Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
CITY OF PRESCOTT
PARKS & PUBLIC WORKS COMMITTEE
MONDAY, OCTOBER 19, 2026
5:00 PM
MUNICIPAL BUILDING
800 BORNER ST
PRESCOTT, WI 54021
1) Call to Order
2) Roll Call
3) Approve Minutes for September 21, 2026
4) Consideration to Purchase and Install Snowplow Equipment on Public Works Truck
5) Discussion on Spraying Riverfront with Herbicide AquaNeat
6) Fairy Wonderland Project Grant Contract and Cedar Corporation Engineering Services
Contract
7) Review of Parks Improvement Fund and Capital Improvement Items
8) Other Business
a) Update on Trail Connection from Magee Park to Walnut Circle
9) Adjourn
NOTICE
ACCESS TO THE MUNICIPAL BUILDING FOR THE DISABLED IS AVAILABLE AT
THE MAIN ENTRANCE. ALL THOSE WITH SPECIAL NEEDS SHOULD CALL CITY
HALL OFFICES (715-262-5544) IF ASSISTANCE IS REQUIRED
IT IS POSSIBLE THAT A QUORUM OF THE COMMON COUNCIL OR OTHER CITY
COMMITTEES MAY BE PRESENT AT THIS MEETING. THIS IS INCIDENTAL AND
NO ACTION WILL BE TAKEN BY THE COUNCIL OR ANY OTHER COMMITTEES.
Parks and Public Works Committee Meeting Minutes
September 21st, 2026
Pursuant to due call and notice thereof, a meeting of the Parks and Public Works
Committee was held September 21st, 2026, Municipal Building, 800 Borner Street,
Prescott, Wisconsin, 54021. The meeting was called to order at 5:01 PM.
Committee Present: Ben Bettis, Dar Hintz, Lindsey Sorenson
Committee Absent: None
Staff Present: City Administrator Matt Wolf, City Planner Luke Wiese
Others Present: Mayor Mike Gerke, Greg Adams of Cedar Corporation
1. Approve Minutes for July 20th, 2026
Hintz motioned to approve the minutes for July 20th. Bettis seconded; motion passed
without a negative voice (3-0).
2. Discussion on Riverfront Improvements Dock Planning
City Administrator Wolf provided an update on the potential riverfront transient dock. The
City was awarded a $53,395 Boating Infrastructure Grant for the Phase 2 riverfront
improvements. The grant is intended for transient recreational vessels 26 feet or longer.
Greg Adams of Cedar Corporation presented the riverfront transient dock proposal. The
dock incorporates multiple slip sizes and angled slips.
Committee member Bettis expressed concerns with the current design. He noted that the
angled slips are oriented opposite the direction of the river flow, which may make it difficult
to park. Bettis also raised concerns about ice and said the dock should be designed with
that in mind.
Bettis asked if some of the slips could be seasonal. Wolf explained that the grant may not
allow seasonal slips, but staff would confirm. Wolf stated that if the grant does not allow
seasonal slips, it may be better for the City to forego the grant if seasonal slips are
preferred.
The Committee supported incorporating electrical service, public Wi-Fi, potable water
service, dock lighting, security cameras, and slip numbering into the design. Committee
member Sorenson suggested that staff coordinate with the Fire Chief regarding safety
equipment and emergency access features.
3. Well 4 Park Concept Plan
City Planner Luke Wiese presented the Well 4 Park Concept Plan. The concept plan would
replace the existing Prescott Skate Park.
The plan incorporates climbing as a central play element while also adding a trail
connection from Borner Street to Dexter Street. A picnic pavilion, playground equipment,
and possible relocation of equipment from Shane Park Circle are also included in the plan.
The Committee generally supported the concept plan, including climbing as the central
recreational element, and preferred the name The Bluffs Park. Staff will continue refining
the concept and return with a final design at a future meeting.
4. 526-11 Dead or Diseased Tree Removal on Private Property
City Administrator Wolf gave an overview of City Code § 526-11. The ordinance allows the
City to require removal of dead or diseased trees on private property when the trees
constitute a hazard to life and property or harbor insects or disease that pose a potential
threat to other trees within the City. Property owners are notified in writing and have 60
days after service of the notice to remove the tree at their own expense. If the property
owner does not comply, the City may remove the tree and charge the cost of removal on
the owner's property tax notice. Wolf explained that the City has typically addressed these
issues after receiving a complaint and asked whether the Committee would like staff to
take a more proactive approach.
