Please note that, upon reasonable notice, at least 24 hours in advance, efforts will be made to accommodate the
needs of disabled individuals through appropriate aids and services or provide a video link for meetings. For additional
information to request this service, please contact the City Clerk's Office at 715-479-8682 ext. 224,
525 E. Maple Street, P.O. Box 1269, Eagle River WI 54521.
AGENDA NOTICE (10/16/2026)
THE PLANNING COMMISSION OF THE CITY OF EAGLE RIVER WILL HOLD A SPECIAL SESSION ON
THURSDAY, OCTOBER 22, 2026, AT 5:00 P.M. AT CITY HALL, 525 E. MAPLE STREET IN EAGLE RIVER.
Notice is hereby given that a majority of the City Council of the City of Eagle River may be attending scheduled
Planning Commission meetings either in person or via zoom. This constitutes a meeting of the City Council
pursuant to State ex rel. Badke v. Greendale Village Bd., 173 Wis. 2d 553, 494 N.W.2d 409 (1993), and must be
noticed as such, although the Council will not take any formal action at these meetings.
This meeting will be available by Zoom at the following link:
https://us06web.zoom.us/j/85111695208?pwd=x5pMv8crrbsPuYwefObTYbJG0m83b3.1
Meeting ID: 851 1169 5208
Passcode: 963936
1) Call to Order.
2) Roll Call.
3) Discussion and possible action on the following agenda item(s):
a) Comprehensive Plan, Review and Possible Modification of the Following Chapters/Maps:
i) Chapter 7, Land Use
ii) Map 6, Existing Land Use
iii) Map 7, Future Land Use
b) Scheduling of recurring Comprehensive Plan Special Meetings moving forward
4) Adjournment.
Robin Ginner, City Administrator
September 17, 2026
A meeting of the Plan Commission of the City of Eagle River was called to order at 5:05pm by Mayor Deb
Brown.
Roll Call: Alex Forer, Mary Horant, Adam Grassl, Kim Schaffer and Deb Brown. John Hletko arrived at
5:45PM. Also in attendance Becky Bolte. Absent: Robin Ginner and Brad Adamovich.
a) Comprehensive Plan update: Eric Sonnleitner was present for North Central Wisconsin Regional
Planning Commission. Review of NCWRPC Chapters 5 - Transportation, Chapter 6 – Economic
Development, including Data Centers discussion, and Chapter 8, Intergovernmental Cooperation.
Sonnleitner gave summaries of each chapter presented. Discussion.
b) Scheduling of recurring Comprehensive Plan Special Meetings. The next meeting for the Planning
Commission Comprehensive Plan review and update was scheduled for October 22, 2026 at 5:00pm at
Eagle River City Hall.
Motion by Horant, 2
nd by Grassl to adjourn at 5:05PM. Carried, all.
Becky J Bolte - Clerk
1 City of Eagle River Comprehensive Plan
Chapter 7
Land Use
Land use analysis is a means of broadly classifying how land is used. Each type of use has its own
characteristics that can determine compatibility, location, and preference to other land uses in the City .
The land use plan brings together consideration for both the physical development as well as the social
characteristics of the City. Land use mapping and related information is used to analyze the current pattern
of development and serves as the framework for formulating how land will be used in the future.
To arrive at an optimum plan that will be both effective and implemented, the plan must account for past
development activity as well as current market factors and conditions that shape where and how land will
be developed. This chapter discusses uses of l and in the City of Eagle River . The existing land use types
are defined, current land uses are analyzed, and existing and potential land use conflicts are identified.
Previous Plans and Studies
Vilas County Comprehensive Plan, 2023
The Vilas County Comprehensive Plan’s chapter on land use analyzes patterns of development, existing
land use, and future land use. The 2023 plan sets the following land use goals:
• Provide for a well-balanced mix of residential, business, industrial, recreational, forestry, and other
uses to serve the future needs of Vilas County and to maintain the area as a desirable place to
live and work.
• Work cooperatively with Town and neighboring governments to promote coordinated land use
and a compatible development pattern that respects private property rights; to minimize land use
conflicts and negative development impacts; to carefully consider the use, location, and density of
development and how it affects the natural resources, community character, anticipated growth,
and need for utilities and services.
