Updates and Procurement Plan:
1) Phase 1 of the Portage County Courthouse Remodel
2) Jail and Law Enforcement Center
June 2, 2026
Agenda
• Scope
• Estimated Cost
• Schedule
• Decision Points
Courthouse Remodel – Phase 1
• Approved Project Budget
• Schedule
• Bid Packages
• Decision Points
Jail/LEC
Courthouse
Remodel –
Phase 1
• Branch Court AV Upgrades
• Entrance Improvements
(Single Point of Entry)
• Family Court
• Register in Probate
Initial Scope
Branch Court
AV Upgrades
Scope
• New Monitors, Microphones, Speakers & Supporting Tech.
Estimated Cost
• $550,000
Schedule
• Branch 1 – Wk of Aug 3rd 2026
• Branch 2 – Wk of Aug 10th 2026
• Branch 3 – Wk of Aug 17th 2026
*Portage Facilities completing supporting work
Decision Point
• EPA (AV Contractor) Contract approved on May 5th, 2026
Entrance
Improvements
(Single Point
of Entry)
Scope
• New scanner, interior vestibule, door hardware,
window film.
Estimated Cost
• $450,000
Schedule
• Aug 2026 through Sept 2026 (pending material
availability)
Decision Point
• County Board Approval – 6/16/2026
Family Court
Scope
• New courtroom, judges chamber, modified conference
space
Estimated Cost
• $820,000
• Value engineering still happening
Schedule
• Design Documents – 6/30/2026
• Bidding/Procurement – July 2026
• Construction - Nov 2026 through Jan 2027 (pending
material availability)
Decision Point
• County Board Approval – 8/18/2026
Register in
Probate
Removed from this project
Facilities Dept is developing a
better solution that will utilize
space vacated by Steven Point
Courthouse
Projects –
Phase 1
Final Scope
• Branch Court AV Upgrades
• Entrance Improvements (Single Point of Entry)
• Family Court
Estimated Costs
$550K (Branch Court AV)
$450K (Entrance Improvements)
$820K (Family Courts)
$1,820,000
Decision Points
• Entrance Improvement - County Board Approval – 6/16/2026
• Family Court - County Board Approval – 8/18/2026
On to the Jail/LEC
Jail/LEC
Agenda
•Approved Project Budget
•Schedule
•Bid Packages
•Decision Points
Jail/LEC
Jail/LEC
$121M Construction (Findorff)
+ $34M Soft Costs (Owner Direct)
$155M Total Project Budget
Approved Project Budget
Jail/LEC
Design Phase: In Progress
Start Construction: August 2026
Testing/Training: Aug 2028 - Oct 2028
Relocation & Occupancy: Fall 2028
Schedule
Jail/LEC
BP#1 – Precast Concrete Walls (Bid w/ true-up)
BP#2 – Mass Grading (Bid w/ true-up)
BP#3 – Critical Contractor Early Procurement (RFP w/
true-up)
BP#4 – Footings & Foundations (Bid w/ true-up)
BP#5 – Final Construction Documents (Bid & Finalize
true-ups)
Bid Packages
Jail/LEC
BP#1 – GMP#1 to Board: $3.5M 6/16/26
(Precast Concrete Walls )
BP#2 – GMP#2 to Board: +$5.5M 8/18/26
(Mass Grading)
BP#3 – GMP#3 to Board: +$36M 9/15/26
(Critical Contractors)
BP#4 – GMP#4 to Board: +$20M 10/20/26
(Footings & Foundations)
BP#5 – GMP#5 to Board: +$56M 3/16/27
(Final Construction Documents)
Total Construction: $121M
Decision Points
*GMP = Guaranteed Maximum Price
(Final Construction Documents)
(Precast Concrete Walls )
(Mass Grading)
(Critical Contractors)
(Footings & Foundations)
Preliminary Jail / LEC Schedule
Activity Dates
Oct Nov Dec Jan Feb Mar Apr May JuneJuly Aug SeptOct Nov Dec Jan Feb Mar Apr May JuneJuly Aug SeptOct Nov Dec Jan Feb Mar Apr May JuneJuly Aug SeptOct Nov Dec Jan Feb Mar Apr May JuneJuly Aug SeptOct Nov Dec
Presentation Oct-25
Approval to Proceed Nov-25
Contracting Dec-25
Design Development Process Jan-26 to Jul-26
Guaranteed Maximum Price Package 1-
4 (to board) Jun 26-Oct 26
Construction Document Design Process Jan-26 to Apr-26
100% Construction Docs (Package 5) Feb-27
Guaranteed Maximum Price 5 (to board) Mar-27
Construction Duration Aug-26 to Jul-28
Commissioning/Testing/Training Aug-28 to Oct-28
Occupancy Oct/Nov-28
If We Wait to Do Only 1 Bid Package Mar-27 ------------------Extended Construction Timeline If Wait---------------------------
Preliminary Jail/LEC Schedule - 6/1/2026
2025 2026 2027 2028 2029
Who has the first