Special Meeting of the Town of Lincoln Board of Supervisors (BoS)
Town of Lincoln, Kewaunee County
Thursday, November 13, 2025 following the 7:00 PM 2026 Budget Meeting
Lincoln Town Hall, N8016 Maple Rd, Casco, WI
Chairman Jesse Jerabek called the meeting to order at 7:31 P .M. Also present were Supervisors Dave
Routhieaux and Tony Strnad, Plan Commission Chairman Mick Sagrillo, Zoning Administrator Joe Jerabek,
Town Treasurer, Tim Strnad. Minutes taken by Town Clerk, Mary Ann Salmon.
Zoning Administrator, Joe Jerabek received plans from Sedron for routing a 6” and 12” pipeline from
Kinnard Farms to Casco Creek. A map & plans were received showing the route of proposed discharge
piping from KFI to the creek, boring under Spruce Road, trenching pipe along the east side to Cty Rd S,
where the trench will run along the north side of Cty S. The pipes will then be bored under Cty Rd S to Oak
Rd, where they will be installed via trench along the east side of the road. This project at Kinnard Farms
will be impacting the Right of Way (ROW) for Spruce Road, County Road S, and Oak Road. KFI is installing
a facility that will process digested manure produced by the farm. The plan is to route a 6-inch HDPE
pipeline along Spruce, Oak, and Cty Rd S to discharge a clean water product into Casco Creek, north of
Pheasant Rd between Maple & Oak Rd. Two additional pipes- a 6” & a 12” will be placed in the same
trench beginning mid-way along Cty Rd S & ending in the ROW of Oak Road. These two additional pipes
will transfer rainwater collected & stored from Kinnard feed pads to fields where the water can be
recycled during the growing season using an applicator system called Rain 360.
Mick Sagrillo reviewed detailed drawings submitted for the original 4.24.2023 CUP . At the regular BoS
meeting on 11.06.2025, the Board discussed whether plans fulfil Sedron’s requirements for a 6” pipe as
laid out in the original CUP. Motion made to approve only the 6” pipe to be buried for Sedron (Routhieaux
/Strnad). Motion carried 3-0. No further action is required on the part of Sedron as long as 6” pipes are
used only for Sedron and no further Plan Commission meetings are required. Joe Jerabek can issue the
required building permit upon receipt of payment for the building permit.
KFI will need to have a CUP Hearing to bury the additional 6” & 12” pipe for Rain360 from the north side of
County Rd S right of way of Section 20 to Oak Rd, then bored south under County S along the west right of
way of Oak Road and bore under Oak Road to east side right of way.
Motion to adjourn at 8:42p.m. (Strnad/ Routhieaux). Motion carried (3-0).
Town Clerk, Mary Ann Salmon
(920) 366-3640