Any person planning to attend this meeting who needs some type of special accommodation to participate should call the
County Clerk’s Office at 715-261-1500 or e-mail countyclerk@co.marathon.wi.us one business day before the meeting.
CENTRAL WISCONSIN JOINT AIRPORT BOARD MEETING AGENDA
Conference Room B – East Terminal Upper Level, Mosinee, Wisconsin
April 14, 2026 - 8:00 a.m.
2024-2026 Board Members: Chair Chris Dickinson - Marathon County, Vice Chair Julie Morrow - Portage
County, Dave Ladick - Portage County, Tom Seubert - Marathon County, Kurt Kluck - Marathon County, Rick
Rettler - Portage County, Nicholas Endres - Marathon County
Mission Statement: Provide premier access to the world through aviation and be a catalyst for economic growth
in our
communities. Vision Statement: To be the airport of choice for central and northern Wisconsin.
The monthly meeting of the Central Wisconsin Joint Airport Board will have the option for members and the
publi
c to call-in via telephone conference. Airport Board members and the public may join the meeting by
calling 1-469-480-4192 and enter Conference ID 586 086 871#. The conference line will be open to calls five
(5) minutes prior to the meeting start time listed above.
1) Call to Order by Chair Dickinson at 8:00 a.m.
a) Pledge of Allegiance
2) Approval of Minutes of the March 10, 2026 Board Meeting
3) Public Comment Period: 15-minute time limit
4) Review and Possible Action on GA Apron Construction Engineering Services Contract
5) Review and Possible Action on Permanent Utility Easement with Wisconsin Public Service
6) Staff Reports
a) Director Report
i) Air Service Update
ii) Statistical Report
iii) Flight Schedule
iv) Legislative Update
b) Financial Reports
i) Revenues and Expenses
ii) Budget Comparison
iii) PFC Update
c) Operations and Project Reports
i) Update on Airport Projects
ii) Update on Airport Operations
iii) Triennial Full-Scale Emergency Exercise – May 21, 2026
7) Ovation
a) Fixed Base Operator Report
8) Next Scheduled Meeting Date: May 12, 2026 at 8:00 a.m.
9) Adjournment
01
CENTRAL WISCONSIN JOINT AIRPORT BOARD MEETING MINUTES
CENTRAL WISCONSIN AIRPORT TERMINAL
Conference Room B – East Terminal Upper Level, Mosinee, Wisconsin
March 10, 2026 - 8:00 a.m.
Airport Board: Chris Dickinson, Chair – via Teams J ulie Morrow, Vice Chair
Dave Ladick Kurt Kluck – via Teams
Rick Rettler Th omas Seubert
Nicholas Endres - Absent
Staff: Brian Grefe, Airport Director Mark Cihlar, Assistant Airport Director
Dave Drozd, Finance Director J ulie Ulrick, Badging Coordinator
Visitors: Karl Kemper, Becher Hoppe Josh Harris, Ovation
Collin Eiden, Ovation Trisha Sirny, Wausau West HS Advisor
Alison Iaffaldano, Wausau West HS Student Jim Fredericksen, CWA Operations
Handouts: February Statistical Report
Call to Order: Meeting called to order by Vice Chair Morrow at 8:00 a.m.
Approval of Minutes: Motion by Ladick, second by Rettler to approve the minutes of the February 10, 2026 board
meeting. Motion carried unanimously.
Public Comment Period: None.
Review and Possible Action on Wausau FCCLA Art Selection:
This will be year two of a four-year agreement with the Wausau School District to display a student art installation at
CWA called “Art in Flight”. Wausau East and Wausau West High Schools both brought in their top nine pieces of
artwork for the board to choose from. Board members selected four pieces of art from each school. The selected
artwork will be professionally framed and prepared for installation. A public unveiling will be scheduled, with
students and their families, school staff members, members of the community and local media outlets invited to
attend.
8:16am Dickinson left the meeting.
Review and Possible Action on ARFF/SRE Preliminary Design Contract:
CWA staff began working with Woolpert several months ago to develop a detailed scope of work for preliminary
design of the recently approved Airport Rescue and Fire Fighting/Snow Removal Equipment (ARFF/SRE) facility. The
FAA and BOA previously agreed that an approximate 30% preliminary design effort would be necessary to answer
many of the outstanding questions needed to develop accurate cost estimates, evaluate federal and state funding
eligibility, and submit necessary environmental review documentation to the FAA before the airport moved into the
full design effort. Contract negotiations with Woolpert, the airport’s on-call architectural consultant, are complete.
The cost of the preliminary design contract is $239,162.55 and is eligible for federal reimbursement at a prorated
amount. Reimbursement would likely take place in 2027 as part of a future full-design effort. Motion by Ladick,
second by Seubert to approve Task Order No. 2 with Woolpert in the amount of $239,162.55 for preliminary design
of the ARFF/SRE facility. Motion carried unanimously.
Staff Reports:
Director Report – Brian Grefe:
Air Service Update – American dropped back to two daily flights through the second week in April, then returning to
02
three daily flights throughout the summer. Staff have had positive talks with Delta on the possible return of the
Detroit flight, after their preferred addition of a third Minneapolis flight.
Statistical Report – The February statical report shows total operations up 5.6% on the month, up 3.9% on the year.
ATCT operations were up 25.4% on the month, up 18.1% on the year. Enplanements ended the month with a 21.6%
increase and an increase of 23.2% for the year. Load factors ended with American at 77.2% and Delta at 79.5%.
Flight Schedule – There are four daily flights scheduled through March, with three casino charters coming up. Staff
have an upcoming air service development conference and meetings are scheduled with Delta, United, American,
Sun Country and Avelo, with a few more meeting requests awaiting confirmation.
Legislative Update – The House of Representatives failed to approve the Senate-passed Rotorcraft Operations
Transparency and Oversight Reform (ROTOR) Act. The ROTOR Act would establish new requirements for the
utilization of ADS-B technology by virtually all aircraft and helicopters and increase oversight of commercial and
helicopter traffic and flight routes near airports. DHS funding has still not been approved and local TSA staff are not
getting paid.
Financial Reports – Dave Drozd:
Revenues and Expenses – February revenues end at 12.08% of budget, with expenses ending at 12.03%. Parking
revenues continue to increase, with substantial increases expected when United flights begin. Staff are looking into
converting the employee parking lot into a revenue lot to increase parking capacity, if needed. The west parking lot
needs substantial work prior to being reopened.
Budget Comparison – The budget comparison report shows revenues $2,146 over expenses year-to-date.
PFC Update – None.
Operations & Project Reports – Mark Cihlar:
Update on Airport Operations – The old Rescue 1 fire truck has been listed on the Wisconsin Surplus Auction website
while still in use. Once the new truck arrives and staff have been trained, Rescue 1 will be put out of use.