• In conjunction with local municipalities, retain and preserve the rural, “Northwoods” aesthetics
and related quality of life.
2 City of Eagle River Comprehensive Plan
Regional Comprehensive Plan, 2025
The RCP’s Land Use chapter looks in detail at the land uses through the ten -county region and identifies
the following issues and trends related to land use:
• Dispersed Land Use Patterns. As the Region continues to age, a dispersed population will
impact the ability of residents to access services. There are also concerns about continuing to
fund infrastructure as a result.
• Contamination and Blight. Older neighborhoods in the Region may have sites contaminated
by former industry and structures that have fallen into disrepair. There is an opportunity to
rehabilitate these properties to save infrastructure costs compared to new construction.
• Environmental Features. Development pressures can fragment woodlands and other wildlife
habitat, increase runoff into waterways, impact aesthetics, and contribute to erosion if not
designed properly.
• Land Use Demand. Work-from-home may increase the number of people living in certain
areas, and decrease demand for commercial space, influencing land use patterns and infrastructure
needs.
• Renewable Energy. While renewable energy provides environmental and economic
opportunities, large scale solar and wind power is approved at the State level, with few tools for
municipal and county government to manage its location, screening, and other impacts.
• Comprehensive Plans. While many communities and counties have adopted comprehensive
plans, they are frequently not being updated as required by Wis. Stats. 66.1001. See Map 7 for
Comprehensive Plan status.
3 City of Eagle River Comprehensive Plan
Existing Land Use Inventory
A land use planning process requires that all of the existing land uses in the community and surrounding
area be inventoried. The overall form and arrangement of Eagle River is determined by its pattern of
residential, commercial, industrial and other activities. The location and density of various uses and the
way in which they are grouped, directly affects the quality of life in the City.
Existing land use patterns are needed to understand how to develop a desired future land use pattern.
Table 21 provides a breakdown of land use within the City. Map 6 – Existing Land Use depicts
existing land use throughout the City and surrounding area . Both Table 21 and Map 6 are based off of
2025 aerial imagery.
The most common land use activity within the City is Transportation, mostly due to the presence of the
Eagle River Regional A irport, accounting for over 29 percent of the City’s land base. Other common land
use activities within the City include Residential, Commercial, Outdoor Recreation, and Governmental.
About 10 percent of the City’s land currently consists of undeveloped lands (woodlands and open lands).
However, most of these lands are located in environmentally sensitive areas such as wetlands or
floodplains or in areas with environmental conditions th at limit the suitability for buildings such as areas
in steep slopes.
Residential development generally exists in the core part of the City and in the southern portion of the
City. Commercial development is mostly found within the Downtown area and along major transportation
corridors. The Eagle River Regional A irport is located in the northwest corner of the City , while pockets
of industrial uses are located throughout the City, most prominently adjacent to the airport, and in the
city block between S Forrest St, W Pine St, S Willow St, and W Division St.
Table 21: Existing Land Use, 2025
Acres Percent
Commercial 304 13.9%
Governmental / Institutional 224 10.3%
Industrial 47 2.2%
Open Lands 35 1.6%
Outdoor Recreation 272 12.5%
Residential 362 16.6%
Transportation 640 29.3%
Utility 4 0.2%
Water 111 5.1%
Woodlands 183 8.4%
Total 2,182 100.0%
Source: NCWRPC GI S
4 City of Eagle River Comprehensive Plan
Adjacent to the City is the 1.5-mile radial planning area, which encompasses the City’s whole exterritorial
area. Considerable forested lands as well as scattered low -density residential uses and some businesses
are in this area. There is also residential activity concentrated along water frontage within this area as
well. Much of the future growth of the City will occur in this zone as a result of development pressure
for City services.
This existing land use information provides the foundation for understanding where future land uses may
go. Reviewing what land use patterns have occurred, in addition to reviewing the Natural Resources
Map in this plan, will provide some guidance for what land uses are possible on undeveloped lands.
Land Use Trends
Land Supply
As shown in the Existing Land Use Map and in Table 21, the City contains over 200 acres of undeveloped
land (woodlands and open lands). However, much of these undeveloped lands are located in wetland
and/or floodplain areas, making them unsuitable for development.