The Committee preferred to first get an idea of how many trees and properties this would
apply to. They also stated that enforcement should focus on trees that present an
immediate threat and directed staff to create a set of parameters.
Greg Adams of Cedar Corporation said there is a Wisconsin DNR grant opportunity that
may help offset the cost of tree removal.
5. Firewood Shed at Magee Park
City Administrator Wolf presented the request from Coulee River Trails to place a small
firewood shed at Magee Park for use by park visitors. The shed would be constructed
through the Prescott High School woods/technical education program and would measure
approximately 8 feet wide by 6 feet deep. The final location and placement of the shed
would be coordinated with City staff.
Hintz motioned to recommend the fire shed at Magee Park to Council for approval.
Bettis seconded; motion passed without a negative voice (3-0).
6. Other Business
City Administrator Wolf provided an update on the Armstrong Bench. After looking at the
non-motorized boat launch, the Armstrong family preferred to have the bench moved to
another location within Mercord Mill Park.
The Committee said the bench could be moved when Public Works has time.
Committee member Hintz commented on potholes on Campbell Street and Henry Street.
Hintz also raised a lighting concern for the area and said it should be accounted for if the
City pursues a trail system along Campbell Street.
Commissioner Hintz motioned to adjourn. Bettis seconded; motion passed without a
negative voice (3-0). The meeting was adjourned at 6:24 PM.
The next Parks & Public Works Committee will be October 19, 2026, at 5:00 PM.
Respectfully Submitted,
Luke Wiese, Planner
To: Parks and Public Works Committee
From: Matt Wolf, City Administrator
Date: October 15, 2026
Subject: Purchase and Install Snowplow Equipment on Public Works Truck
Background
The City of Prescott Public Works
Department currently utilizes a
2017 Chevrolet flatbed
truck for snowplowing alleys and
parking lots in the City. Over the
years, this vehicle has experienced
considerable wear and tear from
regular use, particularly during
winter plowing. The truck also has
relatively low ground clearance,
which is a concern during snow
removal operations. This creates
challenges when navigating
deeper snow, snowbanks, and
uneven road surfaces.
To address these concerns, the
Public Works Department is
proposing to transition from the
2017 flatbed truck to the City's 2024
Chevrolet Silverado three-quarter-
ton pickup truck. This vehicle is
better suited for the Department's
plowing and would allow Public
Works to utilize a newer piece of
equipment for winter maintenance.
Figure 1 2017 Flat Bed Truck Used for Plowing Alleys and Parking Lots
Figure 2 Proposed 2024 3/4 Ton Truck for Snowplowing
Discussion
The Public Works Department is requesting authorization to purchase and install a new
9'6" SnowDogg V-Wing snowplow on the 2024 Chevrolet Silverado. The proposed
installation would also include the necessary mounting equipment, lighting system,
controls, and other accessories.
City staff contacted three vendors to obtain pricing for the proposed snowplow
installation:
1. Ellsworth Ford – Quote requested; no response received.
2. Gerlach's – Quote requested; no response received.
3. Kinni Sport & Power - Quote received.
Kinni Sport & Power was the only vendor to provide a quotation. Their September 2026,
proposal includes the snowplow, mounting hardware, controls, lighting, shipping, and
installation labor for a total of $13,187.92.
Financial Considerations
The proposed snowplow purchase and installation were not included in the City's
adopted 2026 Public Works budget.
However, the City is currently anticipating higher-than-budgeted interest revenue
($187,000 currently vs. $100,000 budgeted) during 2026 due to interest rates remaining
elevated. It is proposed that the $13,187.92 purchase be paid from the City's existing
2026 Public Works budget, with the necessary budget amendment completed at the
end of the fiscal year. The amendment would recognize the additional interest revenue
and adjust the appropriate Public Works expenditure appropriation to account for the
purchase.
This approach would allow the Department to place the new plow into snowplowing
service for the upcoming winter season while accounting for the unbudgeted
expenditure with a year-end budget amendment process.
