Board of Water & Sewerage Commissioners — Minutes
City of Stevens Point · Portage County · Board of Water and Sewerage Commissioners · meeting of Oct 19, 2026 · Minutes
Open the original document More from City of Stevens Point
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
City of Stevens Point
Board of Water and Sewerage Commissioners
October 19, 2026 - 12:00 PM
Stevens Point Public Utilities
300 Bliss Avenue, Stevens Point, WI
OR
Zoom Teleconferencing
Meeting ID: 820 26885705
By Computer: Zoom Link
By Phone: (303) 715-8592
MINUTES
Discussion and Possible Action on:
1. Roll Call.
PRESENT: Paul Adamski, Carl Rasmussen, Anna Haines, Ray Schmidt and Jeff
Bushman
ALSO PRESENT: Joel Lemke, Eric Southworth, Shane Kohnen, Jennifer Schmeiser,
Jason Draheim, Jaime Zdroik, Natalie Rink, Ald. Shuda, and Liz/resident
2. Approval of Minutes
Motion made by Carl Rasmussen, seconded by Jeff Bushman to approve the
September 14, 2026 meeting minutes of the Board of Water & Sewerage Commission.
Ayes all. Nays none. Motion carried.
3. Approval of Department Claims
Motion made by Ray Schmidt, seconded by Jeff Bushman to approve the claims for the
month of September as audited and read.
Ayes all. Nays none. Motion carried.
4. Utility rate adjustments for water, wastewater, and stormwater - Joel Lemke
Joel explained that the anticipated water rate increases are listed as a range between
38.19 - 53.96% because there are so many different rate adjustments/tariffs involved
from industrial, public, commercial and residential. The final ruling from the PSC on
water rates is included in the packet. The wastewater analysis was done by Baker Tilly
with a rate of 29%. Stormwater didn't quite meet debt service coverage ratio that is
required through our bonding of past and future debt. So an increase of 45% was
determined by staff for that and also covers increased capital, inflation etc. We are
hoping to have the rate increase and moving from quarterly billing to monthly billing
effective January 1, 2027.
Water rates were issued in two steps by the PSC. The first step and largest increase
would occur on January 1, 2027 and the second small increase of approximately 2-7%
would go into effect once Well 12 goes online.
Paul Adamski explained that Joel provided the Commission a comparison of other
municipalities, not included in the packet, showing their long-term debt, number of
employees, # of customers, Total Utilities Plant, feet of mains etc.
Joel did discuss the rate comparisons that were included in the packet of neighboring
municipalities. With our current rate structure, we are below Wausau, Marshfield,
Wisconsin Rapids and Plover. With the proposed rate increases, we would still be
below Wausau and Marshfield and almost even with Wisconsin Rapids. These
comparisons are for water and sewer, because not all municipalities have storm. Joel
did include monthly averages for residential customers for water and sewer in the
packet after both increases. Pointing out an average family of 4 using 2500 cubic feet of
water, their bill monthly would average $100 and for 2 people using 1300 cubic feet
their monthly bill would average $70 per month.
Anna asked since the increase was approved by the PSC, what our relationship is with
the PSC in regard to the Commission not approving the rate increase. Joel explained
we would have to enter into a contested rate case. This has never been done in the City
of Stevens Point. She is concerned because of how large the increases are.
Joel explained his handout showing the feet of mains in the system from 2021 to 2025.
Our replacement rate is close to averaging 1%. Since 2016, we have increased the
replacement rate. If we are not at 1%, we would be implying our infrastructure would
last more than 100 years. We have grown an average of 0.67% in terms of
subdivisions, East Park Commerce Center etc.
Our last full rate case was in 2018. When a full rate case is completed, the 5 years after
that, you are allowed to do simplified rate cases. In 2025, we realized we were no
longer eligible to do another simplified rate case, which is what prompted the full rate
case. Since our last full rate increase, our total plant/assets have increased by ten
million dollars.
Jeff Bushman asked if we could do the rate increases over a three-year period of time?
Joel stated we did make the request to the PSC and it was denied. We were asking to
evenly distribute Step 1 and Step 2 and it was denied.
Paul stated we did the best we could to make it less painful for the customers, but we
can't really second guess the PSC.
Motion made by Carl Rasmussen, seconded by Ray Schmidt to approve the rates for
the water utility as described in Appendix C of the final decision issued by the PSC
related to docket 5690-WR-110, approval of a sewer rate increase of 29% as supported
by the Baker Tilly analysis provided, and a storm rate increase of 45% as determined is
needed by staff to meet the debt service coverage ratio.
Ayes all. Nays none. Motion carried.
5. To award the bid of Well 12 and Water Treatment Plant Upgrades - Joel
Lemke
Page 142 of the packet has a summary of the open bid results of the well 12 building
and the treatment plant improvements at the former well 4 building. Low bid came in
from Ellis Construction. Staff is recommending we award the bid with those deducts at
$3,656,655.00 with the base bid plus the 15% contingency.
Joel explained how we are using the additional generators from Well 11 for this project,
and he also explained how the bidding is done all online now.
Completion date is looking to be the end of 2027.
Motion made by Ray Schmidt, seconded by Anna Haines, to approve Ellis Construction
with both deducts in for an amount of $3,179,700.00 plus the 15% contingency with an
amount not to exceed $3,656,655.00.
Ayes all. Nays none. Motion carried.
6. Water Supply and Distribution Reports - Eric Southworth
Eric stated our triannual lead and copper sampling program was completed at the end
of September. We had no high lead and copper sample results. Eric will compile the
results to share with the Commission at the November meeting.
7. Sewage Treatment Operations Report - Chris Lefebvre
The Commission reviewed the letter and sewage treatment plant reports that were
included in the packet. One of the two lift stations are almost complete. Anna asked
why we went over the limit for suspended solids. Joel explained as part of the
construction for the influent screw pumps, we had to use a different pump for awhile.
They did anticipate that happening.
8. Construction and Maintenance Report - Shane Kohnen
Shane had nothing else to add to the report included in the packet.
9. Directors Report - Joel Lemke
Joel mentioned Items 4 and 5 of the agenda are on the agenda for Council tonight
because of the timing of the meeting this month. Joel will be reading off the minutes
with the action of Commission at Council.
10. Adjournment.
Motion made by Ray Schmidt, seconded by Jeff Bushman to adjourn the meeting.
Ayes all. Nays none. Motion carried.
Time: 12:29 P.M.