Land Demand
Based on the population projections discussed in Chapter 1, Table 2 2 summarizes the projected land
demand based on the current acres of each land use per person:
Wisconsin DOA Projections project a declining demand for land within the City over the next several
decades. The City of Eagle River’s status as one of the most suitable and desirable locations within Vilas
County for residential development makes the DOA’s projected decrease in demand for land within the
City unlikely.
NCWRPC Projections indicate that, with continued population growth through 2050, an average of 52
acres of developable land are needed per decade between 2020 and 2050, for a total demand of 156 acres
by 2050.
Though the DOA’s population projections are considered the official state projections, the City being
one of the few communities within Vilas County to provide water and sewer infrastructure means that
land demand for future development will likely exceed the DOA projections. Additionally, since the City
provides most of the services geared towards elderly residents within Vilas County, many residents may
move into the City as they advance in age. Therefore, the NCWRPC projections predict an alternative
scenario that could result from these factors.
5 City of Eagle River Comprehensive Plan
Table 22: Land Use Demand in Acres
Projection Category 2020-2030 2030-2040 2040-2050
WI DOA Projected new residents 15 -54 -101
Residential (0.24 acres/person) 4 -13 -24
Commercial (0.20 acres/person) 3 -11 -20
Industrial (0.03 acres/person) 0.5 -2 -3
Total 7 -25 -47
NCWRPC Projected new residents 104 111 119
Residential (0.24 acres/person) 25 26 28
Commercial (0.20 acres/person) 21 22 24
Industrial (0.03 acres/person) 3 3 4
Total 48 52 55
Source: Wisconsin DO A & NCWRPC
The City of Eagle River is well suited for accommodating future development, as it is one of the only
communities within Vilas County that provides municipal water and sewer infrastructure. The City of
Eagle River is also home to many services and amenities that are becoming increasingly important for
residents, making it an even more attractive location for future development. Additionally, shrinking
household sizes means that demand for housing can continue even if there is not a population increase,
since more housing units are needed to house the same number of people when household sizes decrease.
Therefore, it is more likely that future land demands will more closely follow the NCWRPC projections
than the WI DOA projections over the next several decades.
It is also important to note that while the City has an abundant supply of undeveloped land , most of this
undeveloped land is located within wetland or floodplain areas, limiting the development potential of these
lands. Limited land available within the current City boundary that is suited for development could lead
to an increased need for annexation for the City to meet the land demands required for future
development.
Residential
Residential demand is measured by examining population projections from the Wisconsin DOA and the
NCWRPC. Population projections range from a DOA projected decrease of 140 residents between 2020
and 2050 and an NCWRPC projected increase of 334 residents between 2020 and 2050. Table 22 shows
projected residential land demand based on these population projections and the current 0. 24-acre
average acres of residential land per capita, resulting in a projected need for 156 total acres of residential
land between 2020 and 2050 based on NCWRPC projections.
6 City of Eagle River Comprehensive Plan
Commercial and Industrial
Commercial and industrial development is subject to market forces and difficult to predict. Based on
existing density and DOA projections, there is a projected decrease in demand for both commercial and
industrial development for each decade between 2020 a nd 2050. In contrast, the NCWRPC projections
project a need for 76 additional acres of commercial (6 6 acres) and industrial ( 10 acres) lands by 2050.
Should economic development efforts reverse the projected decrease in demand by DOA, and if trends
continue to follow the NCWRPC projections more closely, then more land may be needed for these
types of development.
It is also important to note that the City’s two industrial park s are currently near capacity, which could
result in the City needing to create a new industrial park in order to accommodate future commercial
and industrial development. Another option to fulfill commercial and industrial land demand is
redevelopment and infill development. There are currently underutilized properties, such as vacant lands,
brownfields, and functionally obsolete buildings within the City that offer potential redevelopment and
infill development opportunities within the City.
Land Values
Table 23 displays the assessed land values in the City of Eagle River . It is important to note that lands
enrolled in the Managed Forest Law and Forest Crop Law programs and other tax -exempt lands are not
included in values for Table 2 3. It should also be noted that improvements (structures) are included in
these values. In 2025, the assessed value per acre in the City was valued at about $ 362,422 per acre.
Properties classified as “ Residential” have the highest value per acre within the City , followed by
properties classified as “ Commercial” and “Manufacturing”.