Recommendation
Consider approval moving the quote from Kinni Sport & Power to Council for
consideration of installation of snowplow, mounting hardware, controls, lighting,
shipping, and installation labor for a total of $13,187.92.
Attachment
1. Kinni Sport & Power Quote
1
CP:SamO
Q U O T A T I O N
DATE:
CUSTOMER #:
P.O.#:
100118
TERMS:Net 10th EOM
9/30/2026Kinni Sport & Power LLC
151 State Road 35
River Falls, WI 54022
Phone #: (715)307-4685
Fax #: (715)629-7042
PHONE #:
ALT. #:
(651)269-8437
LOCATION:1
STATUS:Quote1
PAGE:
ORDER #:23704
SALES TYPE:Quote
(651)269-8437CELL #:
City Of Prescott
800 Borner St
RIVER FALLS, WI 54022 US
City Of Prescott
800 Borner St
RIVER FALLS, WI 54022 US
100118BILL TO SHIP TO
MFR PRODUCT NUMBERDESCRIPTION QTY PRICE NET TOTAL
SNWY99101409 $5,847.52 $5,847.52 $5,847.52 129 V-WING SERIES 2 POWER PAK
SNWY99101427 $3,752.00 $3,752.00 $3,752.00 19'6" 29VHD V-WING SERIES 2 FLARED WING
BLADE
SNWY99101397 $605.26 $425.60 $425.60 1PRO CONTROL 2 PLUS - WIRED
SNWY99101364 $511.84 $511.84 $511.84 12020 CHEVY SILVERADO MOUNT KIT
SNWY99100892 $454.72 $454.72 $454.72 1CENTER MEMBER
SNWY99101399 $394.24 $394.24 $394.24 1ESS SMART LIGHTING SYSTEM
SNWY99101441 $402.00 $402.00 $402.00 19'6" EZ FIT DEFLECTOR KIT
**** SHP $400.00 $400.00 $400.00 1SHIPPING / HANDLING, freight to destination
**** LABOR SNOW PLOW $125.00 $125.00 $1,000.00 8LABOR SNOW PLOW
Prices reflected on this quote are valid for 30 days and while current supplies last. However, prices are
subject to change if the program or promotion the prices were quoted under is no longer in effect.
$13,187.92ORDER TOTAL:
$0.00TAX:
SUBTOTAL: $13,187.92
Authorized By:
To: Parks and Public Works Committee
From: Matt Wolf, City Administrator
Date: October 15, 2026
Subject: Treating Riverfront with AquaNeat
Background
The City of Prescott currently budgets $1,500 annually for weed control along the
riverfront. Due to the proximity to the Mississippi and St. Croix Rivers, the City has
identified AquaNeat, for treating weeds above the ordinary high-water mark. (AquaNeat
Aquatic Herbicide is registered with the U.S. Environmental Protection Agency (EPA) to
treat for weeds and brush in aquatic environments)
Although funding for this
activity was increased
beginning in 2025, the City
has not conducted herbicide
treatments along the
riverfront since that budget
increase due to licensing
requirements.
Staff is seeking direction
from the Parks and Public
Works Committee on
whether the City should
resume this activity in 2027
or eliminate the associated
funding from the budget.
Discussion
Staff contacted the Wisconsin Department of Agriculture, Trade and Consumer
Protection (DATCP) for the requirements for applying AquaNeat along the City's
riverfront. This includes the following at a total cost of $148:
1. Obtain workbook in Category 5.0 – Aquatic and Mosquito.
2. Complete the necessary training and pass the certification examination.
3. Apply for a commercial applicator government license following certification.
These requirements would need to be completed before the City could begin spraying.
Also to note, Councilmember Ruona would like the City to not spray the riverfront due to
potential environmental impacts and employee safety.
Budget Considerations
The City's existing $1,500 annual allocation could continue supporting treatment if the
Committee wishes to start treatment. However, staff would first need to obtain the
necessary certification and licensing. Alternatively, the Committee could direct staff to
discontinue treatment and eliminate the $1,500 allocation from the 2027 budget.
Recommendation
Determine whether the City should resume weed control treatments along the riverfront
by retaining the $1,500 allocation in the 2027 Budget or eliminate the funding and leave
the riverbank untreated removing the $1,500 from the budget.