Update on Airport Projects – The GA Apron project will go out to bid this week. The next project up is the GA Access
Road Reconstruction project, which will go out to bid soon.
Ovation – Fixed Base Operator Report:
February fuel sales were up 5% over last year. They have an accepted offer for the open A&P mechanic position,
with services expected to start by May 1st. The individual has 15 years of experience and should be a good fit with
their organization.
Next Scheduled Meeting Date: April 14, 2026 at 8:00 a.m.
Adjournment: 9:00 a.m. Meeting called to adjourned by Vice Chair Morrow.
_______________________________________
Julie Ulrick, Recording Secretary
03
Agenda Item Summary
Airport Board Meeting Date: April 14, 2026
Agenda Item Title: #4) Review and Possible Action on GA Apron Construction Engineering Services Contract
Staff Responsible: Mark Cihlar, Assistant Airport Director
Background: The asphalt pavement that serves as the General Aviation (GA) Apron is at the end of life and is in need of
improvement through reconstruction or major rehabilitation. This area is important to improve because of the planned
use in this area with the new GA Terminal and GA Transient Hangar. In May of 2025, the Central Wisconsin Joint Airport
Board approved the following: 1) A resolution the use 2026 AIP Entitlement funding for a project in this area, and 2) A
preliminary design contract to complete FAA project formulation and environmental review. In September of 2025, the
board approved a final design contract with Becher Hoppe Associates to have the project bid out in time for a 2026 AIP
grant request.
Airport staff worked with Becher Hoppe to scope and negotiate a contract for the necessary engineering oversight
required during construction of the project. The recommended contract with Becher Hoppe has been negotiated in good
faith in accordance with FAA AC 150/5100-14E. The record of negotiations for this contract is attached to this Agenda
Item Summary. This contract, along with the previously approved Preliminary Design and Final Design contracts for this
project, are all AIP eligible project costs.
The Wisconsin DOT Bureau of Aeronautics (BOA) opened bids for the project on April 2, 2026, and is preparing the final
grant application paperwork to submit to the FAA.
Timeline: If approved by the board, the contract cost will be included in the final grant application, and work on this
contract will begin after the grant is awarded. Construction is anticipated to begin in August of 2026.
Financial Impact: The construction engineering services contract has a total cost of $314,370.29. See attached Record of
Negotiations. This amount is eligible for state and federal funding under the grant.
The low bid on the project was submitted by Earth Inc., with a total construction cost of $2,486,853.00. This puts the
total cost of the project $3,013,141. This amount includes design, construction engineering services, and BOA
administrative expenses. This total cost will be funded 95% with AIP funding, 2.5% with state funds, and CWA’s 2.5%
share of the project will be $75,329. This amount is eligible to be paid for with PFC funds.
Through the preliminary design effort, airport staff requested support from the FAA to leverage CWA’s future 2027 AIP
Entitlement funding for this project through a single, multi-year grant in 2026, allowing the project to be constructed in
one construction season. This approach was taken because of the significant cost savings through improved
constructability and reduced design effort compared to bidding the project in two phases over two construction seasons.
Although the actual cost savings cannot be known, this approach resulted in an unexpected opportunity for the airport.
At this time, the FAA has indicated that this project has been included on the list for 2026 AIP Discretionary funding, and
the project is anticipated to be fully funded with 2026 AIP funding. This is an additional $1,562,484 of project funding
that CWA will receive, and CWA’s 2027 AIP Entitlement funding will remain available for future projects.
04
Agenda Item Summary
Contributions to Airport Goals: This final design contract supports the 2025 Airport Goals to Enhance General Aviation
and Improve and Maintain Facilities, and is consistent with the 2023 Terminal Area Master Plan.
Recommended Action: Airport staff recommend approval of the Construction Engineering Services contract with Becher-
Hoppe Associates.
Attachments: Scope of Work, Fee Proposal, and Record of Negotiations
05
Page 1 of 5
ATTACHMENT A
Scope of Services
Central Wisconsin Airport
Mosinee, WI
General Aviation Apron Reconstruction
CWA1022
Construction Engineering Services
March 27, 2026
PROJECT DESCRIPTION
This project includes improvements to the Central Wisconsin Airport in Mosinee,
Wisconsin. The project consists of the following:
Base Bid: Reconstruct Central Apron & Rehabilitate Taxilane 3 and Eastern
Portions of General Aviation Apron
Alternate Bid #1: Reconstruct Taxilane 3 within General Aviation Apron
Alternate Bid #2: Reconstruct Portion of Eastern General Aviation Apron
This scope is for engineering services associated with the construction phase of the
project. The specified time for construction substantial completion is 45 working days.
Construction is anticipated to start in August 2026. Based on the WisDOT Federal
Development Manual (FDM), the percentage factor for probable working days is ~70%
of possible working days for the majority of the project work. Using this percentage, it is
probable that 45 working days would be expired after 65 possible working days.
Additionally, it is estimated that there will be 5 non-working days during concrete curing
periods, where work on non-controlling items will take place. From these estimates, our
level of effort is based on a minimum of 70 weekdays (14 weeks) of on-site construction
oversight. 12 hour working days are included for our RPR for 45 of the 70 days. 8 hour
working days are included for our RPR for 25 of the 70 days. Additionally, 5 nights
worth of work are anticipated to take place during Phase 8.
06
Page 2 of 5
The following scope of services has been developed to accomplish the goals for this
project:
SCOPE OF SERVICES
I. LUMP SUM ITEMS
1. Pre-Construction Tasks
a. Scoping/Preliminary Coordination: Consultant will coordinate with the
BOA, contractor, sub-consultants, and internally to estimate scoping items
such as timeline, required tasks, and appropriate staffing for the project.
b. Erosion Control Implementati on Plan (ECIP) Coordination: Consultant
will review the ECIP and coordinate with the contractor to develop the
ECIP to the point where it’s ready for DNR and BOA review and comment.
Consultant will follow up with contractor to ensure that DNR and BOA
comments are addressed..
c. Obtain/Review Construction Schedule: Consultant will review the
contractor’s initial schedule for compliance with project specifications and
airport operations. Consultant will coordinate with contractor and airport
manager to modify schedule as required to meet project specifications and
accommodate airport operations.
d. Coordinate, Prepare, Conduct, Document Pre-Construction Meeting:
Consultant will coordinate, prepare for, conduct, and document a pre-
construction meeting at the airport.
e. Safety Plan Compliance Do cument (SPCD) Coordination: Consultant
will review the contractor’s SPCD and coordinate with the contractor to
develop the SPCD to the point where it’s ready for BOA review and
approval/comment. Consultant will follow up with contractor and BOA to
ensure that the SPCD approval is formalized.
f. Prepare Digital Terrain Models (DTM): Consultant will prepare and
provide DTMs to the contractor to be used for GPS machine grading.