Table 23: Assessed Land Value (per acre), 2025
Land Classification Total Value of Land Total Value per Acre
Residential $154,622,800 $450,795
Commercial $149,378,100 $304,853
Manufacturing $3,332,900 $222,193
Agriculture $0 $0.00
Undeveloped $0 $0.00
Forest $0 $0.00
Agricultural Forest $0 $0.00
Other $0 $0.00
Total $307,333,800 $362,422
Source: WI Department of Revenue
7 City of Eagle River Comprehensive Plan
Opportunities for Redevelopment
There are numerous infill and redevelopment opportunities within the City of Eagle River . Pockets of
vacant land, brownfields, and functionally obsolete buildings exist throughout the City where new
industrial, commercial, and residential development could occur. There are also scattered vacant and
underutilized buildings that once were industrial type uses throughout the City . Additionally, the City has
an aging housing stock, as many of the City’s residential areas are showing their age and could be
revitalized .
There are also numerous previously contaminated sites within the City that could be redeveloped,
provided proper remediation of these sites occurs. According to the WI DNR’s Bureau of Remediation
and Redevelopment Tracking System (BRRTS), there were 160 previously contaminated sites within the
City as of Spring 2026. Of these sites, two have an open status and need remediation. The remaining 158
contaminated sites have been remediated to DNR standards and have either already been redeveloped
or are ready for redevelopment. Several agencies such as the WI DNR, WEDC, and EPA all offer funding
and assistance programs for cleaning up brownfields and contaminated sites. The DNR maintains a list of
brownfield resources here: https://dnr.wisconsin.gov/topic/Brownfields/Financial.html .
Existing and Potential Land Use Conflicts
Short-Term Rentals
The high number of housing units being used as short -term rentals pose potential conflicts for the City.
Wisconsin’s “Right -to-Rent” law (Wis. Stat. 66.1014) limits the ability of local governments to restrict
short-term rentals. Local governments such as the City of Eagle River are limited to regulating aspects of
the short -term rentals such as requiring licenses for short -term rental operators and regulating the
maximum number of days a short-term rental unit can be rented out (no less than 180).
Data Centers
With d ata centers rapidly spreading throughout the country, it is important to consider the potential
impacts of data centers . On one hand, data centers can potentially provide beneficial impacts s uch as
increases in property tax revenues for communities and more jobs. On the other hand, there are
significant public concern s regarding data centers, such as potential harmful impacts on the environment,
increased utility costs for residents, and a negative impact on community aesthetics . Environmental and
utility cost concerns are mainly due to the significant amounts of resources (water, electricity, etc .) that
are needed for data centers to operate.
When it comes to regulating data centers, zoning is the strongest tool available to municipalities. Zoning
allows municipalities to limit the districts where data centers are allowed via permitted or conditional
use, or to outright prohibit data centers . Municipalities can als o use zoning to impose conditions and
restrictions on data center development such as setback, height, screening, and access requirements in an
effort to help mitigate potential local concerns. Many municipalities and counties throughout Wisconsin
are also considering temporary 12-month moratoriums on data center development. A moratorium on
data center development gives the municipality time to determine the proper regulations and restrictions
on data center development that would best serve their community .
8 City of Eagle River Comprehensive Plan
Future Land Use
The previous portions of this comprehensive plan have presented a discussion on population trends,
environmental conditions, transportation and infrastructure considerations, housing and economic
conditions and trends, and existing land use patterns and goals, that are needed when considering growth
expectations for the City of Eagle River . The Future Land Use Map (Map 7) takes into consideration
all of these factors and illustrates graphically how the City of Eagle River is planned to grow for the next
20 years. It is important to note that the future land use plan map is not a zoning map, rather it is a
depiction of the desired growth patterns for several years into the future . The City’s zoning ordinance
and zoning map are the actual documents that set standards for each of the land uses, including setbacks,
height limitations, minimum lot sizes, etc. It is also important to note that the future land use plan is
dynamic and can be amended as market trends or the local economy change. The Wisconsin
Comprehensive Planning Law, Ch. 66.1001, requires that the comprehensive plan be updated no less than
once every ten years, and the zoning ordinance must be consistent with the comprehensive plan. The
future land use plan map often shows some areas to be used for purposes other than what the current
use may be. That map is a blueprint for development and can be changed. It is dynamic. The following
paragraphs, along with information presented thro ughout this plan, help explain the reasoning behind the
future land use plan categories.