To: Parks and Public Works Committee
From: Matt Wolf, City Administrator
Date: October 15, 2026
Subject: Fairy Wonderland Improvements
Background
In 2023, the City Council approved a concept plan for improvements to Fairy
Wonderland Park in partnership with Healing Play, Inc. The improvements include
additional playground equipment, a stormwater pond, parking lot, youth soccer/football
field, restroom facilities, lighting, and other park amenities (see attached Concept Plan).
Healing Play, Inc. has raised more than $500,000 toward the installation of the first two
phases of playground equipment, with the remaining improvements planned as part of
the final phase.
Following the completion of the Elm/Washington Street project, the City identified
$1,138,457 in surplus funding within its Capital Projects Fund resulting from grant
funding received after the City's 2023 borrowing. To avoid additional borrowing for
planned 2027 capital improvements, the City allocated $683,567 of these funds toward
Fairy Wonderland Park.
In partnership with Healing Play, Inc., the City submitted a grant application to the
Wisconsin Department of Natural Resources (DNR) to assist with funding the final
phase. On September 18, 2025, the City was notified that it had been awarded
$387,594 through the federal Land and Water Conservation Fund (LWCF), administered
by the Wisconsin DNR.
Discussion
The City has now received the formal grant contract from the Wisconsin DNR (see
attached) for the Fairy Wonderland Park Improvements. With the grant the financing
breaks down as follows:
The grant provides approximately 40.41%
of the estimated project cost, with the
remaining 59.59% funded through the City's
previously allocated Capital Improvement
Fund.
Funding
Total Project Estimate $959,210
Wisconsin DNR Grant $387,594
City's Estimated Share $571,616
Previously Allocated City Funding $111,951
Estimated Savings to City $111,951
The agreement establishes a grant period of August 25, 2026, through August 24, 2029,
and requires compliance with applicable federal and state requirements, including
bidding, permitting, accessibility, and continued use of the property for public outdoor
recreation. The agreement also requires DNR approval of development plans before
construction and places permanent restrictions on converting the property to uses
inconsistent with public outdoor recreation.
To advance the project toward construction in 2027, Cedar Corporation has submitted
an Engineering Services Agreement (see attached) for the Fairy Wonderland Park
Improvements. The proposed services include topographic surveying, preliminary and
final engineering design, permitting, preparation of construction plans and
specifications, bidding assistance, construction staking, construction observation, and
project administration.
Cedar Corporation's proposal estimates a construction cost of $848,900 and
engineering fees totaling $110,300. The proposed project schedule anticipates
completion of final engineering design in February 2027, construction bidding in March
2027, commencement of construction in April 2027, and final project completion by
August 31, 2027.
The engineering services moves forward project specifications, obtain necessary
regulatory approvals, and solicit competitive construction bids. Final project costs will be
established following completion of the bidding process and reviewed against the
available project funding.
Recommendation
1. Consider recommendation of the Land and Water Conservation Fund Grant
through the Wisconsin DNR for $387,594 to City Council for Approval
2. Consider recommendation of Approval of the Engineering Services Agreement
with Cedar Corporation for a total of $110,300 to City Council for Approval
Attachments
1. Fairy Wonderland Concept Plan
2. Wisconsin DNR Grant – Land and Water Conservation Fund Grant
3. Cedar Corporation Engineering Proposal
C O R P O R A T I O N
STORMPOND
SOCCER FIELD RESTROOMS
CITY OF PRESCOTTFAIRY WONDERLAND PARKCONCEPT PLAN
EXISTINGTRAIL
FAIRY WONDERLANDCONCEPT LAYOUT
PEARL STREET
CANTON STREET
FENCE
PARKING LOT
PARALLEL PARKING(TYP) 29 STALLS
RELOCATEEXISTINGTRAIL
21 STALLS
LIGHT POLES(TYP) 2
SOLAR LIGHT(TYP)60' SPACING
BICYCLE RACKS
Project No. Pl338-234
Date: Oct 9, 2026
Standard Short Fonn Agreement for Professional Services 2019 Agreement- Page 1 of8
Attached: Standard Conditions
Confirmation of Client Request for Services
between Cedar Corporation (ENGINEER)
and City of Prescott (CLIENT)
Authorization to Perform Professional Engineering Services
ENGINEER is hereby authorized to proceed with the project listed below. The services are to be
completed in a timely manner mutually agreeable with the CLIENT and ENGINEER.