2. Construction Management Program (CMP): Consultant will prepare a CMP in
accordance with FAA AC 150/5370-12B, Appendix A.
3. Airport Layout Plan Package: Not included in scope.
4. Initial Constructi on Layout and Control: Consultant will provide slope staking
and control prior to start of construction items of work. Setting control involves
setting irons around the perimeter of the project at ~400’ intervals with horizontal
coordinate information, then running a level loop through all of the control points.
Slope staking involves providing stakes near the slope intercept at each station,
07
Page 3 of 5
and providing cut/fill information to station features as requested by the
contractor.
5. Record Drawings: Consultant will prepare record drawings in Adobe (.pdf)
format to represent as-built conditions of the project.
II. COST PLUS FIXED FEE ITEMS
1. Management Engineering:
a. Project Preparation: Consultant will prepare templates for the
documents and tools utilized during construction, including:
Pay estimates
Daily progress reports
Weekly progress reports
Submittal log
Material submittal checklist
Weekly meeting agendas
Item record account worksheets
Erosion control inspection worksheets
Construction GPS setup
b. Project Coordination: Consultant will provide professional engineering
services as required to monitor project progress and resolve issues.
c. Interpret Plans and Specifications: Consultant will assist contractor with
interpreting plans and specifications. Internally, the project manager will
introduce resident project engineers/representatives to the project.
d. Supervise Sub-Consultants: Consultant will supervise and coordinate
with sub-consultants.
e. Review Shop Drawings, Submittals, and Quality Control Plans:
Consultant will review submittals for all materials incorporated into the
project for general conformance with project specifications.
f. Pay Estimates/Variation in Quantities: Consultant will tabulate quantities
during construction and review with the Contractor weekly. Consultant will
prepare periodic pay estimates duri ng construction, provide to the
contractor for approval, present to Sponsor for approval, and submit to BOA
for payment. Consultant will also submit any requested variation in
quantities information after the project is completed.
g. Weekly Progress Reports: Consultant will complete weekly progress
reports to include:
Weekly dollar amount of work completed
Progress of major items
Engineering daily labor amounts
08
Page 4 of 5
Daily summary of work , personnel, and equipment.
h. Weekly Meeting Agendas & Minutes: Consultant will prepare and transmit
the previous week’s meeting minutes and the following week’s meeting
agenda each week.
i. Prepare Change Orders: Consultant will pr epare change orders as
necessary.
j. Consultation with Owner: Consultant will keep the Airport informed
throughout the project and answer questions from the Airport as requested.
k. Final Inspection/Acceptance: Consultant will organize and provide record
of a final project inspection, and coordinate acceptance. After the
inspection, Consultant will transmit mi nutes of the final inspection meeting
and verify completion of any remaining punchlist items.
l. Monitor/Review Testing Work: Consultant will review Contractor QC
testing and Engineering QV testing work performed, and verify that test
results meet project specifications.
m. Project Acceptance and Closeout: Consultant will work with the Airport,
BOA, and contractor to resolve outstanding issues and close out the project.
2. Construction Engineering
a. Construction Staking: Consultant will perform all layout and staking per
project specifications. Anticipated staking tasks include:
i. Phasing limits
ii. Object free areas
iii. Removals/sawcuts
iv. Erosion control
v. Ducts
vi. Subgrade
vii. Underdrains
viii. Subbase 12” minus
ix. Subbase 3” minus
x. Cement treated permeable base
xi. Concrete pavement
xii. Base course/asphalt
xiii. Tie downs
xiv. Pavement markings
b. Construction Oversight
i. On-Site Representatives: Consultant will provide full-time
construction observation as de scribed above in the Project
09
Page 5 of 5
Description. The main tasks perfo rmed by the representatives will
include:
Observe and photograph construction operations
Verify compliance with project specifications
Coordinate miscellaneous field adjustments
Measure quantities
Conduct traffic control inspections
Conduct erosion control inspections
Coordinate testing
Prepare daily progress reports
Prepare weekly progress reports
Prepare pay estimates
Stakeholder coordination
ii. Project Manager Site Visits/Meetings: The project manager and/or
assistant project manager will typically visit the site at least weekly
to observe construction progress and conduct weekly progress
meetings. Additional site visits during critical construction phases
including subgrade preparation, ce ment treated base placement,
concrete paving, asphalt paving, and phasing transitions are
anticipated.
c. Testing: Subconsultant American Engineer ing Testing, Inc. (AET) will
provide material testing services as described in Attachment C.
Project Manager: Karl Kemper, PE will be the project manager. Kevin Hahn, PE will
be the assistant project manager.
Resident Project Representative(s): Sean Sailer, EIT is anticipated to be the full-time
on-site representative. Kevin Bella is anticipated to provide part-time RPR support.
Other staff will provide additional support as needed.
DBE Goal: The DBE goal is N/A for this project.
Wage Rates: We have used our 2026 wage rates and 2026 IRS mileage and per diem
rates to prepare the fee proposal. If construction occurs after 2026, updated rates will
need to be accounted for in the contract.
Overhead & Profit: We have used our audited 2024 overhead rate of 179.14% and an
11% profit factor to prepare this proposal.
If additional effort is required for construction services, any amendment for additional
services will include additional fixed fee.
P:\2024\2024.035 - BOA - CWA GA Apron\Admin\Contracts - Working\Construction\CWA GA Apron_Construction Services_Attachment
A_Scope.docx
10
Becher‐Hoppe Associates, Inc.
COST PRICE ANALYSIS WORKSHEET
ATTACHMENT B ‐ FEE ESTIMATE
CONSTRUCTION ENGINEERING SERVICES
Page 1 of 1
WisBOA/FAA Funded Projects AIRPORT: Central Wisconsin Airport
2026 Wage Rates PROJECT NUMBER : CWA1022 PREPARED BY: KRK
2024 DOT O/H Rates PROJECT DESCRIPTION: GA Apron Reconstruction CHECKED BY:
DATE: 3/31/26 rev 1 APPROVED BY:
E S T I M A T E D H O U R S
STAFF Project Project RPR RPR Surv Surv Resource Tech. Direct Direct + Mat'ls Vehicle Drone Robotic GPS Total CONSULTANT PROFIT ON SUM OF PROPOSED
CLASSIFICATION Engr. III Engr. I Crew Crew Manager Assist TOTAL Labor G&A Overhead Supplies miles Total (hr) Actual COSTS ITEMS 1& 2 ALL COST CONTRACT
& WAGE RATES =======> (Karl) (Kevin H) (Sean) (Kevin B) Chief Asst (Matt) (Jodi) HOURS Costs 179.1400% 0.725$ $100 $40 $40 Lodging Meals Costs 11% ITEMS AMOUNT
No. WORK ELEMENT 12 3 4 a 4 b 4 c 4 d 4 e 4 f 45 6 1 ‐6 NO.