Future Land Use Map Classifications:
Future land use classifications are groups of land uses that are compatible and separates conflicting uses.
The classifications are not zoning districts and do not have the authority of zoning but are intended for
use as a guide when making land use and zoning de cisions.
Downtown Commercial Use
This land use category encompasses the downtown commercial core and allows limited residential uses
as described in the City of Eagle River Zoning Code. This district is intended to accommodate the wide
variety of property uses, which were part of the hist oric development of the downtown area of Eagle
River. Appropriate zoning districts for this land use category include Downtown Commercial or Planned
Unit Development (PUD).
Highway Commercial Use
This land use category is intended to accommodate those motorist oriented commercial activities which
may not be compatible with the downtown commercial district and whose services are community or
region wide and to accommodate limited residential uses as described in the City of Eagle River Zoning
Code. Appropriate zoning districts for this land use category include Highway Commercial and Planned
Unit Development (PUD).
Industrial Use
This land use category is intended to accommodate manufacturing, warehousing, fabricating, packing,
packaging, assembly, repairs, terminals, departments, storage and similar uses which do not include
residential uses or short -term residential use or dwelling unit of any kind. Appropriate zoning districts for
this land use category include Industrial.
9 City of Eagle River Comprehensive Plan
Park and Recreation Use
This land use category is intended to preserve and perpetuate in an open state certain areas, such as rivers
and drainage ways, wetlands and marshes, parks, floodplains and green belts and natural habitats for plants
and animal life. It is also intended to utilize these areas for parks, recreation and recreation facilities
including, through conditional use, campgrounds. Appropriate zoning districts for this land use category
include Park and Recreation and Government Use.
Government Use
This land use category applies to those lands where federal, state, local governmental and quasi -
governmental activities are conducted and where governments or quasi -governmental units hold title to
such lands for community or public use. Appropriate zoning district s for this land use district include t he
Government Use district.
Residential
There are several residential future land use classifications mapped in the Future Land U se Map which are
described below. Types of residential development desired within the City range from s ingle-family
housing to multi -family housing options such as apartment complexes and condominiums .
2025 Wisconsin Act 173 requires residential densities to be mapped; see Map 7: Future Land Use.
Residential land use categories and densities found on this map are as follows:
Single Family Use
This future land use category has a maximum density of 6. 05 dwelling units per acre and is intended for
low-density single-family residential. Appropriate zoning districts for this land use category include Single -
Family Residence and Planned Unit Development (PUD) .
Single/Two Family Use
This future land use category has a maximum density of 6.05 dwelling units per acre and is intended for
moderate density, allowing both single -family and two -family units. Appropriate zoning districts for this
land use category include Single/Two Family Residence and Planned Unit Development (PUD).
Multiple Family Use
This land use category has a maximum density of 6.05 dwelling units per acre and is intended for high-
density, allowing for multi- family housing. Appropriate zoning districts for this land use category include
Multiple-Family Residence and Planned Unit Development (PUD).
Mixed Use
This land use category has a maximum density of 6.05 dwelling units per acre and is intended for
commercial, office, entertainment, institutional, and residential uses. The idea is to customize
development to the land/water features bordering the property and the State Highway infrastructure.
The following zoning districts are most appropriate for this future land use category: Highway
Commercial, Multi-Family Residence, Single - and Two -Family Residence, Single -Family Residence,
Office/Residence, and Planned Unit Development (PUD).
10 City of Eagle River Comprehensive Plan
Office/Residential Use
This land use category has a maximum density of 6.05 dwelling units per acre and is intended for moderate
density residences with office buildings or civic, government, educational or institutional structures.
Appropriate zoning districts for this land use category include Office/Residence, Planned Unit
Development (PUD) or Government Use.
** - Note that, per State Statute, 100-year floodplains, wetlands, and lands owned by local, state, or federal
government that are not intended for development do not count towards net density for any residential
areas mapped in the Future Land Use Map.
Projected Residential Land Demand
Wisconsin Act 173 also requires comprehensive plans to project residential land demand in five- year
increments. Because the State’s official population projections are only available in ten -year increments
(as shown earlier in Table 22) , and Act 173 requires five -year increments, the five -year demand is
calculated by dividing each decade in two as indicated below in Table 24. Note that the DOA projection
reflects the “low” range of acreage demand and the NCWRPC projection reflects the “high” range of
demand, with actual demand likely falling somewhere between the two.