Project: Fairy Wonderland Park Improvements
Scope of Work: Engineer will complete professional design and construction engineering services
including topographic survey , utility data, base mapping, photo documentation, boundary verification,
preliminary design, public information meetings, staff/committee/council meetings, final design
documents, opinion of probable costs, permitting, specifications, bid documents, construction staking,
construction observation and construction administration services for the Fairy Wonderland Park
Improvements Project for construction in year 202 7.
Scope of Services: Cedar Corporation (hereinafter called "Engineer") proposes to render professional
design, bidding, contract award, and construction engineering services for the City of Prescott (hereinafter
called "Client") with respect to the above Scope of Work related to the Fairy Wonderland Park
Improvements Project in accordance with the City of Prescott (hereinafter called "Project"). The Engineer
will provide required professional services during the course of the Project as follows:
Land Surveying:
• Perform field topographic survey and utility data collection and incorporate into a base map
for the Fairy Wonderland Park project area, to complete the engineering design of the Project
described above. Perform any additionally required information including , sanitary sewer,
water main and laterals, storm sewer, property boundary for the project.
Preliminary Design Engineering:
• Attend initial kickoff meeting with city staff and city committee to discuss overall Project goals
and to finalize the Project work plan and schedule. The project concept plan has been developed
over the last several years. The project design will incorporate the features outlined in the
project concept plan attached with this proposal.
• Preparation of preliminary plans showing the bathroom building, parking lot, athletic
field, storm water pond, parking plan on Pearl Street, and existing trail modifications.
Project No. Pl338-234
Date: Oct 9, 2026
Standard Short Fann Agreement for Professional Services 2019 Agreement- Page 2 of 8
Attached: Standard Conditions
• Review governing agency permit requirements. Preliminary review of all WDNR required
construction site erosion control, and cultural resources permits.
• Meet with city staff, committee & council to review preliminary designs.
Incorporation and refinement of any necessary or suggested changes in the preliminary
design. Coordinate public informational meeting, if required.
• Attend required city staff, committee, council, and other governing agency meetings.
Final Design Engineering, Plans, Specifications, Bidding Documents, Permits:
• Preparation of final design documents, bathroom building plan, athletic field plan, parking
lot plan, construction detail sheets, erosion control plan, grading and restoration plan, traffic
control plan, construction specifications and bidding documents, and opinion of probable
costs.
• Preparation and submittal of necessary regulatory permit request application forms to the
Wisconsin Department ofNatural Resources for storm water management and construction
erosion control Water Resource Application Project Permit Discharge Storm Water from
Construction Site (WRAPP), and cultural resources permits.
• Submittal of 90% completed plans and specifications for review by the Client.
• Updated cost estimates at the 90% complete stage.
• Incorporation of comments received and prepare 100% completed plans and specifications.
• Bid documents to comply with the WDNR Knowles Nelson Grant requirements.
Bidding and Contracts:
• Prepare Advertisement for Bid to be published in the Client's official newspaper. Engineer will post
the Project to its Website via the Quest Electronic Construction Document Network for bid documents
download by prospective bidders.
• Provide answers and clarification of questions from contractors, suppliers, sub-contractors, and
Client during bidding, including preparation of any necessmy bid addendums.
• Coordinate electronic public bid opening.
• Review the bid results, prepare bid tabulation results for all bidders, confirm that low bidder has obtained
all bonds and insurance, and is capable of completing the work, and recommend bid award after review
of all bids.
Project No. Pl338-234
Date: Oct 9, 2026
Standard Short Fann Agreement for Professional Services 2019 Agreement- Page 3 of 8
Attached: Standard Conditions
• The Engineer will coordinate the issuance of Notice of Award, execution of Contract Documents,
required Bonds and Insurance, and Notice to Proceed with the Client.
• Attend required city staff, cmmnittee, council and other governing agency meetings.
Construction Engineering:
• Conduct a pre-construction meeting with Client, contractor, sub-contractors, utility companies, etc.
• Provide one-time horizontal and vertical control staking and layout for construction, as needed. Engineer
is not responsible for preservation of construction staking for the contractor, and any required re-staking
due to contractor negligence will be performed at the expense of the contractor. Any required re-staking
due to vandalism or severe weather will be discussed and negotiated with the Client.