I. LUMP SUM ITEMS
1 PRE‐CONSTRUCTION TASKS:
a Scoping/Prelim Coord 32 8 4 8 52 hr. 3,054.24$ 5,471.37$ ‐$ 937.82$ 9,463.43$
b ECIP Coord 11 6 4 4 25 hr. 1,090.54$ 1,953.59$ ‐$ 334.85$ 3,378.98$
c Obtain/Review Constr Schedule 184 4 17 hr. 699.10$ 1,252.37$ ‐$ 214.66$ 2,166.13$
d Prepare, Conduct, Doc't Pre‐Con Mtg 91 2 6 6 33 hr. 1,554.00$ 2,783.84$ 40 76.00$ 105.00$ 477.16$ 4,920.00$
e SPCD Review and Coordination 182 2 13 hr. 578.96$ 1,037.15$ ‐$ 177.77$ 1,793.88$
f Prepare DTMs 12 12 hr. 587.16$ 1,051.84$ ‐$ 180.29$ 1,819.29$
Pre‐Construction Subtotal 44.0 64.0 16.0 16.0 4.0 ‐ ‐ 8.0 152 hr. 7,564.00$ 13,550.16$ ‐$ 40 mi. ‐ ‐ 0 hr. ‐$ 76.00$ 105.00$ $0.00 2,322.55$ 23,541.71$
2 CONST INSPCT MGMT & REPT PRGRM: 11 63 2 8 57 hr. 1,882.82$ 3,372.88$ ‐$ 578.13$ 5,833.83$
Const Insp Mgmt Subtotal 1.0 16.0 32.0 8.0 ‐ ‐ ‐ ‐ 57 hr. 1,882.82$ 3,372.88$ ‐$ 0 mi. ‐ ‐ 0 hr. ‐$ ‐$ ‐$ ‐$ 578.13$ 5,833.83$
3 AIRPORT LAYOUT PLAN PACKAGE: 0 ‐$ ‐$ ‐$ ‐$ ‐$
ALP Package Subtotal ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 0 hr. ‐$ ‐$ ‐$ 0 mi. ‐ ‐ 0 hr. ‐$ ‐$ ‐$ ‐$ ‐$ ‐$
OTHER TASKS:
4 Initial Construction Layout/Control/Slope Staking 22 4 24 1 51 hr. 2,197.04$ 3,935.78$ 25.00 $ 100 14 2 76.00$ 788.50$ 674.61$ 7,620.93$
5 Record Drawings 1 4 16 4 25 hr. 779.38$ 1,396.18$ ‐$ 239.31$ 2,414.87$
Other Tasks Subtotal 1.0 6.0 16.0 4.0 24.0 24.0 1.0 ‐ 76 hr. 2,976.42$ 5,331.96$ 25.00 $ 100 mi. ‐ 14 2 hr. ‐$ 76.00$ 788.50$ ‐$ 913.92$ 10,035.80$
TOTAL LUMP SUM AMOUNT 46.00 86.00 64.00 28.00 28.00 24.00 1.00 8.00 285.00 hr. 12,423.24$ 22,255.00$ 25.00 $ 140 mi. ‐ 14 2 hr. ‐$ 152.00$ 893.50$ ‐$ 3,814.60$ 39,411.34$ 39,411.34$
% OF TOTAL HOURS 16.1% 30.2% 22.5% 9.8% 9.8% 8.4% 0.4% 2.8% 100.0% cross check 39,411.34$
II. ACTUAL COST ITEMS
1 MANAGEMENT ENGINEERING:
a Project Preparation 1 2 40 2 45 hr. 1,159.38$ 2,076.91$ ‐$ 355.99$ 3,592.28$
b Project Coordination 16 16 32 hr. 1,860.96$ 3,333.72$ ‐$ 571.41$ 5,766.09$
c Interpret plans and specifications 21 21 6 4 34 hr. 1,238.20$ 2,218.11$ ‐$ 380.19$ 3,836.50$
d Supervise Sub‐Consultants 21 6 18 hr. 917.64$ 1,643.86$ ‐$ 281.77$ 2,843.27$
e Review shop dwgs/submittals 41 64 0 1 6 76 hr. 2,565.52$ 4,595.87$ ‐$ 787.75$ 7,949.14$
f Pay estimates/ variation in quantities 21 0 8 8 28 hr. 1,104.62$ 1,978.82$ ‐$ 339.18$ 3,422.62$
g Weekly Progress Reports 43 4 38 hr. 1,933.14$ 3,463.03$ ‐$ 593.58$ 5,989.75$
h Weekly Meeting Agendas and Minutes 43 4 38 hr. 1,933.14$ 3,463.03$ ‐$ 593.58$ 5,989.75$
i Prepare change orders 41 6 20 hr. 1,052.40$ 1,885.27$ ‐$ 323.14$ 3,260.81$
j Consultation w/ Owner 17 17 34 hr. 1,977.27$ 3,542.08$ ‐$ 607.13$ 6,126.48$
k Final inspection/acceptance 91 2 6 6 33 hr. 1,554.00$ 2,783.84$ 40 76.00$ 105.00$ 477.16$ 4,920.00$
l Monitor/review testing work 21 6 18 hr. 917.64$ 1,643.86$ ‐$ 281.77$ 2,843.27$
m Project Acceptance and Closeout 41 64 0 8 68 hr. 2,268.96$ 4,064.61$ 160 116.00$ 696.69$ 7,146.26$
Construction Management Subtotal 71.0 217.0 150.0 44.0 ‐ ‐ ‐ ‐ 482 hr. 20,482.87$ 36,693.01$ ‐$ 200 mi. ‐ ‐ 0 hr. ‐$ 76.00$ 221.00$ ‐$ 6,289.34$ 63,686.22$
2 CONST. ENGINEERING:
a CONSTRUCTION STAKING:
i Phasing limits 18 6 15 hr. 661.81$ 1,185.57$ 25.00 $ 50 5 38.00$ 274.25$ 203.21$ 2,349.84$
ii Object free areas 13 2 6 hr. 270.11$ 483.88$ 25.00 $ 1 40.00$ 82.94$ 901.93$
iii Sawcuts/Removals 13 2 6 hr. 270.11$ 483.88$ 25.00 $ 1 40.00$ 82.94$ 901.93$
iv Erosion Control 0 hr. ‐$ ‐$ ‐$ ‐$ ‐$
v Ducts 0 hr. ‐$ ‐$ ‐$ ‐$ ‐$
vi Subgrade 22 0 16 38 hr. 1,664.66$ 2,982.07$ 25.00 $ 100 14 76.00$ 708.50$ 511.14$ 5,891.37$
vii Underdrains 28 6 16 hr. 710.74$ 1,273.22$ 25.00 $ 50 5 38.00$ 274.25$ 218.24$ 2,501.45$
viii Subbase 12" minus 22 0 16 38 hr. 1,664.66$ 2,982.07$ 25.00 $ 100 14 76.00$ 708.50$ 511.14$ 5,891.37$
ix Subbase 3" minus 22
0 16 38 hr. 1,664.66$ 2,982.07$ 25.00 $ 100 14 76.00$ 708.50$ 511.14$ 5,891.37$
x Cement treated permeable base 21 0 8 20 hr. 881.26$ 1,578.69$ 25.00 $ 50 7 38.00$ 354.25$ 270.59$ 3,109.79$
xi Concrete pavement 22 0 16 38 hr. 1,664.66$ 2,982.07$ 25.00 $ 100 14 76.00$ 708.50$ 511.14$ 5,891.37$