Table 24: Act 173 Residential Demand Projections
Projection and Residential
Land Use
2025-
2030
2030-
2035
2035-
2040
2040-
2045
2045-
2050
Total
2025-
2050
DOA Projected Land Demand 2 -6 -6 -12 -12 -35
NCWRPC Projected Land Demand 12 13 13 14 14 67
S ou rce: DOA & NCWRPC
11 City of Eagle River Comprehensive Plan
Land Use Programs
A number of different programs directly and indirectly affect land use within the City. The principal land
use programs utilized by the City include the Eagle River Zoning Ordinance, the City’s Subdivision
Ordinance, and extraterritorial zoning. See the Im plementation Chapter for more on these ordinances.
Comprehensive Planning Programming
Wisconsin’s comprehensive planning law was established in state statutes in 1999. The comprehensive
plan is intended to be a local government's guide to community physical, social, and economic
development. Comprehensive plans are not meant to serve as land use regulations in themselves; instead,
they provide a rational basis for local land use decisions with a twenty -year vision for future planning and
community decisions.
The Wisconsin Comprehensive Planning Law does not mandate how a local community should grow, but
it requires public participation at the local level in deciding a vision for the community's future. The
uniqueness of individual comprehensive plans reflects community -specific and locally driven planning
processes.
While a local government may choose to include additional elements, a comprehensive plan must include
at least all of the nine elements below as defined by the Comprehensive Planning Law (s. 66.1001).
• Issues and Opportunities (Demographics)
• Agricultural, Natural and Cultural Resources
• Housing
• Utilities and Community Facilities
• Transportation
• Economic Development
• Land Use
• Intergovernmental Cooperation
• Implementation
12 City of Eagle River Comprehensive Plan
Goals, Objectives, and Policies
Goal: Guide future development and redevelopment of both public and private property.
Objectives:
1. Plan for future residential, light industrial, commercial, urban forestry, recreation conservancy and
other uses in accordance with public input.
2. Recommend development patterns .
3. Guide future development for compatibility .
4. Develop a future land use map for the future potential land uses considering existing land use,
economic conditions, location and density over the next 20 years.
5. Continue to r eview and update City ordinances and policies to ensure that they can effectively
guide land use development throughout the City in an effort to miti gate and prevent land use
conflicts.
Map 6City of Eagle River - Vilas County
210 McClellan St., Suite 210, Wausau, WI 54403
715-849-5510 - staff@ncwrpc.org - www.ncwrpc.org
North Central
Wisconsin Regional
Planning Commission
Prepared By:
This map is neither a legally recorded map nor a survey
and is not intended to be used as one. This drawing is
a compilation of records, information and data used for
reference purposes only. NCWRPC is not responsible for
any inaccuracies herein contained.
Source: WisDOT, WI DNR, NCWRPC, Vilas Co
²
DRAFT
0 0.65 1.30.33
Miles
Minor Civil Division
U.S. Highway
State Highway
County Highway
Local Roads
Private Roads
Parcels
Existing Land Use 2025
Agriculture
Commercial
Governmental / Institutional
Industrial
Open Lands
Outdoor Recreation
Residential
Transportation
Utility
Woodlands
Water
"·32
¡¢45
"·70