• Provide full-time resident Project representative construction observation services during underground
utility construction and periodic part-time hours as needed during other construction related work to
observe contractor's work in conformance with plans, specifications and contract documents. The
Engineer cannot guarantee the performance of, and shall have no responsibility for, the actions or
omissions of any contractor, sub-contractor, supplier, vendor, or any other entity furnishing materials or
performing any construction work on the Project. Provide Client copies of construction observation
report documents.
• Provide construction coordination and administration services for the Project during construction. Oversee
and coordinate construction activities, including processing change orders and payment requests. Attend
weekly on-site progress meeting with contractor and Client.
• The Client shall review and approve all Work Directives or Change Orders for the Project as
presented by the Engineer prior to the work being commenced by the contractor.
• Prepare and provide as-built construction record drawings to the Client in AutoCAD electronic and hard
copy format upon completion.
• Attend required city staff, cmmnittee, and other governing agency meetings.
• Assist the Client with the requirements of the WDNR Knowles Nelson grant.
Project No. Pl338-234
Date: Oct 9, 2026
Standard Short Fann Agreement for Professional Services 2019 Agreement- Page 4 of 8
Attached: Standard Conditions
Method of Compensation: Work will be completed on a Lump Sum basis for $100,300 [not-to-exceed
without prior approval of CLIENT] for professional design and construction engineering services for
the Project in the amount described below pursuant to the proposed services listed in the above Scope of
Services. Any additional work not included in the Scope of Services will be invoiced to the Client on a
time and material basis. The Engineer will provide the Client a written quote for any additional work at
the Client's request. The Client will be responsible for all applicable governing agency fees including
but not limited to permit, review, application, recording, etc., fees.
Payments are due and payable thiliy (30) days from the date of the ENGINEER's invoice. Amounts
unpaid thirty (30) days after the invoice date shall bear interest at the rate of one percent (I%) per
month from invoice date.
Project No. Pl338-234
Date: Oct 9, 2026
Agreement- Page 5 of 8
Attached: Standard Conditions
Standard Short Fonn Agreement for Professional Services 2019
FAIRY WONDERLAND PARK IMPROVEMENTS
Construction Cost Estimate $848,900
Design Construction Engineering Fees:
Topographic Field Survey
Geotechnical Services
Utility Locating
Preliminary Design Engineering
Required City Meetings
Final Design Engineering
Agency Permitting
Specifications, bid documents, final cost estimate
Construction Engineering Fee:
Advertising, Bidding and Contract Services
Shop Drawing Reviews, Preconstruction Meeting
Construction Staking and Layout
Construction Observation
Construction Coordination and Administration
Construction Record Drawings
$4,000
$3,500
$1,500
$38,000
$1,500
$20,000
$3,500
$2,500
$2,200
$1,600
$5,500
$19,000
$6,500
$1,000
Total Engineering Lump Sum "Not to Exceed" Fee $110,300
Project No. Pl338-234
Date: Oct 9, 2026
Standard Short Form Agreement for Professional Services 2019 Agreement- Page 6 of8
Attached: Standard Conditions
Timeline: Work will be completed as follows:
TASK COMPLETION DATE
City Council Notice to Proceed
Preliminary Design Engineering
Final Design Engineering
Bid Opening
City Council Award Bid
Notice of Award & Contract Documents
Pre-Construction Meeting
Commence Construction
Substantial Completion of Construction
Final Completion
October 26, 2026
November 2026
February 2027
March 11, 2027
March 22, 2027
April 5, 2027
April 9, 2027
April 12, 2027
August 6, 2027
August 31, 2027
Client Supplied Information: The Client will provide the Engineer with available copies of construction
record plans for existing water system, sanitary sewer system, storm sewer system, water main, sanitary
sewer, laterals, and storm sewer field location marking, utility systems maps, sanitary sewer televising
video and reports, assessor property owner maps and parcel information, right -of-way maps, recorded
easement documen ts, prope1iy title search if needed, known site environmental issues and concerns,
boundary survey/certified survey/plat maps, Project review input and comments, etc. for the Project.
