Village of Whiting, hereinafter
referred to as “Whiting”, both municipal corporations of the County of Portage, State of Wisconsin.
WHEREAS, Plover and Whiting are agreeable to providing emergency water service to each other under
certain expressed conditions described herein,
NOW, THEREFORE, IT IS MUTUALLY AGREED by and between Plover and Whiting as follows:
1. Plover agrees to provide emergency water service to Whiting and Whiting agrees to provide
emergency water service to Plover, if and when the following conditions occur:
a. An emergency occurs of such nature and duration as to justify a request by either Plover
or Whiting to have water furnished by the other party; and
b. The party that is requested to provide emergency water service makes its own
determination that an emergency actually exists; and
c. The party that is requested to provide emergency water service determines it has
sufficient excess capacity to provide the service at the time it is requested; and
d. Emergency water service can be provided through mutually agreed on metered
connections which are properly equipped to facilitate the emergency water service
without any adverse impacts to the party providing emergency service or its customers.
2. An “emergency” is defined as a sudden occurrence or rupture which results from equipment
failure or a major transmission water main failure, and the consequential decrease of water
available to supply the permanent customers of the party experiencing the emergency. An
“emergency” may include insufficient water available under a situation that results from plant
maintenance, inadequate storage facilities, insufficient plant capacity or water quality, or some
other long-term occurrence of a similar kind.
3. The party requesting and receiving emergency water service agrees to pay the party providing
emergency service the commodity charge as set forth in the current rate order issued by the
Public Service Commission of Wisconsin for the party providing service. Both Plover and
Whiting agree to request that a standby service charge not be imposed by the Public Service
Commission of Wisconsin.
4. The party that provided emergency service shall submit an invoice to the party that received
such service, and the party that received emergency service shall pay the invoice within thirty
(30) days from the date the invoice is submitted. If the party that received service fails to pay
such invoice within thirty (30) days after submission, this Agreement may be terminated at the
supplier’s discretion and the party that received service shall be liable for all accrued
indebtedness and damages resulting from such breach.
5. Plover and Whiting shall consult and mutually decide whether any mains or other facilities must
be installed to accommodate the provision of emergency service under this agreement. Prior to
installing any mains or other facilities, the parties shall mutually agree on how the costs of such
mains or facilities shall be allocated among the parties.
6. The required water meter maintenance shall be performed according to Wisconsin
Administrative Code Public Service Commission Chapter 185 and costs associated with such will
be paid for jointly by Plover and Whiting. Any future facility maintenance required to the mains,
valves, or other facilities will be paid for by the party owning the facilities with the meter and
meter manhole being a shared maintenance cost.
7. The party receiving emergency water service shall only serve permanent customers within their
normal service boundary.
8. The party providing emergency water supply shall provide water of such quality and pressure
that normally exists in its distribution system at the point of interconnection between Plover
and Whiting. The party receiving emergency water service shall be responsible for maintaining
the water quality and pressure after it is received beyond the point of interconnection.
9. A party providing emergency water service to the other may discontinue such service only after
the party providing service gives the other 24 hours notice of the discontinuation. Service may
be discontinued for any reason.
10. This Agreement is active from the date that both parties sign the document until a party decides
to terminate said Agreement. Either party may terminate the Agreement by notifying the other
party, in writing, with at least six (6) months advance notice of the party’s intent to terminate.
Upon termination of this Agreement, neither party shall have any obligation to provide
emergency service to the other.
11. Neither Plover or Whiting shall be held responsible for any damages relating to furnishing or not
furnishing emergency water service under this Agreement. A party that is requested to provide
water under this Agreement shall be saved and held harmless by the party requesting service
from all claims or damage of any kind, nature and description which may arise as a result of
making this Agreement and furnishing or not furnishing water hereunder.
12. Neither this Agreement, nor any rights there under, shall be assigned or transferred by Plover or
Whiting to another.
13. In the event that a court of competent jurisdiction or governmental agency with like authority
declares any portion of this Agreement unconstitutional, invalid or otherwise unlawful, then the
entire Agreement shall be deemed terminated.
IN WITNESS WHEREOF, the parties have executed this Agreement pursuant to resolutions adopted by
their respective governing bodies,
VILLAGE OF WHITING Signed in presence of:
By: By: ____
Village President
By: ______________________________ By:__________________________________
Village Clerk
VILLAGE OF PLOVER Signed in presence of:
By: By: ____
Village President
By: ______________________________ By:__________________________________
Village Clerk
Plover Water System, 300 Waters Way, P.O. Box 37, Plover, WI 54467 345-5250, 345-5248
Well 1 Generator Bid Memo- 2026_0216 Page 1 of 1 Printed: 2/13/2026 7:03:00 AM
Agenda Item:
Discussion/Action: Approval of Well 1 Generator Project Bid
The purpose of this project is to provide backup power to Well 1. The generator
will be enclosed as part of the wellhouse building addition and automatically
become source 2 in the event of a mainline power outage. CBS Squared prepared
plans and the advertised bid package documents. Bid openings occurred February
12th.