xiii Base course/asphalt 23 6 32 70 hr. 3,028.82$ 5,425.83$ 25.00 $ 200 30 190.00 $ 1,535.00$ 930.01$ 10,944.66$
xiii Tie downs 21 0 8 20 hr. 881.26$ 1,578.69$ 25.00 $ 50 7 38.00$ 354.25$ 270.59$ 3,109.79$
xiv Pavement markings 13 2 6 hr. 270.11$ 483.88$ 25.00 $ 50 1 38.00$ 114.25$ 82.94$ 976.18$
Construction Staking sub‐total ‐ 20.0 ‐ ‐ 161.0 130.0 ‐ ‐ 311 hr. 13,632.86$ 24,421.92$ 300.00 $ 850 mi. ‐ 106.0 7 hr. ‐$ 684.00$ 5,820.25$ ‐$ 4,186.02$ 48,361.05$
b CONSTRUCTION OVERSIGHT:
i Resident Project Representatives 900 302 1202 hr. 31,895.14$ 57,136.95$ 200.00 $ 4200 70 3,875.00$ 9,720.00$ 9,793.53$ 108,745.62$
ii Project Manager Site Visits/Weekly Meetings 42 84 126 hr. 6,940.08$ 12,432.46$ 680 646.00$ 1,139.00$ 2,130.98$ 22,642.52$
Construction Engineering Subtotal 42.0 84.0 900.0 302.0 ‐ ‐ ‐ ‐ 1328 hr. 38,835.22$ 69,569.41$ 200.00 $ 4880 mi. ‐ ‐ 70 hr. ‐$ 4,521.00$ 10,859.00$ ‐$ 11,924.51$ 131,388.14$
c TESTING:
American Engineering Testing (AET) 22 4 hr. 210.76$ 377.56$ ‐$ 30,870.50$ 64.72$ 31,523.54$
Testing Subtotal 2.0 ‐ ‐ ‐ ‐ ‐ ‐ 2.0 4 hr. 210.76$ 377.56$ ‐$ 0 mi. ‐ ‐ 0 hr. ‐$ ‐$ ‐$ 30,870.50$ 64.72$ 31,523.54$
TOTAL ACTUAL COST AMOUNT 115.00 321.00 1050.00 346.00 161.00 130.00 0.00 2.00 2125.00 hr. 73,161.71$ 131,061.90$ 500.00 $ 5930 mi. 0 106 77 hr. ‐$ 5,281.00$ 16,900.25$ 30,870.50$ 22,464.59$ 274,958.95$ 274,958.95$
% OF TOTAL HOURS 5.4% 15.1% 49.4% 16.3% 7.6% 6.1% 0.0% 0.1% 100.0% cross check Fixed Fee 274,958.95$
LUMP SUM AMOUNT = 39,411.34$
ACTUAL COST AMOUNT = 252,494.36$
FIXED FEE AMOUNT = 22,464.59$
MAXIMUM COMBINED SUM = 314,370.29$
LABOR, OVERHEAD & PROFIT ACTUAL COSTS ‐ TRAVEL, MEALS, FIELD SUPPLIES, ETC.
P:\2024\2024.035 - BOA - CWA GA Apron\Admin\Contracts - Working\Construction\CWA GA Apron_Construction Services_Attachment B_Fee Negotiation
BOA CONSTRUCTION PROPOSAL new
REV 4-08 Printed on 3/31/2026
11
Mailing Address:
100 CWA Drive, Suite 227
Mosinee, WI 54455
Phone: 715-693-2147
Visit us at www.fly-cwa.org
Record of Negotiations:
Central Wisconsin Airport
Construction Engineering Services
Date: April 6, 2026
Contract Title: Construction Engineering Services – GA Apron Reconstruction/Rehabilitation
Location: Central Wisconsin Airport
Anticipated AIP Grant: TBD
1. In 2020, the Central Wisconsin Airport (CWA) conducted a competitive solicitation for Airport
Engineering Services through a Request for Qualifications (RFQ) in accordance with FAA
Advisory Circular 150/5100- 14E. This solicitation resulted in a five- year on- call engineering
agreement with Becher Hoppe Associates, inc., for projects beginning prior to August 31, 2025.
2. On May 13, 2025, the Central Wisconsin Joint Airport Board formally initiated the GA Apron
Reconstruction/Rehabilitation project by approving a preliminary design contract with Becher
Hoppe for the project . L ater, on September 9, 2025, the Board entered into a Final Design
Contract for the project with Becher Hoppe.
3. On March 12, 2026, the advertisement for bids was published with a bid opening scheduled for
April 2, 2026. In order to submit a grant application as soon as possible after bids were opened,
CWA informed Becher Hoppe that they would like to have the Construction Engineering contract
for the project negotiated before bid opening.
4. On March 27 , 202 6, Becher Hoppe provided CWA a draft scope of work and a blank fee
spreadsheet to use for preparing an Independent Fee Estimate (IFE) for the scope of work.
5. On March 30, 2026, CWA reviewed and discussed the scope of work with Becher Hoppe. After
clarifying a few questions about some of the assumptions, CWA agreed the scope of work was
reasonable. This work was included in the solicitation scope of the original RFQ.
6. On March 31, 2026, CWA staff with experience estimating and negotiating projects of similar
scope prepared an IFE for this scope of work. The IFE for the project estimated the total effort
required to complete the scope of work would have a total cost of $292,429.19. In accordance
with FAA AC 150/5100-14E, a fee proposal would be expected to be within 10% of this range, or
between $263,186 and $321,672.