"·70
"ÿG
"ÿH
N
Railroad
St
E Hospital Rd
HiPinesLn
PleasureIsland
Rd
E Spruce St
W Illinois St
W Mill St
CapichDr
E Wall StPark St
ESilver Lake Rd
E Pine St
N Sixth St
E Tamarack St
N Hirzel St
E Sheridan St
N First St
E Division St
N
Seventh
St
N
W
isconsin
St
E MapleSt
Bridge
St
AgofRd
Illinois Rd
N Silver Lake RdN Third St
S First St
N
BirchSt
S Third StS Second StS Fourth St
Loon Lake Rd
S Fifth St
S Main St
S Sixth St
S Seventh St
S
RailroadSt
WDivision St
N Eighth St
N
M
ichigan
St
N
M
innesotaSt
N Main St
NicoletSt
W Sherburn St
N
Adam
sRd
S Aquila Ct
N Red Fox Ln
W Jack Frost St
W Recycling Way
S Willow St
E Walnut St
N Aquila Ct
E Mckinley
N Bond St
S Forrest St
Oak Dr E Tuss St
W Pine St
N Indiana St
NDyerPark
N Bluebird Rd
Elm
Dr
LostRiverRd
BolteRd
TreesS
t
Lynx Lake
Duck Lake
Otter Lake
Eagle Lake
Yellow
Birch Lake
Silver Lake
Dollar Lake
Taylor
Lake
Watersmeet
Lake
Catfish Lake
Rice Creek
Eagle River
Wisconsin River
Mud Creek
Oneida
County
Town of
Washington
Town of
Cloverland
Town of Lincoln
Town of
Lincoln
Existing Land Use
WINCHESTER
PRESQUE ISLE
LAND O'LAKES
BOULDER
JUNCTION
PHELPS
MANITOWISH
WATERS
CONOVER
PLUM LAKE
LAC DU
FLAMBEAU
ARBOR VITAE
CLOVERLAND WASHINGTON
LINCOLN
Eagle River
ST. GERMAIN
Map 7City of Eagle River - Vilas County
210 McClellan St., Suite 210, Wausau, WI 54403
715-849-5510 - staff@ncwrpc.org - www.ncwrpc.org
North Central
Wisconsin Regional
Planning Commission
Prepared By:
This map is neither a legally recorded map nor a survey
and is not intended to be used as one. This drawing is
a compilation of records, information and data used for
reference purposes only. NCWRPC is not responsible for
any inaccuracies herein contained.
Source: WisDOT, WI DNR, NCWRPC, Vilas Co
²
DRAFT
0 0.65 1.30.33
Miles
Minor Civil Division
U.S. Highway
State Highway
County Highway
Local Roads
Private Roads
Parcels
Future Land Use
Forestry
Single Family Residential
Single & T wo Family Residential
Multi-Family
Downtown Commercial
Highway Commercial
General Business
Office/Residential
Recreation/Recreation Business
Industrial
Mixed Use
Parks & Recreation
Transportation
Water
"·32
¡¢45
"·70
"·70
"ÿG
"ÿH
N
Railroad
St
E Hospital Rd
HiPinesLn
PleasureIsland
Rd
E Spruce St
W Illinois St
W Mill St
CapichDr
E Wall StPark St
ESilver Lake Rd
E Pine St
N Sixth St
E Tamarack St
N Hirzel St
E Sheridan St
N First St
E Division St
N
Seventh
St
N
W
isconsin
St
E MapleSt
Bridge
St
AgofRd
Illinois Rd
N Silver Lake RdN Third St
S First St
N
BirchSt
S Third StS Second StS Fourth St
Loon Lake Rd
S Fifth St
S Main St
S Sixth St
S Seventh St
S
RailroadSt
WDivision St
N Eighth St
N
M
ichigan
St
N
M
innesotaSt
N Main St
NicoletSt
W Sherburn St
N
Adam
sRd
S Aquila Ct
N Red Fox Ln
W Jack Frost St
W Recycling Way
S Willow St
E Walnut St
N Aquila Ct
E Mckinley
N Bond St
S Forrest St
Oak Dr E Tuss St
W Pine St
N Indiana St
NDyerPark
N Bluebird Rd
Elm
Dr
LostRiverRd
BolteRd
TreesS
t
Lynx Lake
Duck Lake
Otter Lake
Eagle Lake
Yellow
Birch Lake
Silver Lake
Dollar Lake
Taylor
Lake
Watersmeet
Lake
Catfish Lake
Rice Creek
Eagle River
Wisconsin River
Mud Creek
Oneida
County
Town of
Washington
Town of
Cloverland
Town of Lincoln
Town of
Lincoln
Future Land Use
WINCHESTER
PRESQUE ISLE
LAND O'LAKES
BOULDER
JUNCTION
PHELPS
MANITOWISH
WATERS
CONOVER
PLUM LAKE
LAC DU
FLAMBEAU
ARBOR VITAE
CLOVERLAND WASHINGTON
LINCOLN
Eagle River
ST. GERMAIN
Source: City of Eagle River website. First collected Oct 21, 2026.