Project No. Pl338-234
Date: Oct 9, 2026
Standard Short Form Agreement for Professional Services 2019 Agreement- Page 7 of8
Attached: Standard Conditions
Services Not Provided as Part of this Proposal: Archaeological studies and investigations,
environmental studies and assessments, environmental investigations, boundary survey, easement
documents, title search, land acquisition, field locating and marking of existing underground utility
systems, governing agency permit fees, ecological studies and investigations, flood plain studies and
determination, traffic impact analysis and report, WIDOT Trans 233 permits and approval request, and
historical site studies and investigations are not included as part of this proposal.
Sincerely,
CEDAR CORPORATION
Greg Adams, P.E.
Municipal Engineering Team Leader
Accepted this day of , 2027
By: _________________________________ ________________________________
Mike Gerke, Mayor Matt Wolf, City Administrator
Standard Short Fonn Agreement.docx Agreement - Page 8 of 8
To: Parks and Public Works Committee
From: Matt Wolf, City Administrator
Date: October 16, 2026
Subject: Review of Parks Improvement Fund and Capital Improvement Items
Discussion
The City is updating our Capital Improvement Plan (CIP) for 2027-2033. The current
plan is at the following link: https://www.prescottwi.gov/DocumentCenter/View/960/CIP-
2025-2031
As part of the updated CIP, the City will include projects funded through the Parks
Improvement Fund. Staff would like the Parks and Public Works Committee to review
projects that have previously been discussed or for which the City has existing
obligations under approved development agreements. The Committee is being asked to
provide feedback on project priorities, anticipated timelines, and any additional projects
that should be considered for inclusion in the CIP.
The list below identifies current and proposed park projects, along with their estimated
costs and potential timelines.
The Parks Improvement Fund currently has a balance of $252,596. However, $100,000
of this balance is already committed to improvements associated with the Coulee River
Trail network under the grant agreement executed with Friends of Freedom Park.
Additionally, the City has agreed to provide matching funds of up to $20,000 for future
trail improvements based on funds raised by Friends of Freedom Park/Coulee River
Item
Estimated
Cost
(2027)
Rationale Timeline Funding Proposed
Non-Motorized Boat Launch Phase 2 $69,600 Repairs and
Maintenance
None Parks Improvement
Fund
The Bluffs Park Unknown Replacement of Shane
Park Circle Park
None Parks Improvement
Fund
Magee Park Shelter $12,500 Lion's Club Request &
Cost Share
2027 Parks Budget
Trail - Dexter Street to Borner Street $80,000 The Bluffs Development
Agreement (D.A.)
2027-2030 Parks Improvement
Fund
Trail - Walnut Circle to Magee Park $140,000 Walnut Circle D.A. & FFP
Grant Agreement
2027-2028 Parks Improvement
Fund
Trails. These commitments leave approximately $132,596 in currently uncommitted
funds, assuming the full $20,000 matching contribution is utilized.
The City does contribute its 30% of room tax that it received towards are Parks
Improvement Fund, which conservatively adds $40,000 a year to the Fund balance.
Additionally, any remaining funds within the Parks Budget Repair and Improvements
Escrow line item goes into the Parks Improvement Fund balance, which varies annually
depending on repairs and maintenance costs.
The City currently has $157,995 in Parks Impact Fees available to fund eligible
improvements identified in the Community Needs Assessment Report. However, the
report does not currently include the proposed improvements to The Bluffs Park, which
would replace the existing park at Shane Park Circle.
Although a detailed cost estimate has not yet been prepared for The Bluffs Park, based
on the improvements completed at Sunset Park, the estimated project cost is
anticipated to range from $150,000 to $300,000.
Staff would like the Parks and Public Works Committee to consider adding The Bluffs
Park improvements to the Community Needs Assessment Report to potentially allow
Parks Impact Fees to be used toward the project. If the Committee supports this
approach, staff will contact Trilogy Consulting to determine whether the report can be
amended, what the amendment process would involve, and whether the proposed
improvements would qualify as eligible impact fee expenditures.
Recommendation
1. Review the proposed park improvement projects and provide direction on project
priorities, anticipated construction timelines, and any additional improvements
that should be considered for inclusion in the City's 2027–2033 Capital
Improvement Plan.
2. Provide direction on whether to pursue an amendment to the City's Parks Impact
Fee Community Needs Assessment Report to include the proposed
improvements to The Bluffs Park.