7. On March 31, 2026, after preparing the IFE, CWA requested a fee proposal from Becher Hoppe
for the scope of work and received it later that day . CWA reviewed the proposal, which had a
total cost of $338,834.16. This amount was 15% higher than the IFE. Later that same day, CWA
discussed the proposal with Becher Hoppe. Becher Hoppe explained that their proposal included
enough effort in the actual cost items to account for a “worst case scenario” if additional effort
needed if there were delays or challenges with the project. Becher Hoppe noted that they have
12
Mailing Address:
100 CWA Drive, Suite 227
Mosinee, WI 54455
Phone: 715-693-2147
Visit us at www.fly-cwa.org
a strong record at CWA of finishing projects below the full contract ed amount on previous
projects. After further discussion, Becher Hoppe did agree that there may be additional
efficiencies gained on this project with Becher Hoppe staff working at the airport on multiple other
projects during the same timeframe. Becher Hoppe agreed to reduce the actual cost effort
included in the proposal.
8. On March 31, 2026, Becher Hoppe provided CWA a revised proposal for the scope of work with
a total cost of $314,370.29. This amount was 7.5% higher than the IFE.
9. On March 31, 2026, CWA finished reviewing the revised proposal and informed Becher Hoppe
that the fee was acceptable, and asked Becher Hoppe to prepare the contract for consideration
by the Central Wisconsin Joint Airport Board.
10. On April 14 , 202 6, CWA will recommend approval of the Construction Engineering Services
contract with Becher Hoppe , negotiated in good faith, to the Central Wisconsin Joint Airport
Board.
_____________________________
Mark Cihlar, AAE
Assistant Airport Director
13
Agenda Item Summary
Airport Board Meeting Date: April 8, 2026
Agenda Item Title: #5) Review and Possible Action on Permanent Utility Easement with Wisconsin Public Service
Staff Responsible: Mark Cihlar, Assistant Airport Director
Background: WPS has several utility easements on airport property. WPS recently requested another permanent utility
easement to provide utilities to the new Transient Hangar and to the new GA Terminal, both of which are currently
under construction.
The proposed utility easement is presented with a temporary exhibit identifying the approximate location of the
easement corridor. A final exhibit will be prepared after installation and registered on the property deed.
If approved by the Central Wisconsin Joint Airport Board, the easement will have to be signed by the Marathon County
Administrator and the Portage County Executive and returned to WPS who will record it with the deed of the property.
Timeline: WPS will be able to schedule installation of utilities to the hangar as soon as they receive the signed utility
easement.
Financial Impact: This easement has no financial impact to the airport.
Contributions to Airport Goals: This utility easement supports the 2025 Airport Goals to Enhance General Aviation and
Improve and Maintain Facilities.
Recommended Action: Airport staff recommends approval of Resolution R-02-26 for the Permanent Utility Easement
with WPS.
Attachment: Resolution R-02-26, Permanent Utility Easement
14
R-02-26
RESOLUTION
Central Wisconsin Airport Permanent Utility Easement
WHEREAS, Marathon County and Portage County, Wisconsin hereinafter referred to as the Joint
Airport Board, each being a municipal body corporate of the State of Wisconsin, is authorized by Wis.
Stat. §114.11 (1973), to acquire, establish, construct, own, control, lease, equip, improve, maintain, and
operate an airport, and
WHEREAS, the Joint Airport Board desires to develop or improve the Central Wisconsin Airport
(CWA), Marathon County, Wisconsin, and
WHEREAS, Wisconsin Public Service (WPS) provides electrical utility service to facilities located at
CWA, and
WHEREAS, WPS is adding new utility services to general aviation development on CWA property,
and
WHEREAS, the new utility locations are compatible with the intended use of CWA property as
identified in the airport master plan, and
NOW, THEREFORE, BE IT RESOLVED that the Central Wisconsin Joint Airport Board resolves and
ordains as follows:
Electric Underground Easement by and between the Joint Airport Board and Wisconsin Public Service
affecting Parcel Identification Number (PIN) 251-2707-342-9998 is hereby approved.
Dated this 14th day of April, 2026.
_________________________________________
Central Wisconsin Joint Airport Board Chair
15
3342679 Easement
THIS INDENTURE is made this ______ day of ______________,
______, by and between Marathon County, Wisconsin, and
Portage County, Wisconsin, municipal corporations, as joint
tenants, ("Grantor") and WISCONSIN PUBLIC SERVICE
CORPORATION, a Wisconsin Corporation, along with its
successors and assigns (collectively, "Grantee") for good and valuable
consideration, the receipt and sufficiency of which are hereby
acknowledged, Grantor, owner of land, hereby grants and warrants to,
Grantee, a permanent easement upon, within, beneath, over and across
a part of Grantor’s land hereinafter referred to as "easement area"
more particularly described as follows:
Part of the Northwest Quarter of the Northwest Quarter (NW
1/4 – NW 1/4) of Section 34, Township 27 North, Range 7
East, City of Mosinee, County of Marathon, State of
Wisconsin, as shown on the attached Exhibit “A”.
Return to:
Wisconsin Public Service Corp.
Real Estate Dept.
P.O. Box 19001
Green Bay, WI 54307-9001
Tax Parcel Identification Number
(PIN)
25127073429998
1. Purpose: ELECTRIC UNDERGROUND and GAS - The purpose of this easement is to construct, install,
operate, maintain repair, replace and extend underground utility facilities, conduit and cables, electric pad-
mounted transformers, manhole, electric pad-mounted vacuum fault interrupter, concrete slabs, power
pedestals, riser equipment, terminals and markers, together with all necessary and appurtenant equipment
under and above ground, as well as pipeline or pipelines with valves, tieovers, main laterals and service
laterals, together with all necessary and appurtenant equipment under and above ground, including cathodic
protection apparatus used for corrosion control, as deemed necessary by Grantee, for the transmission and
distribution of electric energy, signals, television and telecommunications services; natural gas and all by-
products thereof, or any liquids, gases, or substances which can or may be transported or distributed through
a pipeline, including the customary growth and replacement thereof. Trees, bushes, branches and roots may
be trimmed or removed so as not to interfere with Grantee's use of the easement area.
2. Access: Grantee shall have the right to enter on and across any of the Grantor’s property outside of the
easement area as may be reasonably necessary to gain access to the easement area and as may be reasonably
necessary for the construction, installation, operation, maintenance, inspection, removal or replacement of
the Grantee’s facilities.
3. Buildings or Other Structures: Grantor agrees that no structures will be erected in the easement area or in
such close proximity to Grantee's facilities as to create a violation of all applicable State of Wisconsin
electric and gas codes or any amendments thereto.