Recommendation: To approve qualified low bid contract upon pending
engineer completed review of the Contractor’s submitted bid documents.
Water System Memo
To: Utility Committee, President Wolf, Steve Kunst
From: Matt Saloun, Water System Manager
Date: 02/16/2026
Subject: Well 1 Generator Project Bid
Date: February 12, 2026
RE: Well #1 Generator Building
Plover, WI
CBS² PLOVV 25001
Ms. Tammy Wojalewicz/Mr. Gary Wolf/ Mr. Steve Kunst
Village Clerk/Village President/Village Administrator
Village of Plover
2400 Post Road
PO Box 37
Plover, WI 54467
Dear Tammy/Gary/Steve,
Bids for the Village of Plover Well #1 Generator Building project were received at 2:00 p.m. on
February 12, 2026 . Two bids were received and accepted for the project and are summarized
below:
Base Bid
Eagle Construction Co., Inc $336,990.00
Altmann Construction Company, Inc. $377,500.00
The itemized bid tabulation is attached.
Based on our review, it is our opinion that Eagle Construction Co., Inc. of Wisconsin Rapids has the
equipment and experience to perform the work as defined in the bidding documents. If the Village
of Plover decides to proceed with the project as bid, we therefore recommend award of the project
in the amount of $336,990.00 to Eagle Construction Co., Inc.
Should you have any questions, please contact me by phone at (715) 829-7979, or by e-mail at
jstrand@cbssquaredinc.com.
Sincerely,
Jon Strand
Project Manager
Enclosure
Plover Water System, 300 Waters Way, P.O. Box 37, Plover, WI 54467 345-5254, 345-5248
Utility Report 2026_0216 Page 1 of 3 Last printed 2/13/2026 6:48:00 AM
Water System Report
To: Utility Committee, Gary Wolf, Steve Kunst
From: Matt Saloun, Water System Manager
Date: 02/16/2026
Agenda items:
Discussion/Action:
o Utility Plans- Green Tree Farm Subdivision- Green Tree Construction Inc-
Pleasant Drive/CTH R
o Updating Emergency Water Agreement with Village of Whiting
o Updating Emergency Water Agreement with City of Stevens Point
o Approval of Well 1 Generator Project Bid
Project Updates:
• Lincoln water tower- AT&T updating equipment/ replacing antennas (01/27-2/12/2026)
• Well 1 Generator Project- Finalized Request for Proposals, Advertised Bid Proposals,
Pre-Bid Site visit, Bid Opening.
• Disk Tower- Nsight lease updated. Working to schedule equipment re-install.
Report:
• 22 Plover Pointe Manor- Frozen service under trailer (01/19/26)
• Completed First Aid/ CPR refresher course. (01/20/26)
• 2431 Sunrise Court- No water. Frozen water line in the wall. (01/23/26)
• 47 Plover Pointe Village- Burst pipe under trailer. (01/25/26)
• 2 Plover Pointe Village- Frozen line under trailer. (01/27/26)
• 138 Plover Pointe Village- Frozen line under trailer. (1/28/26)
• 1782-1794 Plover Road- Burst pipe/ building flooding. (01/28/26)
• 177 Plover Pointe Village- Frozen service under trailer (01/31/26)
• 630 Gloria Drive- No water. Frozen line identified on outside wall. (02/02/26)
• Hydrant hit on north end of Torrey Pines. (02/04/26)
• Staff- Updating breakroom, painting well 3 pump discharge piping, meter testing, meter
replacements, cross connection inspections.