16
4. Elevation: Grantor agrees that the elevation of the ground surface existing as of the date of the initial
installation of Grantee's facilities within the easement area will not be altered by more than 4 inches without
the written consent of Grantee.
5. Restoration: Grantee agrees to restore or cause to have restored Grantor's land, as nearly as is reasonably
possible, to the condition existing prior to such entry by Grantee or its agents. This restoration, however,
does not apply to any trees, bushes, branches or roots which may interfere with Grantee's use of the
easement area.
6. Exercise of Rights: It is agreed that the complete exercise of the rights herein conveyed may be gradual
and not fully exercised until sometime in the future, and that none of the rights herein granted shall be lost
by non-use.
7. Binding on Future Parties: This grant of easement shall be binding upon and inure to the benefit of the
heirs, successors and assigns of all parties hereto.
8. Easement Review: Grantor acknowledges receipt of materials which describe Grantor’s rights and options
in the easement negotiation process and furthermore acknowledges that Grantor has had at least 5 days to
review this easement document or voluntarily waives the five day review period.
9. Limitations: This easement is subject to the following limitations because the “easement area,” described
above, is located upon, within, beneath, over and across part of an actively operating regional airport
established and managed jointly by political subdivisions of the State of Wisconsin, pursuant to authority
granted by the state under Wis. Stats., Chap. 114, and subject to regulation by several other state and federal
authorities:
a. Compliance with Federal Aviation Regulations and Security Requirements. Grantee’s access is subject
to Federal Aviation Regulations and Federal Airport Security Regulations, including but not limited to
49 CFR Parts 1540 and 1542, and 14 CFR Part 139., and the Grantor’s policies as outlined in Grantor’s
Federal Aviation Administration (FAA) approved Airport Certification Manual and the Transportation
Security Administration (TSA) approved Airport Security Plan. Grantee further agrees that any fines
levied upon the Grantor or Grantee through enforcement of these regulations because of acts by
Grantee's employees, agents, suppliers, guests, or patrons shall be borne by Grantee to the extent said
acts contributed to said fines.
b. Interference with Radio and Navigation Aids Prohibited. Grantor operates a varied spectrum of licensed
and unlicensed wireless radio, microwave and IP traffic to provide Navigation Aids and other critical
safety services to aircraft and personnel as well as other land-based vehicles and equipment. The stable,
reliable and economical delivery of these services has absolute priority over any other uses or operations
of the Grantee. Therefore, any interference experienced by Grantor that coincides with Grantee’s
activities will be presumed to be caused by the Grantee. Grantor reserves the right to demand the
Grantee turn off its equipment until all interference problems are resolved. Once a “shut-off” order is
delivered to the Grantee, Grantee’s equipment must be turned off as soon as possible. Grantee assumes
the risk of any interference and any costs, damages or claims that are a result of interference caused by
the Grantee will be the responsibility of the Grantee. Grantor also reserves the right to require the
Grantee to take any action necessary, in the sole discretion of Grantor, to proactively shield or otherwise
prevent Grantee’s activities from causing interference.
17
c. Rules and Regulations of Joint Airport Board. Grantor shall have the right to adopt from time to time,
and to enforce, rules and regulations which Grantee agrees to observe and obey with respect to the use
of the airport premises and appurtenances, provided that such rules and regulations shall not be
inconsistent with safety, current rules and regulations of the FAA and any future changes prescribed
from time to time by the FAA.
d. Protection of Aerial Approaches to Airport. Grantor reserves the right to take any action it considers
necessary to protect the aerial approaches of the airport against obstruction, together with the right to
prevent Grantee from erecting, or permitting to be erected, any building, any other structure, or
operating any vehicles or equipment on the easement area, which, in the opinion of the Grantor, would
limit the usefulness of the airport or constitute a hazard to aircraft, now or in the future.
e. Airport Development. Grantor reserves the right to increase the size or capacity of any public aircraft
facilities, including but not limited to, runways, hangars, taxi-ways, terminals, navigational facilities or
common use portions of the airport, or make alterations thereto or reconstruct or relocate them or
modify the design and type of construction thereof or close them or any portions of them, either
temporarily or permanently.
f. Force Majeure. Grantor shall not be responsible to Grantee if the fulfillment of any of the terms of this
Easement is delayed or prevented by revolutions or other civil disorders, wars, acts of enemies, strikes,
fires, floods, acts of God, adverse weather conditions, legally required environmental remedial actions,
or by any other cause not within the control of the Grantor.
[REMAINDER OF PAGE LEFT BLANK]
18
WITNESS the hand and seal of the Grantor the day and year first above written
Marathon County, Wisconsin
Organization name
Sign Name
Print name & title
Sign Name
Print name & title
STATE
OF
)
)SS
COUNTY
OF
)
This instrument was acknowledged before me this _______ day of ___________________, _______, by the
above-named_________________________________________________________ Marathon County,
Wisconsin, municipal corporations, to me known to be the Grantor(s) who executed the foregoing instrument
on behalf of said Grantor(s) and acknowledged the same
Sign Name
Print Name
Notary Public, State of
My Commission expires:
This instrument drafted by: Erica Pomerening
Wisconsin Public Service Corporation
REMS Entity ID WR Number Document ID REMS Formatted Number
1493310 WMIS-3457557 3342679 INT11-493-310
19
WITNESS the hand and seal of the Grantor the day and year first above written
Portage County, Wisconsin
Organization name
Sign Name
Print Name and Title
STATE
OF
)
)SS
COUNTY
OF
)
This instrument was acknowledged before me this _______ day of ___________________, _______, by the
above-named_________________________________________________________Portage County,
Wisconsin, municipal corporation, to me known to be the Grantor(s) who executed the foregoing instrument
on behalf of said Grantor(s) and acknowledged the same
Sign Name
Print Name
Notary Public, State of
My Commission expires:
This instrument drafted by: Erica Pomerening
Wisconsin Public Service Corporation
REMS Entity ID WR Number Document ID REMS Formatted Number
1493310 WMIS-3457557 3342679 INT11-493-310
20
Legend
THIS MAP IS NOT TO BE USED FOR NAVIGATIONNAD_1983_HARN_WISCRS_Marathon_County_Feet
Feet148.03
Notes
DISCLAIMER: The information and depictions herein are for informational purposes and Marathon County-City of Wausau specifically
disclaims accuracy in this reproduction and specifically admonishes and advises that if specific and precise accuracy is required, the same
should be determined by procurement of certified maps, surveys, plats, Flood Insurance Studies, or other official means. Marathon
County-City of Wausau will not be responsible for any damages which result from third party use of the information and depictions herein
or for use which ignores this warning.
0148.03
Road Names
Parcels
Parcel Lot Lines
Land Hooks
Section Lines/Numbers
Right Of Ways
Named Places
Municipalities
2020 Orthos Countywide
Red: Band_1
Green: Band_2
Blue: Band_3
**Temporary Exhibit **
**Final Exhibit will be sent for approval at a later date**
21
CENTRAL WISCONSIN AIRPORT STATISTICAL REPORT
SUMMARY - MARCH 2025 - 2026
09-Apr-26
2025 2026 % CHGE. 2025 2026 % CHGE.
MONTH MONTH 25-26 Y-T-D Y-T-D 25-26
ACTUAL LANDINGS
AMERICAN 60 60 0.0% 186 199 7.0%
DELTA 59 59 0.0% 184 181 -1.6%
CHARTERS 2 1 -50.0% 5 4 -20.0%
TOTAL OPERATIONS 242 240 -0.8% 750 768 2.4%
ATCT OPERATIONS 758 893 17.8% 2,189 2,586 18.1%
AIRLINE CANCELLATIONS
AMERICAN 3 8 0.0% 4 9 125.0%
DELTA 3 3 0.0% 3 3 0.0%
TOTAL CANCELLATIONS 6 11 83.3% 7 12 71.4%
ENPLANED PASSENGERS
AMERICAN 2,754 3,183 15.6% 7,534 10,025 33.1%
DELTA 3,366 3,207 -4.7% 9,969 10,429 4.6%
CHARTERS 229 183 -20.1% 568 556 -2.1%
TOTAL ENPLANED PASSENGERS 6,349 6,573 3.5% 18,071 21,010 16.3%
DEPLANED PASSENGERS
AMERICAN 2,644 2,888 9.2% 7,053 9,149 29.7%
DELTA 3,301 3,315 0.4% 9,201 9,934 8.0%
CHARTERS 229 183 -20.1% 568 556 -2.1%
TOTAL DEPLANED PASSENGERS 6,174 6,386 3.4% 16,822 19,639 16.7%
AIR FREIGHT - AMERICAN 5 0 -100.0% 5 212 4140.0%
AIR FREIGHT - DELTA 0 0 0.0% 0 0 0.0%
TOTAL AIRFREIGHT - AIRLINES 5 0 -100.0% 5 212 4140.0%
TOTAL AIRFREIGHT - GENERAL AVIATION 126,316 115,190 -8.8% 367,972 346,495 -5.8%
AIRLINES & GEN AVIATION - AIR FREIGHT 126,321 115,190 -8.8% 367,977 346,707 -5.8%
LOAD FACTOR-CURRENT MONTH SEATS PAX FACTOR
AMERICAN 3,998 3,183 79.6%
DELTA 4,256 3,207 75.4%
22
Central Wisconsin Airport – Flight Schedule
April 14, 2026
Arrivals – Delta
4982 15:37 from MSP CRJ-900
4934 21:00 from MSP CRJ-900
Departures – Delta
5384
07:00 to MSP CRJ-900
4982 16:17 to MSP CRJ-900
Arrivals – American
3557 13:43 from ORD E170
3556 18:02 from ORD E170
3350 23:48 from ORD E170
Departures – American
3346 05:40 to ORD
E170
3987 14:13 to ORD E170
3556 18:32 to ORD E170
Arrivals – United
Service begins June 1, 2026
Departures – United
Service begins June 1, 2026
MSP = Minneapolis
ORD = Chicago O’Hare
Total CWA Flights Daily = 5
Upcoming Charter Schedule
Apr. 14th – Sun Country to Caesar’s/Omaha
Apr. 20th – Sun Country to Riverside/Laughlin
May 4th – Never Forgotten Honor Flight
June 1st – Never Forgotten Honor Flight
23
FIN - Budget vs Actual for Organization
Company County of Marathon
Organization Cost Center: 53510 CWA Operations
Period FY2026 - March
Ledger Account Original Budget Actuals (Current Period) Actuals (YTD) Budget Remaining Budget Used (%)
Revenues
Federal Grants 0 0 0
Parking Fees 1,150,000 110,701 280,481
Airport Fees 2,373,000 201,757 619,308
Advertising 60,000 0 15,039
Local Departments 0 0 0
Interest on Investments 45,000 0 0
Property Sales 0 0 0
Other Miscellaneous Revenues 100,000 0 0
Transfer In from Other Funds 398,205 0 0
Gain/Loss Sales of Fixed Assets 490,000 0 0
Total Revenues 4,616,205 312,458 914,829 3,701,376 19.82%
Expenditures
Personnel 2,153,029 101,492 429,326 1,723,703 19.94%
Salaries and Wages 59,981 303,903
Employee Benefits 481 3,560
Employer Contributions 41,030 121,863
Contractual Services 966,500 30,928 170,829 795,671 17.68%
Professional Services 13,931 59,528
Utility Services 1,323 67,241
Repair and Maintenance Services - Other 2,147 9,558
Special Services IT 13,315 31,796
Other Contractual Services 213 2,706
Materials and Supplies 513,500 28,974 208,673 304,827 40.64%
Office Supplies 26 1,895
Publications, Subscriptions and Dues 3,000 12,546
Travel 250 1,660
Operating Supplies 176 4,197
Repair and Maintenance Supplies 22,583 51,261
Other Repairs and Maintenance Supplies 980 11,172
Other Supplies and Expense 1,960 125,943
Building Materials 38,000 0 163 37,837 0.43%
Metal Products 0 163
Wood Products 0 0
Raw Materials 0 0
Fabricated Materials 0 0
Fixed Charges 120,000 0 26,919 93,081 22.43%
Capital Outlay 380,000 0 6,923 373,077 1.82%
Debt Service 445,176 0 0 445,176 0.00%
Total Expenditures 4,616,205 161,394 842,833 3,773,372 18.26%
Net Change 151,064 71,996
24
2025-2026 CWA Budget Summary YTD - March
March YTD - 2026 March YTD - 2025 % CHANGE
Federal Grants $0 $8,248
State Grants - Other $0 $0
Parking Fees $280,481 $233,369
Airport Fees $619,308 $635,206
Other Charges for Services $15,039 $14,752
Other Local Governments $0 $0
Interest on Investments $0 $80,505
Property Sales $0 $18,872
Other Miscellaneous Revenues $0 $0
Total Revenues $914,828 $990,952 -7.68%
Personnel Services $429,326 $457,937
Contractual Services $170,829 $222,858
Supplies and Expense $208,673 $131,317
Building Materials $163 $219
Fixed Charges-Insurance $26,919 $24,080
Capital Outlay $6,923 $237,933
Total Expenses $842,833 $1,074,344 -21.55%
Revenue over Expense $71,995 -$83,392
25