Water System Report
Plover Water System, 300 Waters Way, P.O. Box 37, Plover, WI 54467 345-5254, 345-5248
Utility Report 2026_0216 Page 2 of 3 printed 2/13/2026 6:48 AM
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Year Summary
2026 Well 1 21,796 21,796 48.25% Tot
2026 Well 2 11,514 11,514 25.49% Tot
2026 Well 3 11,866 11,866 26.27% Tot
2026 Tot 45,176 0 0 0 0 0 0 0 0 0 0 0 45,176 Tot
2026 Avg 1,479 1,563 Avg
2026 Max 1,561 Max
10-Jan
2026 Min 1,115 Min
1-Jan
2025 Tot 46,970 44,609 48,350 47,054 60,722 65,348 73,369 70,588 52,465 46,505 39,171 41,570 636,721 Tot
2025 Max 1,783 1,765 1,820 1,802 2,326 2,773 2,884 3,043 2,290 1,909 1,548 1,534 3,043 Max
2025 Avg 1,515 1,593 1,559 1,560 1,958 2,189 2,298 2,277 1,748 1,500 1,305 1,340 1,737 Avg
2024 Tot 44,171 42,507 43,714 45,534 53,251 54,487 60,771 62,981 58,480 50,214 40,892 42,754 599,756 Tot
2024 Max 1,633 1,570 1,854 1,755 2,159 2,292 2,372 2,259 2,329 1,946 1,688 1,582 2,372 Max
2024 Avg 1,424 1,429 1,410 1,517 1,717 1,786 1,960 2,031 1,949 1,619 1,363 1,379 1,632 Avg
Pumping Report
Date of Minimum
Date of Maximum
Nitrate Report - 2026
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Well 1 Raw 11.3
Well 2 Raw 11.5
Well 3 Raw 14.6
Well 1&2 Dist 6.9
Well 3 Dist 7.3
Nitrate Report - 2025
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Well 1 Raw 12.0 11.4 11.3 11.5 11.6 11.6 11.7 11.7 11.6 11.4 11.3 11.3
Well 2 Raw 11.6 11.2 11.7 11.9 12.0 11.9 11.8 11.9 11.8 11.8 11.7 11.6
Well 3 Raw 14.8 14.3 14.3 14.1 13.9 13.8 13.8 13.9 14.0 13.5 14.4 14.5
Well 1&2 Dist 6.7 6.7 6.7 6.8 7.0 6.9 6.9 6.9 7.0 6.8 6.7 6.8
Well 3 Dist 7.5 7.4 7.3 7.3 7.1 7.1 7.1 7.2 7.4 7.0 7.3 7.2
Water System Report
Plover Water System, 300 Waters Way, P.O. Box 37, Plover, WI 54467 345-5254, 345-5248
Utility Report 2026_0216 Page 3 of 3 printed 2/13/2026 6:48 AM
Wastewater System Memo
To: Steve Kunst, Gary Wolf, Utility Committee, Village Board
From: Lyle Lutz
Date: February 16, 2026
Subject: Wastewater Utility Report
_____________________________________________________________________
1. A Request for Proposals is out for River Dr. Lift Station Engineering services. The RFP
was sent to several respectable engineering firms for their consideration. Proposals are
tentatively to be received by February 20th for following review.
2. Donohue has provided draft final reports for both the Facility Design review and
Collection system Master plans. StaƯ are reviewing for final comments and edits to
generate the final reports to be presented at the March Utility committee/Board
meetings.
3. The screw press underwent regular scheduled maintenance in replacing some screen
panels and screw wiper. This maintenance is expected to improve the sludge
dewatering performance. StaƯ made quick turnaround on the work with the machine
only being down for a couple days to complete the work.
4. Logan has been working with a UWSP student and their interest in evaluating the
potential of composting our Biosolids with compost site yard waste. They are looking to
understand feasibility of the process along with review of other facilities that currently
compost biosolids. While this likely is not a immediate potential process for the Village,
it may provide insights as to if it would be worth exploring the potentials of the Village
Wastewater Utility and the Village operated yard waste collected materials.
5. As the weather gets warmer, staƯ will begin annual collection system cleaning and
inspections as time allows. They will also proceed with annual lift station maintenance.
6. Ingredion is doing a trial on some new scrubber equipment that uses and discharges up
to an additional 10,000 gals/day. The additional discharges are not anticipated to
contain any additional loadings and if they do go with the upgrades there are ways they
would reduce that additional consumption to normal historical usage. A temporary
increase in maximum daily and monthly allowances was discussed to allow for the trial
period increased usage and discharge. No long-term adjustments were deemed
necessary to the current discharge agreement at this time.
7. The facility received 3,500 gallons of septage, 59,500 gallons of holding tank, and
510,387 gallons of leachate in January. All processes have been exceptionally stable
and minimal impacts from the cold snaps were noticed. There were a couple electronic
glitches on some of the outside process meters that measure Dissolved Oxygen. The
meters shut down during extremely cold days. The outages were short lived, and
operations were appropriate for the periods.
Parameter
Units
Flow
MGD
CBOD
mg/l
Suspended
solids
mg/l
Phosphorus
mg/l
Ammonia
mg/l
Design / Limit 1.8000 25 30 0.67 Daily
Variable
January Average 1.5981 2.4 4.9 .14 .24
Source: Village of Plover website. First collected Oct 18, 2026.